Cambridge City Council
Environment Scrutiny Committee, Tuesday 22 June 2010 at 9.30am

Key Decision - Madingley Cycle Scheme

Agreed Scrutiny 1 paper

Environment Scrutiny Committee agreed this item on Tuesday 22 June 2010. Below is the council's own wording, with the papers it was decided on.

Item10/39/ESC

Resolved

The Madingley Road project is part of the Cycle Cambridge programme and aims to improve the existing poor provision for cyclists along Madingley Road. This corridor has been identified as a priority for funding from the Joint Funded Capital Cycleways budget and so it is proposed that £150,000 from the 2009/10 budget is put towards this project in addition to the £250,000 from the Western Area Corridor Transport Plan. Decision of Executive Councillor for Climate Change and Growth: Agreed: To note the details of the Madingley Road project as set out in this report at paragraph 3.3 o the report, and to agree to a contribution of £150,000 towards the project. Reason for the Madingley Road is an important radial route for cyclists and was identified as one of the radial routes which should be improved at the November 2002 Cambridge Environment and Transport Area Joint Committee as part of the Joint-funded Cycleways programme. This project could not subsequently be progressed due to issues with potential bus priority schemes on Madingley Road and implications arising from the Transport Innovation Fund proposals for the northwestern quadrant of the City. Cambridgeshire County Council have now decided that a bus priority scheme will not be pursued further east along Madingley Road and that the proposed cycle improvement scheme should not affect any future works undertaken as part of the Transport Innovation Fund. Any alternative options considered and rejected: N/A Scrutiny Considerations: The Cycling and Walking Development and Promotion Officer presented the item. Members were keen to make the best use of Cycle England money available to the City. Members were prepared to take a pragmatic approach to pinch points provided the Tree protocol is observed. The Scrutiny Committee considered and endorsed the recommendations unanimously. The Executive Councillor for Climate Change & Growth approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) N/A
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Executive summary

The Madingley Road project is part of the Cycle Cambridge programme and aims to improve the existing poor provision for cyclists along Madingley Road. This corridor has been identified as a priority for funding from the Joint Funded Capital Cycleways budget and so it is proposed that £150,000 from the 2009/10 budget is put towards this project in addition to the £250,000 from the Western Area Corridor Transport Plan.

Recommendations

The Executive Councillor is recommended: To note the details of the Madingley Road project as set out in this report at paragraph 3.3, and to agree to a contribution of £150,000 towards the project.

Background

3.1Madingley Road is an important radial route for cyclists and was identified as one of the radial routes which should be improved at the November 2002 Cambridge Environment and Transport Area Joint Committee as part of the Joint-funded Cycleways programme. This project could not subsequently be progressed due to issues with potential bus priority schemes on Madingley Road and implications arising from the Transport Innovation Fund proposals for the northwestern quadrant of the City. Cambridgeshire County Council have now decided that a bus priority scheme will not be pursued further east along Madingley Road and that the proposed cycle improvement scheme should not affect any future works undertaken as part of the Transport Innovation Fund. Report Page No: 1 3.2 Cambridge was granted ‘Cycle Demonstration Town’ status in 2008 and links to villages and new growth areas were part of the bid. As Madingley Road is a route out to the West Cambridge site, Madingley and Hardwick, and will be an important link to the North West Cambridge site, this project was included in the Cycle Cambridge Programme.

3.3The existing provision for cyclists along Madingley Road is very narrow, poorly surfaced shared paths on each side of the road with no continuity or provision at side roads. The proposals consulted on included a continuous on-road cycle lane for out-bound cyclists along the length of Madingley Road from the junction with Lady Margaret Road to the Park & Ride site, and the widening to 3 metres of the existing off-road provision for in-bound cyclists. This off-road provision would also include priority over side roads where visibility permits. The layout plans used for the consultation will be available at the meeting.

3.4Public consultation on these initial proposals was undertaken by the County Council in January/February this year, with an exhibition at the Madingley Road P&R and at the central library. Around 300 leaflets were distributed on Madingley Road and surrounding side streets of which 137 were returned. Of these 91 were in favour with 7 against and 39 giving no opinion. The few comments made on the scheme related to a dislike of shared paths, a desire to see better signage of shared paths, and a wish to see the improvements extended further west.

3.5The previous report stated that there was £400,000 funding available from the Western Corridor Area Transport Plan. This was an error made by the County Council as only £250,000 is available and the initial figure included the Joint Funded Cycleways Capital budget. Updated estimate costs indicate that the off road improvements, mainly on the in-bound side, will cost £395,000 and so the out-bound on-road cycle lanes may have to be white lines only rather than coloured in red if no additional Cycling England funding becomes available.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Key Decision: Madingley Cycle SchemeDecisions 51 KB DownloadRead as text

At this meeting

Whole meeting
10/35/ESCMinutesOn the agenda 10/38/ESCKey Decision - 2009/10 Revenue and Capital Outturn, Carry Forwards and Significant VariancesAgreed
10/39/ESCKey Decision - Madingley Cycle SchemeThis decision
10/40/ESCKey Decision - Hackney Carriage and Private Hire Licensing Fees and ConditionsAgreed 10/40/ESCaCheaper fees for Greener Vehicles Fuel Types Appendix AOn the agenda 10/40/ESCbCheaper fees for Greener Vehicles Cars registered on or after 1 March 2001 (based on fuel type and CO2 emissions) Appendix BOn the agenda 10/40/ESCcCheaper fees for Greener Vehicles Graph Appendix COn the agenda 10/40/ESCdPlug-in Taxi London Trials Appendix DOn the agenda 10/41/ESCKey Decision - Use of Taxis for Shared Usage Agreed at Point of DepartureApproved 10/42/ESCKey Decision - Bring Bank Recycling SchemeAgreed 10/43/ESCNon-Key Decision - Statutory Litter Duty - Zoning of The DistrictRefused 10/44/ESCKey Decision - 2009/10 Revenue and Capital Outturn, Carry Forwards and Significant VariancesAgreed 10/45/ESCKey Decision - Procurement Approval Report for a Surface Water Management Plan for Cambridge and MiltonAgreed 10/46/ESCKey Decision - Pro-active ConservationApproved 10/47/ESCKey Decision - Proposed City Council Public Art Commissioning StrategyOn the agenda 10/48/ESCKey Decision - Programme Review Car Parks Infrastructure and Replacement ProgrammeNoted 10/49/ESCNon-Key Decision - Charging Policy for Electric Vehicles on City Council Off-Street Car ParksAgreed 10/49/ESCaAsset Replacement Programme Appendix 1On the agenda 10/50/ESCKey Decision - Sustainable City Capital Grants Programme ReviewNoted 10/51/ESCNon-Key Decision - Climate Change Fund Annual Status ReportAgreed 10/52/ESCNon- Key Decision - Cambridge Environment Report 2009-10Approved 10/53/ESCGrey (Waste) Water Recycling System at Mill Rd DepotApproved 10/54/ESCaVoltage Optimisation Guildhall TrialOn the agenda 10/54/ESCb1 Year Extension of Reverse Agency AgreementOn the agenda 10/54/ESCcTree Maintenance Framework Agreement 2010-14On the agenda

Who was there

10 of 10 attended
TW
Councillor Tim WardChair, present
SK
Councillor Simon KightleyVice-Chair, present
LH
Councillor Lewis HerbertCommittee Member, present
AP
Councillor Adam PogonowskiCommittee Member, present
DT
Councillor Damien TunnacliffeCommittee Member, apologies, sent representative
PS
Councillor Paul SaundersCommittee Member, present
SK
Councillor Susannah KerrCommittee Member, present
SN
Councillor Stuart NewboldCommittee Member, present
RZ
Councillor Roman ZnajekCommittee Member, present
RS
Councillor Raj ShahReserve, present as substitute

On this subject at Cambridge

Search all
  1. Key Decision - Madingley Cycle SchemeThis decision
  2. Non Key Decision - Community Empowerment and Local Participation in Decision MakingRefused
  3. Key Decision - 2009/10 Outturn - Strategy PortfolioApproved
  4. Key Decision - 2009/10 Revenue and Capital Outturn, Carry Forwards and Significant Variances - General Fund - OVERVIEWRefused
  5. Key Decision - Outturn 2009-10- Customer Services and Resources PortfolioApproved
  6. Non-Key Decision - Customer Access Strategy OutcomesAgreed

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies