Cabinet: 1. Approved the preferred option of a phased refurbishment of the Town Hall as the basis for a consultation with the public, staff and trade unions; 2. Requested that the Executive Director (Place) submit a further report to Cabinet in April 2023 on the outcome of the consultation process to coincide with a report recommending detailed terms for the transfer of the Council’s lease obligation for 3 Knowsley Place to Pennine Care NHS Foundation Trust; 3. Noted the intention to submit a detailed investment case for the refurbishment of the Town Hall to Cabinet by summer 2023; 4. Noted that, subject to satisfactory progress on the proposals to refurbish the Town Hall and the transfer the Council’s lease obligations for 3 Knowsley Place, options for the disposal of the Q Park roof site and Humphrey House will then be presented to Cabinet; 5. Noted the intention in the longer term to withdraw from the lease for 6 Knowsley Place subject to sufficient refurbished accommodation being made available at the Town Hall; and 6. Noted the findings of the Member Working Group on the future of the Town Hall as set out in the report in Part B of this agenda.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1.1This report presents the findings of a cross party Working Group established to look at the future of Bury Town Hall. The final report of the Group appears in a report in part B of this agenda, as it contains commercially confidential information relating to rental agreements .
1.2The condition of the Town Hall is such that the Council cannot continue occupation without making a clear decision on whether to invest in the building or seek to replace it.
1. 3. The Working Group considered options in the context of the Council’s wider administrative estate, in particular the office blocks at 3 and 6 Knowsley Place. The report also deals with the sites of Q Park roof and Humphrey House; decisions on both sites have been held back pending a decision on the Town Hall.
1.4The report presents a preferred option for the purposes of consultation. The preferred option is to undertake a phased refurbishment of the Town Hall. This will create higher quality office space in the Town Hall. It will also allow for a phased decant of staff from 3 Knowsley Place timed to align with the availability of newly refurbished space in the Town Hall. The preferred option will also create options for the Q Park roof and Humphrey House sites to be sold to enable further brownfield housing to be developed in the town centre.
1.5The viability of the plan has been enhanced by negotiations with Pennine Care NHS Foundation Trust with a proposal for the Trust to take over the lease of 3 Knowsley Place from the Council, but to enable the Council to retain occupancy of floors 3 and 4 until the phased refurbishment allows staff to move to the Town Hall.
1.6The proposals in the report will require capital investment into the Town Hall, which the Council owns, but will produce revenue savings by withdrawing from commercial leases and further knock-on savings from operating a smaller more compact estate and reduced energy costs.
Recommendation(s)
That subject to the approval of the recommendation appearing elsewhere on this agenda that the Council approve heads of terms for the transfer of its lease for 3 Knowsley Place to Pennine Care NHS Foundation Trust: (1) Cabinet approves the preferred option of a phased refurbishment of the Town Hall as the basis for a consultation with the public, staff and trade unions.
(2) That the Executive Director (Place) be requested to submit a further report to Cabinet in April 2023 on the outcome of the consultation process to coincide with a report recommending detailed terms for the transfer of the Council’s lease obligation for 3 Knowsley Place to Pennine Care NHS Foundation Trust.
(3) That Cabinet note the intention to submit a detailed investment case for the refurbishment of the Town Hall to Cabinet by summer 2023.
(4) That Cabinet note that, subject to satisfactory progress on the proposals to refurbish the Town Hall and the transfer the Council’s lease obligations for 3 Knowsley Place, options for the disposal of the Q Park roof site and Humphrey House will then be presented to Cabinet.
(5) That Cabinet note the intention in the longer term to withdraw from the lease for 6 Knowsley Place subject to sufficient refurbished accommodation being made available at the Town Hall.
(6) That Cabinet note the findings of the Member Working Group on the future of the Town Hall as set out in the report in Part B of this agenda.
3. Reasons for recommendation(s)
3.1The recommendations to commission a phased refurbishment of the Town Hall and to withdraw from leased premises at 3 and 6 Knowsley Place are the most cost-effective way of continuing to provide accommodation for the Borough’s civic and democratic functions and suitable space for the Council’s administrative staff.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.