DECISION 1. Cabinet notes the progress of the ALPD to date. 2. Cabinet notes the Future Assets Programme and implications for disposal. 3. Cabinet approves the withdrawal of property assets for disposal set out in paragraph 20 below from the ALPD. 4. Cabinet approves the classification of property assets detailed at paragraph 21 below as surplus and to add to the ALPD property assets set out in Appendix 2. 5. Cabinet approves delegated authority to the Head of Land and Property to determine and agree terms for the sale of property assets in consultation with the s151 Officer, the Monitoring Officer, and the Exec Director (Place). 6. Cabinet approves the disposal of Spurr House, Pole, Unsworth. 7. Cabinet approves the establishment of the ATP (Asset Transformation Programme) to replace the ALPD. 8. Cabinet Notes the removal of North Block, Radcliffe from the proposed disposal sites, pending further consultation with Elected Members.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1. This report provides an update in relation to the progress of the Council’s Accelerated Land and Property Disposals Programme (ALPD) which has been in operation following Cabinet approval on 24 th November 2020. This report provides a rationale as to why some sites are to be withdrawn, under review and to be added to the programme and outlines the Future Assets Programme (FAP) with regards to disposals.
2. Further this report seeks approval for the disposal of Spurr House, Pole Lane, Unsworth.
3. Proposes a new programme to encompass the ALPD and Future Asset Programme (FAP),(disposals only) to be known as the Asset Transformation Programme (ATP)
4. Three phases of land and building assets (hereafter referred to as property assets) have been approved for disposal by Cabinet on 24th March 2021, 30th June 2021 and 13th October 2021 with an update provided to Cabinet on 9 March 2022. Subsequent to that permission to dispose of some sites have been undertaken following individual reports to Cabinet
5. Led by the Land and Property team, a team of officers have been making steady progress on preparing and disposing of the smaller property assets, alongside other key officers from across the Business, Growth and Infrastructure (BGI) Department focusing on the larger, more strategic Council-owned property assets.
6. Preparing some of the property assets for disposal that are classed as open space have resulted in challenges and objections from residents through the Public Open Space advertising procedure that is statutorily required by law which has resulted in the property assets being removed from the ALPD.
7. As noted in the Phase 3 Cabinet paper (13 th October 2021), the Council does reserve the right not to dispose of a property asset, should it be determined following review that it should be retained. Further development of the ALPD has identified the potential need to retain property assets for short-term use and several property assets to remain within the ownership of the Council, as alternative uses have been identified that supports other Council strategies.
Recommendation(s)
8. To note the progress of the ALPD to date.
9. To note the Future Assets Programme and implications for disposal.
10. To approve to the withdrawal of property assets for disposal set out in paragraph 20 below from the ALPD
11. To approve the classification of property assets detailed at paragraph 21 below as surplus and to add to the ALPD property assets set out in Appendix 2.
12. To approve delegated authority to the Head of Land and Property to determine and agree terms for the sale of property assets in consultation with the s151 Officer, the Monitoring Officer, and the Exec Director (Place)
13. To approve the disposal of Spurr House, Pole, Unsworth.
14. To approve the establishment of the ATP (Asset Transformation Programme) to replace the ALPD. Reasons for recommendation(s) 15. To be apprised of the progress of the ALPD and other disposals to date.
16. To make best use of the Council’s property assets. Disposing of property assets to reduce holding costs, reduce the Councils' carbon footprint and to generate capital receipts.
17. To enable the Council to continue to generate capital receipts that can enable other Council projects to be supported.
18. To bring together all the property asset disposals within one programme Alternative options considered and rejected
19. No other options were considered / were applicable _________________________________________________________ Report Author and Contact Details: Name: Roger Frith Position: Head of Land & Property Department: BGI (Business Growth and Infrastructure) E-mail: [email protected] ___________________________________________________ Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.