Bury Metropolitan Borough Council
Cabinet, Wednesday 11 February 2026 at 6.00pm

In-house delivery of Biodiversity Net Gain on Council-owned land - Part A

Noted Executive 3 papers

AI summaryBury Cabinet approves in-house delivery of Biodiversity Net Gain on six Council-owned sites, starting with pilot sites at Hollins Mount and Chesham, to sell biodiversity units to developers.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedSix Council-owned receptor sites authorised for registration
MoneyInitial costs funded from reservesExpected recovered within three years through unit sales
What happens nextSubmit pilot sites to Defra registerHollins Mount and Chesham, then a third site in 2027-28
Who it affectsDevelopers needing off-site BNG in BuryAnd Council greenspace management in the Borough

What was decided

Cabinet authorised officers to prepare six Council-owned sites, sign a 30-year legal agreement, enter a three-year GMCA Responsible Body service, and submit sites to Defra's biodiversity gain site register. Report P6, P8, P10, P11

Cabinet noted the intention to initially submit two pilot receptor sites, Hollins Mount and Chesham, subject to legal agreement with GMCA. Report P12, P51, P52

Cabinet approved in-house self-management and up-front investment, and authorised the Director of Finance to ringfence income from biodiversity unit sales to cover 30-year management, maintenance and any profits for other nature projects. Report P13, 2.2

Why

To keep the benefits of biodiversity net gain from Bury's development within the Borough rather than losing them regionally or nationally. Report P16

To improve management of, and maximise investment in, Council-owned greenspace and deliver the statutory 10% BNG requirement introduced in 2024. Report P17, 1.1, 5.1

To enable any surpluses or profits to support resourcing and other nature projects under the Bury Biodiversity Strategy. Report P18, P81

What happens next

Officers will prepare the six sites, secure a 30-year legal agreement, commission the GMCA Responsible Body service, and submit sites to Defra for inclusion on the biodiversity gain site register. Report P6, P8, P10, P11

Two pilot sites, Hollins Mount and Chesham, will be submitted first, with a third site to follow in 2027-28, and the remaining four sites subject to market demand. Report 10.1, 8.4, P51, P52, P53, P54, P55, P56

Income from unit sales will be ringfenced by the Director of Finance to cover 30-year management, maintenance and to support other nature-related projects across the Borough. Report 2.2, P96

The money

  • 275 off-site biodiversity units Estimated need in Bury from Places for Everyone allocations Report P45
  • 391 units Total units the six Council-owned sites could collectively accommodate Report 8.5, P73
  • c.133 units Units the two pilot sites (Hollins Mount and Chesham) could deliver to the market Report 8.5

Options considered

  • Chosen: In-house delivery using GMCA Responsible Body service and Defra registration of six Council-owned sites. Secures BNG benefits locally, improves greenspace management, allows reinvestment of profits in nature projects, and supports statutory BNG delivery. Report P15, P16, P17, P18, P19
  • Rejected: Take no action and not provide receptor sites in Bury. Developers would deliver off-site BNG outside the Borough, so Bury would lose biodiversity enhancements and investment in its own land. Report 4.1, 4.2, 10.5

Implications

  • Financial: Initial up-front costs will be funded from reserves and the business case assumes recovery within three financial years through biodiversity unit sales, with no pressure on the revenue budget or medium term financial strategy thereafter. Report P13, P96
  • Legal: Sites must be legally secured for at least 30 years via a conservation covenant with a Defra-designated responsible body or a Section 106 agreement; registered sites will be restricted to biodiversity enhancement use and cannot be disposed of without formal deregistration. Report P91, P92, P93, 9.1
  • Risk: The Council takes on legal liability and risk for delivering BNG over 30 years, with potential external enforcement action including remediation notices, injunctions and financial penalties for non-compliance, and conflicts of interest arising from its dual role as landowner and local planning authority. Report 10.4, P91, P94
  • Equalities: An Equality Impact Assessment found no likely equalities impacts from this activity. Report P83
  • Climate: The approach supports the Government's target to halt biodiversity decline by 2030 and the Council's Carbon Neutrality by 2038 commitment, alongside Local Nature Recovery Strategies. Report 5.3, P80, P85
  • Staffing: A dedicated resource will be required to track and manage BNG delivery in the Borough as the work matures. Report P13, 10.3

Who and where

  • Developers in Bury needing to meet the statutory 10% biodiversity net gain requirement Report 1.1, 5.1, 6.1
  • Six Council-owned sites: Hollins Mount, Chesham, Springwater Park, Outwood, Old Kay's Park and Philips Park Report P51, P52, P53, P54, P55, P56
  • Greater Manchester Combined Authority as Defra-designated Responsible Body Report 1.2, 9.2, P8
  • Greater Manchester Ecology Unit which produced the Needs and Supply Assessment Report 8.1, 8.2, P48
  • Borough residents and greenspace users benefiting from enhanced management of Council land Report P17, P81

Timeline

  • 2024: Government introduced mandatory 10% biodiversity net gain requirement for new development needing planning permission. Report 1.1, 5.1
  • January 2025: Cabinet approved use of six Council-owned sites for BNG subject to legal agreements and Defra registration. Report 1.2
  • 2026-02-11: Cabinet approved in-house delivery and the GMCA Responsible Body service for an initial three-year subscription. Report 9.2, 10.1
  • 2026/27: Hollins Mount Farm projected to deliver 79 units, Chesham Woods 54 units, totalling 133 units from the two pilot sites. Report 8.5, P72, P73
  • 2026-2028: Bury aims to secure three BNG receptor sites over the three-year period, with the ultimate intention of delivering all six. Report 10.1, P72, P73
  • 30 years: Legal minimum period for which biodiversity units and habitat management must be secured on registered sites. Report 7.2, P91

Plain English for the jargon

  • Biodiversity Net Gain (BNG): A mandatory requirement for new development to deliver a 10% net gain in biodiversity value from the pre-development state.
  • Receptor sites: Off-site locations registered with Defra where biodiversity units can be delivered to compensate for losses elsewhere.
  • Biodiversity unit: A unit of measurement quantifying the biodiversity value of a site; also called a biodiversity credit.
  • Statutory Biodiversity Metric: The Defra calculator tool used to calculate biodiversity value for BNG purposes.
  • Responsible Body: An organisation designated by Defra to create and enforce legally-binding conservation covenants on off-site BNG providers.
  • Conservation covenant: A legally binding agreement to conserve the natural features of land, made with a Defra-designated responsible body.
  • Section 106 Agreement (S106): A planning obligation under the Town and Country Planning Act 1990, used here as the alternative legal mechanism to secure BNG sites.
  • Defra: Department for Environment, Food and Rural Affairs, which maintains the national Biodiversity Gain Site Register.
  • GMCA: Greater Manchester Combined Authority, granted Responsible Body status by Defra.
  • LNRS: Local Nature Recovery Strategy, identifying opportunities for habitat creation and restoration.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.127

Resolved

Decision Cabinet: Noted the opportunities identified in relation to in-house delivery of BNG on Council owned land. For the six Council-owned receptor sites, authorised the Executive Director of Place, Head of Property and Director of Law and Governance, in consultation with the relevant portfolio holders to: engage in works to prepare the sites for delivery; enter into an agreement with the GMCA for the commissioning of the GMCA Responsible Body service, and agree to use the service for a period of three years; sign a legal agreement securing the sites for 30 years, if terms can be agreed; and d) submit the sites to the Department for Environment, Food & Rural Affairs for inclusion on their register of biodiversity gain sites to enable the Council to advertise the units for sale. Noted the intention to initially submit two pilot receptor sites at Hollins Mount and Chesham (if legally secured with GMCA) to the Department for Environment, Food & 4. Rural Affairs for inclusion on their register of biodiversity gain sites; Approved the in-house self-management of the sites and authorise up-front investment required to bring these sites to market, recognising that this work will require a dedicated resource to track and manage the delivery of Biodiversity Net Gain in the Borough; and Authorised the Director of Finance to ringfence income from Biodiversity Unit sales to cover 30-year management and, maintenance costs along with any profits to support resourcing demands and, where relevant, implement other nature related projects across the Borough in accordance with the Bury Biodiversity Strategy. Reasons for decisions: To help ensure that the benefits of biodiversity net gain from development in the Borough are secured locally, as opposed to regionally or nationally. To improve management of, and maximise investment in, Council-owned greenspace. To have the ability to redirect any surpluses/profits to support the growth of resources to implement other nature related projects across the Borough. To support and facilitate the delivery of development in Bury which meets the statutory BNG requirements. Alternative options considered and rejected: · To take no action. The lack of opportunities for developers to deliver off-site BNG within Bury is likely to result in developers delivering this outside of the Borough meaning that Bury would not benefit from biodiversity enhancements. · Furthermore, the Council would lose the opportunity to secure investment in and enhancement of its land.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

1.1In 2024, the government introduced a mandatory requirement for new development requiring planning permission to deliver a 10% net gain in biodiversity value. To deliver this 10% biodiversity net gain (BNG), developers must firstly look to achieve this on-site, but if this cannot be achieved, they can provide BNG on sites elsewhere that have been formally registered as such with the Department for Environment, Food and Rural Affairs (Defra).

1.2In January 20251, Cabinet approved the use of six Council-owned sites for Biodiversity Net Gain subject to legal agreements and registration with Defra. This report sets out how these receptor sites can be brought forward through in-house delivery now that the options available to the Council have evolved following Defra’s grant of Responsible Body status to Greater Manchester Combined Authority (GMCA).

2. Recommendation(s)

2.1That Cabinet:

 Note the opportunities identified in relation to in-house delivery of BNG on Council-owned land.

 For the six Council-owned receptor sites, authorise the Executive Director of Place, Head of Property and Director of Law and Governance, in consultation with the relevant portfolio holders to:

a) engage in works to prepare the sites for delivery;

b) enter into an agreement with the GMCA for the commissioning of the GMCA Responsible Body service, and agree to use the service for a period of three years;

1 https://councildecisions.bury.gov.uk/documents/s42592/Draft%20Cabinet%20Report%20Receptor%20Sites.p

df c) sign a legal agreement securing the sites for 30 years, if terms can be agreed; and

d) submit the sites to the Department for Environment, Food & Rural Affairs for inclusion on their register of biodiversity gain sites to enable the Council to advertise the units for sale.

 Note the intention to initially submit two pilot receptor sites at Hollins Mount and Chesham (if legally secured with GMCA) to the Department for Environment, Food & Rural Affairs for inclusion on their register of biodiversity gain sites;

 Approve the in-house self-management of the sites and authorise up-front investment required to bring these sites to market, recognising that this work will require a dedicated resource to track and manage the delivery of Biodiversity Net Gain in the Borough; and

2.2Authorise the Director of Finance to ringfence income from Biodiversity Unit sales to cover 30-year management and , maintenancecosts along with any profits to support resourcing demands and, where relevant, implement other nature related projects across the Borough in accordance with the Bury Biodiversity Strategy.

3. Reasons for recommendation(s)

 To help ensure that the benefits of biodiversity net gain from development in the Borough are secured locally, as opposed to regionally or nationally.

 To improve management of, and maximise investment in, Council-owned greenspace.

 To have the ability to redirect any surpluses/profits to support the growth of resources to implement other nature related projects across the Borough.

 To support and facilitate the delivery of development in Bury which meets the statutory BNG requirements.

4. Alternative options considered and rejected

4.1To take no action. The lack of opportunities for developers to deliver off-site BNG within Bury is likely to result in developers delivering this outside of the Borough meaning that Bury would not benefit from biodiversity enhancements.

4.2Furthermore, the Council would lose the opportunity to secure investment in and enhancement of its land.

_________________________________________________________ Report Author and Contact Details:

Name: David Wiggins

Position: Service Manager: Strategic Planning and Infrastructure

Department: Place

E-mail: [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
In-house delivery of Biodiversity Net Gain on Council-owned land: Part ADecisions 534 KB DownloadRead as text
PDF
PART A Appendix A: Map of potential Council-owned BNG receptor sitesDecisions 6.7 MB Download
PDF
PART A Appendix C Background information GMCA BNG Responsible Body ServiceDecisions 393 KB Download

At this meeting

Whole meeting

Who was there

9 of 18 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 18 on the meeting page

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies