To note the report. Decision of Exec Cllr for Climate Change and Growth: Agreed: 1. Noted the progress and achievements to date of the Sustainable City Capital Project Grants (PR4). 2. Note the decision in January 2010 to combine the Sustainable City Capital Project Grants with the Sustainable City Revenue Project Grants, effectively ending Sustainable City Project Grants as a capital programme. Future decisions regarding the budget for Sustainable City Revenue Project Grants will be made as part of the annual budget process. Reason for the No decision needed Any alternative options considered and rejected: N/A Scrutiny Considerations: The Climate Change Officer introduced the report. The Scrutiny Committee noted the report. The Executive Councillor for Climate Change and Growth noted the report. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) N/A
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Programme Review Programme Title Sustainable City Capital Project Grants
Manager Simon Chubb, Sustainable City Manager
Approved Timescale 1 April 1997 to 31 March 2011
Scrutiny Committee Climate Change & Growth
Committee Date 22 June 2010
Recommendation The Executive Councillor is recommended to: 1 Note the progress and achievements to date of the Sustainable City Capital Project Grants (PR4). 2 Note the decision in January 2010 to combine the Sustainable City Capital Project Grants with the Sustainable City Revenue Project Grants, effectively ending Sustainable City Project Grants as a capital programme. Future decisions regarding the budget for Sustainable City Revenue Project Grants will be made as part of the annual budget process.
1 Programme Remit “The Sustainable City Programme is designed to encourage bids for capital schemes from a broad range of local organisations which improve the sustainability of Cambridge City. Judgements about the relative contribution made by different schemes to sustainability will be made against their predicted or potential impact on various ‘sustainability’ indicators adopted by the Council. Matching external funding, equal to at least half of the total of the annual programme, will be sought by the Council”. Cambridge City Council Medium Term Strategy, Sept 2009, pg 250
2 Review of Achievement of Project Objectives The Sustainable City Capital Grants Programme is administered by Cambridge City Council’s Sustainable City Team and, along with the Sustainable City Revenue Grants, Core Funding Grants and promotional activities, is a key mechanism for engaging community groups in helping to deliver the Council’s environmental objectives. These are published in the Council’s environmental strategy document which is reviewed periodically: the current document is the Cambridge Environmental Framework 2009-121.
1 http://www.cambridge.gov.uk/ccm/navigation/environment-and-recycling/sustainable-city/what-we- are-doing/ The Sustainable City Capital Grants Programme was established in 1997 and has supported a total of 171 projects during the period up to March 2009. In response to the changing demand from grant applicants for capital and revenue grants, a recommendation was included within a report to Environment Scrutiny Committee on 12th January 2010 to transfer the remaining budget for the Sustainable City Capital Grants Programme (for 2009/10 and 2010/11) to the Sustainable City revenue grants programme2. This then avoids the need to transfer budget between the capital and revenue grants programmes depending on the demand from applicants, and also reflects the fact that grants awarded are considered de-minimis i.e. below the £15,000 threshold for capitalisation of expenditure. Figure 1 illustrates the profile of expenditure from the Sustainable City Capital Grants Programme against its budget, as well as expenditure from the Sustainable City revenue project and core funding grants for comparison. This shows the transfers which have occurred between the project grants budgets (e.g. in 2009/10, the total capital grants budget of £30,000 was transferred to the revenue grants budget giving a combined total of £40,000), as well as the reduced demand for core funding grants in 2010/11 from £68,000 in 2009/10 to £52,000 in 2010/11.
Figure 1: Profile of capital & revenue project and core funding grants
90 80 70 60 50 £000's
40 30 20 10 0 8
1 /9
/9
/0
/0
/0
/0
/0
/0
/0
/0
/0
/1
/1 97
10 /2 19
20 19
Capital project grants budget Capital project grants expenditure Revenue project grants expenditure Revenue core funding grants expenditure
2 http://www.cambridge.gov.uk/public/councillors/agenda/2010/01%20January/0112env/08.pdf (recommendation l, page 2) An analysis of available documentation of projects supported by the Sustainable City Capital Grants Programme has been undertaken for the period April 2002 to March 2009, comprising 99 projects, to assess the extent to which the objectives of the original remit have been achieved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.