Community Services Scrutiny Committee refused this item on Thursday 14 October 2010. Below is the council's own wording, with the papers it was decided on.
As set out in the officer’s report. Any alternative options considered and rejected: As set out in the officer’s report. Scrutiny Considerations: The committee received a report from the Recreation Services Manager. In response to a member’s question the Head of Arts and Recreation confirmed that, whilst S106 funding was for ‘formal open space’, its use for this type of sports project was appropriate. The Scrutiny Committee considered and endorsed the recommendations in the report by 7 votes to 0 (unanimous). The Executive Councillor for Arts and Recreation approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensations granted): None
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1The project Approval to grant S106contributions to fund the installation of a climbing wall at Kelsey Kerridge Sports Hall was given March 2010.
A revised project to include the additional feature of a large bouldering facility at a further cost of £30,000 is now proposed.
Target Start date November 2010 Target completion date December 2010
1.2The Cost Total Capital Cost £ 90,000
C:\DOCUME~1\BURGE1G\LOCALS~1\TEMP\XPGRPWISE\AB PA - KELSEY KERRIDGE ADDITIONAL FUNDING.DOC Item xx Page 2 of 5
Capital Cost Funded from:
Funding: Amount: Details:
Reserves £0 N/a
Repairs & Renewals £ 0 N/a
Section 106 £ 90,000 Formal Open Space
Other
Revenue Cost – met by Kelsey Kerridge
Year 1 £0
Ongoing £0
1.3The Procurement Kelsey Kerridge Sports Hall Trust has tendered the above works and is looking to award the works to “Zig Zag Climbing walls”. Capital Project Appraisal & Procurement Report
1.4What is the project? The previously approved project was to provide a new climbing wall and overhang in Kelsey Kerridge. Approved funds totalled £60,000 from S106 Formal Open Space contributions.
The project remains the same as the previous report, but a new feature of a bouldering facility is being added at a cost of £30,000 to make best use of the space available and provide a diverse climbing experience.
New regulations about the size of crash mats mean that the multi- use space within the climbing wall room is now required for the larger crash matting and a smaller, unusable space is left.
To make best use of this space a bouldering wall facility has been added to the project and additional funds of £30,000 are requested to fund this additional and unique facility for Cambridge.
C:\DOCUME~1\BURGE1G\LOCALS~1\TEMP\XPGRPWISE\AB PA - KELSEY KERRIDGE ADDITIONAL FUNDING.DOC Item xx Page 3 of 5
1.5What are the aims & objectives of the project? Main objective is to extend and update the climbing wall provision within the Kelsey Kerridge Sports Hall to maximise the potential of the facilities.
This contributes to the Council’s Vision for: • ‘A city which is diverse and tolerant, values activities which bring people together and where everyone feels they have a stake in the community • A city which draws inspiration from its iconic historic centre and achieves a sense of place in all of its parts with generous urban open spaces and well designed buildings.’
1.6Summarise the major issues for stakeholders & other departments? The current facilities, although usable, are not very demanding, offer little advanced climbing experience, are very dated compared to other indoor climbing facilities, and are below the expectation of sports and leisure facilities today.
Disabled provision and access to this facility will be enhanced allowing a range of disabled users that would otherwise not be able to access the experiences of climbing and bouldering.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.