CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bury Metropolitan Borough Council
Cabinet, Thursday 15 January 2026 at 6.00pm

Procurement for Highways framework under the Procurement Act 2023

Approved Executive 1 paper

AI summaryBury Cabinet approves re-procurement of a Highways framework worth around £60 million, with the new tender due to close by July 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet gave approval to begin the tender exercise
Moneycirca £60 millionProjected framework spend over the term
What happens nextTender concludes June to July 2026Then a Cabinet Award Report is presented
Who it affectsHighways services, suppliers and residentsCovers maintenance, surface dressing, civils, structures

What was decided

Cabinet approved proceeding with the re-procurement of the Highways framework under the Procurement Act 2023. Report P3

Why

The re-procurement is needed to meet statutory duties under the Procurement Act 2023 and the Highways Act 1980, and to continue delivering highways works. Report P3, P12, P14

Officers said the existing framework has been an effective way to deliver planned and reactive highways work. Report P4

What happens next

Procurement and Highways officers will review direct awards and other framework options during the tender to maintain service continuity. Report P5

The tender is scheduled to conclude in June or July 2026, after which a further Cabinet report with an Award Report will be brought back for approval to award the framework. Report P3

The money

  • circa £60 million Projected estimated spend of the new framework over its term, subject to available budgets and capital plans Report P3
  • 1% Minimum management fee typically charged by external framework providers Report P4
  • approximately £600,000 Cost the Council would avoid by not using external framework providers, calculated on the projected £60 million value Report P4

Options considered

  • Chosen: Run the re-procurement directly through the Council. Avoids paying a minimum 1% management fee to an external framework provider, estimated at about £600,000 on a £60 million value, and keeps compliance with the Procurement Act 2023 Report P3, P4
  • Rejected: Use external frameworks to source Bury's highways requirements. Framework providers typically charge a minimum 1% management fee, costing around £600,000 on a projected value of £60 million Report P4

Implications

  • Legal: The re-procurement will be conducted in accordance with the Procurement Act 2023 and supports the Council's Highways Act 1980 duties. Legal services will be consulted on any terms and conditions queries. Report P12, P14
  • Financial: Costs of the procurement exercise will be met from existing budget provision and the capital programme, with actual framework spend dependent on available budgets, capital investment plans and any additional funding during the term. Report P3, P15
  • Risk: Failing to re-procure would hinder the Council in meeting its highways maintenance duties, delay capital investment and compromise maintenance. The project will comply with the Procurement Act and progress will be reported through highlight reports to mitigate challenge from suppliers. Report P12, P13
  • Equalities: Officers do not expect any changes that would have equality impacts from this activity. Report P8
  • Climate: Environmental impact and considerations are recorded as not applicable. Report P9, P10

Who and where

  • Highways department and Council staff delivering maintenance, surface dressing, major civils and highway structures Report P3, P4, P5
  • Existing and prospective framework suppliers, with a stated emphasis on SME participation Report P3, P6
  • Borough residents and road users who rely on highways maintenance and active travel and sustainable transport schemes Report P7, P12
  • The Interim Head of Procurement as report author, with procurement and legal services supporting the exercise Report P4, P14

Timeline

  • December 2025: Planned Procurement Notice published to inform the market of the upcoming tender Report P3
  • 15 January 2026: Cabinet considered and approved the re-procurement Report P2
  • June to July 2026: Procurement process scheduled to conclude Report P3
  • After conclusion of procurement: A further Cabinet report accompanied by an Award Report will be presented to seek approval for awarding the framework Report P3

Plain English for the jargon

  • SME: Small and Medium-sized Enterprises
  • Procurement Act 2023: A UK law that came into effect in February 2025, replacing previous EU-derived procurement regulations. It aims to simplify, modernise and improve transparency in public procurement while promoting fair competition and social value.
  • Framework: A contract between a contracting authority and one or more suppliers that provides for the future award of contracts by the authority to those suppliers
  • Planned Procurement Notice: An optional pre-procurement notice giving advance information to the market about an upcoming procurement, helping suppliers prepare and potentially allowing shorter minimum tendering periods
  • Lot: A separately tendered portion of the framework covering a specific discipline, such as maintenance, surface dressing, major civils or highway structures
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.107

Resolved

Cabinet: 1. Approved to precede with the re-procurement exercise Reasons for recommendation(s): To maintain compliance with statutory obligations of the Procurement Act 2023. Alternative options considered and rejected: Use Frameworks to source Bury’s requirements Rejected: Framework providers typically apply a minimum 1% management fee. On a projected framework value of £60 million, this would amount to approximately £600,000, a cost the Council would avoid by delivering the framework directly.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Classification: Decision Type: Open Key

Report to: Cabinet Date: 15 January 2026 Subject: Procurement for Highways framework under the Procurement Act 2023 Report of Cabinet Member for Environment, Climate Change and Operations

Summary This report seeks Cabinet approval to proceed with the re-procurement of a Highways framework in compliance with the Procurement Act 2023. The framework will be structured into several Lots covering all highways related works including as a minimum maintenance, surface dressing, major civils, highway structures with multiple suppliers per Lot to maintain works continuity The Framework is projected to have an estimated spend of circa £60 million though actual expenditure will depend on available budgets, capital investment plans and any additional funding during the framework term. The framework will have a greater emphasis on social value outcomes and SME participation. The Procurement process commenced December 2025 with the publication of a Planned Procurement Notice to inform the market of the upcoming tender. The procurement is scheduled to be concluded June-July 2026. Following this, a subsequent Cabinet report accompanied by an Award Report providing a full audit on the tender process will be presented to seek approval for awarding the framework. Recommendation(s) Cabinet is requested to approve to precede with the re-procurement exercise Reasons for recommendation(s) To maintain compliance with statutory obligations of the Procurement Act 2023. Alternative options considered and rejected 1. Use Frameworks to source Bury’s requirements

Rejected: Framework providers typically apply a minimum 1% management fee. On a projected framework value of £60 million, this would amount to approximately £600,000, a cost the Council would avoid by delivering the framework directly. _________________________________________________________ Authors and Contact Details: Name: Kevin Fletcher Position: Interim Head of Procurement Department: Corporate Core E-mail: [email protected] ________________________________________________________________ Background The existing Highways Framework has successfully supported the delivery of highways related services across multiple Lots, including Minor Civils and Highway Structures. It has proven to be an effective mechanism for delivering both planned and reactive works efficiently, leveraging established suppliers and robust performance monitoring processes.

During the tender process, procurement will work with Highways department to review direct awards/options via frameworks where appropriate to deliver compliance and maintain service continuity.

The new framework will broaden its scope to include additional disciplines/Lots and place greater emphasis on social value outcomes and SME participation.

________________________________________________________________ Links with the Corporate Priorities: 1. Enterprise – The re-procurement of a new framework will assist the Council in achieving its best value obligations under the Local Government Act 1999. 2. Place and Community – Maintaining continuity of highways services supports safe, accessible, and resilient communities, underpins economic growth, and enables delivery of active travel and sustainable transport schemes across the borough.

Equality Impact and Considerations: 3. There are not likely to be any changes that have equality impacts as a result of this activity.

Environmental Impact and Considerations:

4. Not applicable

Assessment and Mitigation of Risk: Risk / opportunity Mitigation

The Council is required to meet its statutory Failing to re-procure would hinder the highways maintenance implications under the Council in fulfilling its statutory Highways Act 1980. obligations, delay highway capital investment deadlines, and compromise highways maintenance, negatively impacting highway users in Bury.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement for Highways framework under the Procurement Act 2023Decisions 133 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 17 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 17 on the meeting page

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies