To consider the project appraisal and procurement report for the vehicle replacement programme 2010/11 Decision of Executive Councillor: · Approved the 2010/11 Vehicle Replacement Programme (PR017) with £397,000 additional funding. The capital cost of the items identified for replacement totals £1,103,000, to be funded from R&R funds held at City Services. There are no additional revenue costs associated with the replacement vehicles. · Approved the carrying out and completion of the procurement of the Vehicle Replacement Programme. If the quotation or tender sum exceeds the estimated contract value by more than 15% the permission of the Executive Councillor and Director of Finance will be sought prior to proceeding. Reason for the As set out in the officer’s report. Any alternative options considered and rejected: N/A Scrutiny Considerations: The Director of City Services confirmed that the funding (£397k) was already approved but the request was to accelerate the replacement a year earlier than planned of a number of vehicles with high revenue and maintenance costs. The Scrutiny Committee considered and approved the recommendations by 7 votes to 0. Conflicts of interest declared by the Executive Councillor (and any dispensations granted): None
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Capital Project Appraisal & Procurement Report
Project Title Vehicle replacements 2010/11
Target Start Date 1st April 2010
Target Completion Date 31st March 2011
Project Manager / Lead Officer David Cox
Scrutiny Committee and Portfolio Strategy and Resources Scrutiny Committee
Scrutiny Committee Date 29 March 2010
1 Recommendation/s
Financial recommendations - The Executive Councillor is asked to approve the 2010/11 Vehicle Replacement Programme (PR017) with £397,000 additional funding. The capital cost of the items identified for replacement totals £1,103,000, to be funded from R&R funds held at City Services. There are no additional revenue costs associated with the replacement vehicles.
Procurement recommendations – The Executive Councillor is asked to approve the carrying out and completion of the procurement of the Vehicle Replacement Programme. If the quotation or tender sum exceeds the estimated contract value by more than 15% the permission of the Executive Councillor and Director of Finance will be sought prior to proceeding.
2 What is the project? Provide a description of the proposed project, justify the reason for the project, and note what alternative options were considered.
This project is the 2010/11 schedule of the rolling programme for the replacement of the City Services fleet, which is funded by R&R contributions. All vehicles are given a set life of six or seven years (six for light commercial vehicles and seven for heavy commercial vehicles) and at the end of this period they are replaced for new. On some occasions vehicles are replaced early if maintenance costs are unsustainable and there are sufficient funds to replace it.
Page 1 of 10 3 Outline the aims and objectives of the project and highlight how it contributes to achieving the Council’s Medium Term Objectives.
This project contributes towards the MTO: Promote Cambridge as a sustainable city, in particular by reducing Carbon dioxide emissions.
The replacement of the vehicles will lead to cutting the carbon footprint of the Council’s fleet of vehicles, due to greater fuel efficiency. The engines in the old vehicles that are to be replaced are all Euro II and III emission compliant. The new vehicles will all be Euro IV (light commercial) and Euro V (heavy commercial) compliant.
Euro IV emission standard led to a legal requirement of 50% reductions in oxides of nitrogen (NOx) and 40% reductions in particulates compared to Euro III levels.
Euro V emission standard lowered the limits even further with another reduction of 55% of nitrogen oxide (NOx).
4 Identify and summarise the impact on and major issues for stakeholders & other departments. Summarise the key results of initial consultation (including members where appropriate).
The main impact is financial, particularly in Waste Management but also in all other departments to a lesser scale. New vehicles cost significantly less to maintain than the ones they replace, therefore a lesser burden on revenue budgets. Refuse collection vehicles, by their nature, are expensive to maintain with a six-year-old vehicle typically costing up to £18K per year. New RCVs, by comparison, cost on average £5K per year, therefore revenue savings of £13K per vehicle can be achieved, however these assumed savings are based on a calendar year not a financial year and the delivery date of the new vehicle will dictate the actual savings achieved. A delivery date six months into the financial year therefore would only deliver 50% of the above claimed savings. Although these revenue savings were not offered in the last budget round for 2010/11, they would have a positive impact on the vehicle maintenance budgets for 2011/12.
There are six RCVs on the replacement list and one large sweeper below; therefore this could lead to potential revenue savings of £90K in Waste Management and £36K in StreetScene.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.