Cabinet: 1. Agreed the outline amendments to the financial regulations as set out in paragraph 10 of this report: · Assistant Director(s) of Regeneration – delegated authority to make decisions involving spending up to £75k · Head of Levelling Up Project Delivery – delegated authority to make decisions involving spending up to £75k · Regeneration Project Managers – delegated authority to make decisions involving spending up to £50k 2. Noted the governance arrangements in place for the delivery of major time limited regeneration schemes.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1.1This report sets out the governance arrangements of delivery of major time limited projects. The Council currently has a number of the major projects are in receipt of time limited funding, in order to successfully deliver these projects we need to be able to make timely decisions to enable these projects to be delivered at pace and in line with the funding requirements set by Government. As part of our successful levelling up bids we have been asked to articulate our governance arrangements, these proposals outline our response. 1.2 In order to ensure that we can meet these requirements it is necessary to use single Cabinet member decisions and make minor revisions to the financial approval levels for staff within business growth and infrastructure. The report sets out the current constitutional arrangements which allow for single member Cabinet decision making and recommendations for minor changes to the scheme of delegation. 2.0 Recommendation(s)
2.1Agree the outline amendments to the financial regulations as set out in paragraph 10 of this report Assistant Director(s) of Regeneration – delegated authority to make decisions involving spending up to £75k
Head of Levelling Up Project Delivery – delegated authority to make decisions involving spending up to £75k
Regeneration Project Managers – delegated authority to make decisions involving spending up to £50k
2.2Note the governance arrangements in place for the delivery of major time limited regeneration schemes.
3.0Reasons for recommendation(s) To ensure and facilitate timely decision making as set out in the summary section of this report. 4.0 Alternative options considered and rejected
Keep existing governance arrangements in place. This was rejected, this matter has been considered in detail by the Regeneration Board and the service has set out a series of concerns if revisions are not made. The inability for project officers to process payments will lead to delays in the delivery of the project. Delays in decision making will have an overarching impact on the delivery of the projects with the timeframes set by Government. _________________________________________________________ Report Author and Contact Details:
Name: Marc Cole Position: Regeneration and Growth Specialist Department: BGI E-mail: [email removed]
Name: Jacqui Dennis Position: Director of Law & Democratic Services Department: Corporate Core Services E-mail: [email removed]
5.1To ensure robust governance arrangements for our complex strategic projects the Chief Executive has established a senior officer Regeneration Board. which he chairs. The terms of reference are appended to the report (see appendix 1). At the Board it was agreed that a review of the local authority’s existing scheme of delegation be undertaken to identify the potential changes needed, to facilitate the timely delivery of the various major regeneration projects falling within the Board’s remit.
5.2In bringing forward this report officers have drawn on the direct experience gained from the Mill Gate and Bury Market Flexi Hall, Radcliffe Town Centre and the Prestwich Town Centre regeneration projects, and the experience of other local authorities has formed the basis of a number of suggested minor changes to the existing scheme of delegation. It is proposed in line with the current constitutional arrangements there would be single Cabinet decision making.
6. Current issues with delivery arrangements
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.