Key Decision - Procurement of CCTV Maintenance Contract
RefusedScrutiny1 paper
Strategy and Resources Scrutiny Committee refused this item on Monday 29 March 2010. Below is the council's own wording, with the papers it was decided on.
To consider the mechanism for awarding a contract for the maintenance of CCTV systems in conjunction with other local authorities. Decision of Executive Councillor: The Leader of the Council authorised the Director of City Services to; · Tender, and in consultation with the Director of Finance and Head of Legal Services award a contract for up to five years for the maintenance of the city’s CCTV system. · Negotiate with other local authorities within Cambridgeshire involving CCTV provision and St Edmundsbury Borough Council to undertake a joint procurement of services and inclusion within the tender document. Reason for the As set out in the officer’s report. Any alternative options considered and rejected: N/A Scrutiny Considerations: The Director of City Services introduced the report. The Scrutiny Committee considered the report and accepted the recommendation by 7 votes to 0. Conflicts of interest declared by the Executive Councillor (and any dispensations granted): None
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Executive summary
1.1The current maintenance contract for the Council’s CCTV system costs £75k per annum. As part of a continuous review of the CCTV system with the objective of delivering a high quality service which is affordable. It is felt that a similar quality of maintenance may be deliverable at a lower cost to the Council.
Recommendations
2.1The Executive Councillor is recommended:
To authorise the Director of City Services to:-
• Tender and, in consultation with the Director of Finance and Head of Legal Services, award a contract for up to five years for the maintenance of the city’s CCTV system.
• Negotiate with other local authorities within Cambridgeshire involving CCTV provision and St Edmundsbury Borough Council to undertake a joint procurement of services and inclusion within the tender document.
Background
3.1The current maintenance contract for the Council’s 127 fixed location Public Space CCTV cameras and the CCTV Control Room equipment is currently £75k per annum and expires at the end of March 2010. This will be extended for up to 6 months from 1st April until 30th September 2010 at a cost 0f £37.6k.
3.2The current contract is of high quality, but it is hoped to deliver the same standard of service at a lower cost, through a collaborative procurement project with a
Report Page No: 1 number of potential partner organisations in Cambridgeshire and St Edmundsbury Borough Council.
3.3The target date for having the new maintenance contract in place will be 1st October 2010 with a view of achieving approximately £20k savings per annum on the costs of CCTV maintenance.
3.4The total cost of a 5 year contract would be approximately £275k and is therefore over the EU procurement threshold making this project an OJEU level procurement process with or without partners. This will be a restricted procedure.
4. Implications
4.1As the project is over the EU threshold it is our intention to engage an agent to act on our behalf to steer this contract through the process.
4.2Capital costs for using an agent to setting up a new contract will be about £5k shared equally between partners with Cambridge City Council’s share being met from the existing CCTV budget.
4.3Costs for implementing a new maintenance contract will be met from existing CCTV budgets.
5. Background papers Current Maintenance Contract CCTV Maintenance Contract Project Papers These background papers were used in the preparation of this report:
6. Appendices None
7. Inspection of papers
To inspect the background papers or if you have a query on the report please contact:
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.