A Climate Change Fund with an initial investment of £250,000 was agreed at Council on 21 February 2008 to be used to provide funding for schemes or activities which will contribute to the achievement of the Council’s climate change and carbon reduction Medium Term Objective. Detailed operational guidelines for management of the fund were agreed at Environment Scrutiny Committee in July 2007, which included a requirement for the total expenditure and achievements of the fund to be reported to Environment Scrutiny Committee annually. This report constitutes the second Climate Change Fund annual status report documenting performance of the fund up to June 2010. Decision of Exec Cllr for Climate Change and Growth: Agreed: To note the second annual status report for the Council’s Climate Change Fund. Reason for the As stated in the officer report. Any alternative options considered and rejected: N/A Scrutiny Considerations: The Climate Change Officer introduced the report. The Scrutiny Committee noted the report and supported the achievements to-date. The amount of officer time taken up by small projects was noted. The Executive Councillor for Climate Change and Growth noted the report. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) N/A
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
To: Executive Councillor for Climate Change & Growth Report by: Head of Policy and Projects: David Roberts Relevant scrutiny Environment Scrutiny Committee 22/06/10 committee:
CLIMATE CHANGE FUND ANNUAL STATUS REPORT Non Key Decision
1. Executive summary 1.1 A Climate Change Fund with an initial investment of £250,000 was agreed at Council on 21 February 2008 to be used to provide funding for schemes or activities which will contribute to the achievement of the Council’s climate change and carbon reduction Medium Term Objective. Detailed operational guidelines for management of the fund were agreed at Environment Scrutiny Committee in July 2007, which included a requirement for the total expenditure and achievements of the fund to be reported to Environment Scrutiny Committee annually. This report constitutes the second Climate Change Fund annual status report documenting performance of the fund up to June 2010.
2. Recommendations 2.1 The Executive Councillor is recommended to approve the second annual status report for the Council’s Climate Change Fund.
3. Background 3.1 A Climate Change Fund with an initial investment of £250,000 was agreed at Council on 21 February 2008 to be used to provide funding for internal schemes or activities which contribute to the achievement of the Council’s climate change and carbon reduction Medium Term Objective.
3.2Table 1 shows the financial status of the Climate Change Fund in May 2010, indicating that a total of 15 investments have been made since the fund’s establishment totalling £205,638. Table 1: Climate Change Fund Financial Status, May 2010 2008/09 2009/10 2010/11 Notes (Surplus) / Deficit £250,000 £243,900 £201,475 Balance b/f less Existing approvals Pilot of Electric Bin -£2,100 13/10/08 ESG approval Lifts by email - 8/9 members. 10/11/08 Finance approval. Chesterton Road -£900 05/11/08 ESG approval Toilet Modernisation by email - 8/9 members. 12/11/08 Finance approval. Corn Exchange -£600 05/11/08 ESG approval Christmas Lighting by email - 9/9 members. Lamps 10/11/08 Finance not approved. 11/11/08 Applicant feedback - suspended pending revision of CCF at ESC 13/01/09. 10/03/09 Applicant feedback to proceed. Arbury Court WC -£2,500 04/03/09 ESG approval Rainwater Harvesting Romsey Rec -£2,500 04/03/09 ESG approval Rainwater Harvesting Energy Audit of Pools -£3,745 26/06/09 ESG approval & Leisure Centres Grand Arcade Annex -£21,700 26/06/09 ESG approval Car Park fan system 16/07/09 Inclusion within capital plan recommended to Full Council. Public Conveniences -£2,725 26/06/09 ESG approval and Park Street Car Park Energy Survey Watercourses Flood -£6,000 09/09/09 ESG approval Risk Survey Grand Arcade Annex -£100,00009/09/09 ESG approval Car Park energy 06/10/09 Environment efficient lighting Scrutiny Committee approval.
Report Page No: 2 2008/09 2009/10 2010/11 Notes Community Centres -£2,995 09/12/09 ESG approval energy audits CornEx LED Bar -£2,760 09/12/09 ESG approval Lights Mill Rd Water -£36,000 09/12/09 ESG approval Efficiency Romsey Rec Green £0 09/12/09 ESG approval Roof - AMENDMENT Replacement boiler at -£3,150 17/03/10 ESG approval Barnwell House Guildhall voltage -£17,963 17/03/10 ESG approval optimisation trial 31/03/10 Exec Cllr approval 22/04/10 Added to Forward Plan. sub-total -£6,100 -£42,425 -£157,113 grand total -£6,100 -£48,525 -£205,638 (Surplus) / Deficit Balance b/f £243,900 £201,475 £44,362
3.3It is the responsibility of the Climate Change Officer to maintain a register containing the status and details of projects supported by the Climate Change Fund, as described by the fund’s operational guidelines (para. 8.3). Table 2 provides key details from this projects register regarding investments made up to May 2010. This indicates that the 15 projects supported by the Climate Change Fund:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.