Resolved

Decision of Executive Councillor for Housing: · Approved the mix, design and layout of the scheme for the redevelopment of Seymour Court. · Approved the Construction Cost of the scheme to the Council of £435,000. · Delegated authority to the Director of Customer and Community Services, following consultation with the Director of Resources and the Head of Legal Services, to negotiate with the County Council the cost to the City Council of bringing the lease of Seymour House to an early end and with Cambridgeshire NHS a contribution to the relocation cost of staff. Scrutiny Considerations: The Committee received a presentation from representatives of the developer (Kier). The presentation is available on request from the Development Officer. In response to questions from members the Head of Strategic Housing and the Kier representatives confirmed the following: - The flats above the parking spaces would be fully insulated to combat any potential noise issues. - Outside drying facilities would be available on site. - TV reception would be via communal aerials. - The total area of the site would be 0.54 hectares. - Using best practice, the percentages included in the report were based on numbers of units and not number of bed spaces or floor area. - Meetings had been held with the Council’s Urban Design Team to discuss height and massing. Different heights had been used to define entrances to the site and emphasise corner plots. The design also maximised available sunlight and limited shadowing and any adverse impact on neighbouring buildings. - Service charge management issues also dictated layout e.g in terms of the number of flats served by lifts. - The separating of the flat blocks would allow for greater long-term flexibility of the site should the demands from older people change. - The development was likely to achieve a SILVER ‘Build for Life’ standard rating. - Solar panels would be incorporated into the design but discussions were ongoing regarding the use of grey water. - The building would achieve level 4 of the Code for Sustainable Homes and use low flow taps and small size baths. - All flats would have shared garden space. In addition, each ground floor flat would have a private terrace, and most non- ground floor flats would have a balcony. One flat would also have access to a roof terrace above the cycle store. - Every residence above two storeys would have lift access. Councillor Al Bander asked a specific question regarding viability of the site for this type of scheme. In response the Head of Strategic Housing confirmed that a full competitive tender process had been undertaken by the Council in order to secure a preferred developer. Based on both cost and quality Kier had been selected as that developer. Discussions with the developer on the baseline scheme then led to a number of improvements, each of which had the support of the Councils Urban Design Team. Officers were therefore confident that the scheme had been fully tested through the tender process. The Head of Strategic Housing agreed to forward Councillor Al Bander information on the footprint of the site, including specific percentages of the affordable and the market housing. In response to further questions from members the Director of Customer and Community Services and the Head of Strategic Housing confirmed the following: - Seymour Court should be empty by the end of January 2011. - The planning process should start in January and approval anticipated by April or May 2011. - Work should start on the site by the 1 st July 2011. - Project management of the scheme by Cyril Sweet would help ensure that the Council was getting value for money. - On past projects the cost of refurbishment had been upwards of £100,000 per unit. The cost of achieving vacant possession of Seymour House would be around £400,000 in respect of early termination of the lease on Seymour House plus a contribution to relocation costs. On the latter a maximum of £220,000 is currently being quoted - Using the worst-case scenario, the project would pay back the capital in 19 years. The normal benchmark for capital pay back was 30 years. - The payment made to Kier would include all S106 contributions The Scrutiny Committee considered and endorsed the recommendations in the report by 5 votes to 0 (unanimous). The Executive Councillor for Housing approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensations granted): None
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Community Services Scrutiny Committee

Recommendations

The Executive Councillor is recommended to; 1. Approve the mix, design and layout of the scheme for the redevelopment of Seymour Court presented to the Committee. 2. Approve the Construction Cost of the scheme to the Council of £435,000. 3. Delegate authority to the Director of Customer and Community Services, following consultation with the Director of Resources and the Head of Legal Services, to negotiate with the County Council the cost to the City Council of bringing the lease of Seymour House to an early end and with Cambridgeshire NHS a contribution to the relocation cost of staff. (see 1.4 below)

Background

At the October 2010 Community Services Committee Meeting the Executive Councillor for Housing approved the principle of the redeveloping Seymour Court as a mixed tenure scheme with the Affordable Housing to be owned and managed by City Homes. The Executive Councillor also gave delegated authority to the Director of Customer and Community Services, following consultation with the Director of Resources and the Head of Legal Services, to sign a Development Agreement with a single house- builder/developer partner to redevelop Seymour Court, subject to a

Page 1 of 6 final scheme being brought before a special Community Services Scrutiny Committee Meeting for approval.

This report outlines the scheme that officers have worked up with Kier, the successful tenderer from the procurement process outlined in the October 2010 Committee report.

1.2The Project The redevelopment of Seymour Court will provide 21 Affordable Housing flats for people over the age of 55 that will be owned and managed by City Homes. The 21 flats comprise;

2 no. 1 bed, 2 person flats 16 no. 2 bed, 4 person flats 2 no. 2 bed, 3 person fully wheelchair accessible flats 1 no. 1 bed, 2 person flat over garages dwelling

There will also be market housing on the site that will be sold at Kier’s risk and comprises 7 no. 2 bed, 4 person houses, 4 no. 3 bed, 5 person houses and 4 no. 4 bed, 7 person houses – a total of 15 houses.

Therefore the redevelopment is made up of 36 dwellings, 58% Affordable Housing and 42% market housing.

The land the market housing will be built on will be transferred freehold to Kier at nil value. (It is the Council’s policy to dispose of land at nil value to housing associations to facilitate new Affordable Housing). This allows Kier to propose an extremely low build cost to the Council in comparison to the actual cost of building the 21 Affordable Housing dwellings. The Council will retain freehold ownership of the Affordable Housing land.

Seymour House is a building at the centre of Seymour Court that is currently leased to the County Council and occupied by health and social care staff. Negotiations are under way to relocate the staff and agreement has been reached for this to happen by the end of June 2011.

Kier will present plans of the layout and design of the proposed scheme at the meeting.

Page 2 of 6 1.3 Aims and Objectives. This project is in line with the Council’s vision for “a city which recognises and meets needs for housing of all kinds – close to jobs and neighbourhood facilities” and provides fully wheelchair accessible dwellings, apartments for people over the age of 55 and market housing. The Affordable Housing dwellings will be owned and managed by City Homes and will contribute to the sustainability of the service.

In relation to well designed buildings, Urban Design and Development Control have been consulted and an initial assessment has shown that the silver or gold standard could be achieved for the Building for Life assessment, promoted by CABE (Commission for Architecture and the Built Environment). This represents a good standard of design.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Seymour Court Scheme ApprovalReport 56 KB DownloadRead as text

At this meeting

Whole meeting
10/79/JDCSeymour Court Scheme ApprovalThis decision

Who was there

7 of 13 attended
SK
Councillor Simon KightleyChair, present
SK
Councillor Susannah KerrVice-Chair, present
SA
Councillor Salah Al BanderCommittee Member, present
AB
Councillor Andy BlackhurstCommittee Member, present
SB
Councillor Sarah BrownCommittee Member, apologies
VS
Councillor Viki SandersCommittee Member, apologies
RS
Councillor Raj ShahCommittee Member, apologies
MT
Councillor Mike Todd-Jones Labour Spokes for HousingCommittee Member, apologies
LW
Councillor Lucy Walker Labour Spokes for Community ServicesCommittee Member, present
DB
Diane Best HMB Co-optee - Leaseholder RepresentativeCo-Optee, present
TD
Tom Dutton Primary Care Trust RepresentativeCo-Optee, absent
BH
Brian Haywood HMB Co-optee - Tenant RepresentativeCo-Optee, present

All 13 on the meeting page

On this subject at Cambridge

Search all
  1. Seymour Court Scheme ApprovalThis decision
  2. 11/0970/FUL: Seymour Court, Seymour StreetApproved
  3. Seymour Court - Disposal of Land to Facilitate Redevelopment SchemeApproved
  4. Seymour Court Scheme ApprovalRefused
  5. Seymour Court Re-developmentAgreed

More from Cambridge Community Services Scrutiny Committee

All decisions
MeetingDecisionOutcome
15 Mar 2018 Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a... Refused Open
15 Mar 2018 Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover... Approved Open
15 Mar 2018 Annual Update on the Work of our Strategic Partnerships - Communities PortfolioDecision The Officer’s report provides an update on the work of the Health and Wellbeing Board and Children’s Trust a... Agreed Open
18 Jan 2018 Policy for Use of Events on Parks and Open SpaceDecision The hosting of events on city parks and open spaces had become increasingly popular with both local and nati... Approved Open