Simister Island Development Consent Order

Decided Executive 2 papers

Cabinet decided this item on Wednesday 14 February 2024. Below is the council's own wording, with the papers it was decided on.

ItemCA.129

Resolved

Cabinet delegated authority to the Executive Director (Growth), in consultation with the Monitoring Officer and Cabinet Member for Strategic Growth, to respond to all consultations and engagement as part of the Simister Island Development Consent Order application process.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

M60 junction 18 Simister Island interchange Preferred route announcement

January 2021 M60 junction 18 Simister Island interchange

Introduction At Highways England we believe in a connected country and our network makes these connections happen. We strive to improve our major roads and motorways - engineering the future to keep people moving today and moving better tomorrow. We want to make sure all our major roads are more dependable, durable and, most importantly, safe.

In the north-west, we are investing in ways to increase capacity and improve connections to make sure your journeys are as reliable as possible.

The M60 junction 18 Simister Island interchange scheme is a critical part of this investment, supporting economic growth by better connecting major cities across the north of England. The scheme is vital in reducing congestion for the future, reducing safety risks, improving journey time reliability for all road users and increasing connectivity between local areas.

Why is the Scheme objectives scheme needed? The main objectives of the scheme are:

Simister Island interchange between the M62, „ To improve the journey experience for users M60 and M66, is one of the busiest motorway of this section of network by: junctions in the north-west, used by around ƒ reducing peak congestion and providing 90,000 vehicles each day. The junction faster average speeds struggles with high volumes of traffic, far ƒ reducing journey times above what it was designed for, and as a result ƒ delivering more reliable journey times suffers from congestion and poor journey time reliability. „ To provide an option which is safe for all road users „ To minimise the impact of our option on the surrounding environment including within Noise Important Areas and Air Quality Management Areas „ To facilitate future economic growth across the Greater Manchester area and support the proposals in the regional and local authorities’ transport strategies and Local Plans

2 Preferred route announcement

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Simister Island Development Consent Order: Appendix 1Decisions 976 KB DownloadRead as text
PDF
Simister Island Development Consent OrderDecisions 395 KB Download

At this meeting

Whole meeting

Who was there

8 of 17 attended
EO
Councillor Eamonn O'BrienChair, present
NB
Councillor Nathan BorodaCommittee Member, present
CC
Councillor Clare CumminsCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
TR
Councillor Tahir RafiqCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
LR
Lynne RidsdaleOfficer, in attendance
JD
Jacqui DennisOfficer, in attendance
PM
Paul McKevittOfficer, in attendance
PB
Philippa BraithwaiteOfficer, in attendance

All 17 on the meeting page

On this subject at Bury

Search all
  1. Simister Island Development Consent OrderThis decision
  2. Simister Island Development Consent OrderDecided

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies