Seymour Court - Disposal of Land to Facilitate Redevelopment Scheme
ApprovedScrutiny2 papers
Strategy and Resources Scrutiny Committee approved this item on Monday 21 March 2011. Below is the council's own wording, with the papers it was decided on.
Decision of Executive Councillor: The Executive Councillor resolved to i. Approve the disposal of the freehold of part of Seymour Court to Kier to facilitate the redevelopment of the site. The part of the site to be disposed is shown outlined on the plan attached as Appendix 1 to the committee report. Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected : N/A Scrutiny Considerations: The committee received a report from the Head of Housing Strategy regarding the disposal of land at Seymour Court. It was clarified that the recommendation should refer to the black outline, and following discussion it was agreed that the reference to colour could be removed. The innovative design of the proposed scheme was welcomed. The Scrutiny Committee considered and approved the recommendations as amended by 8 votes to 0. The Executive Councillor for Customer Services and Resources approved the decision.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Executive summary
1.1The Executive Councillor for Housing has approved a scheme to redevelop Seymour Court.
1.2This report requests that approval be given to the freehold disposal of part of the land at Seymour Court to facilitate the redevelopment scheme.
Recommendations
The Executive Councillor Customer Service and Resources is recommended to :
Approve the disposal of the freehold of part of Seymour Court to Kier to facilitate the redevelopment of the site. The part of the site to be disposed is shown outlined in blue on the plan attached as Appendix 1.
Background
3.1The Executive Councillor for Housing accepted the recommendation of the Community Services Scrutiny Committee on 9 December 2011 to • Approve the mix, design and layout of the scheme for the redevelopment of Seymour Court presented to the Committee. • Approve the Construction Cost of the scheme to the Council of £435,000. • Delegate authority to the Director of Customer and Community Services, following consultation with the Director of Resources and Report Page No: 1 the Head of Legal Services, to negotiate with the County Council the cost to the City Council of bringing the lease of Seymour House to an early end and with Cambridgeshire NHS a contribution to the relocation cost of staff, (see 3.6 below).
3.2At the October 2010 Community Services Committee Meeting the Executive Councillor for Housing approved the principle of the redeveloping Seymour Court as a mixed tenure scheme with the Affordable Housing to be owned and managed by City Homes. The Executive Councillor also gave delegated authority to the Director of Customer and Community Services, following consultation with the Director of Resources and the Head of Legal Services, to sign a Development Agreement with a single house-builder/developer partner to redevelop Seymour Court, subject to a final scheme being brought before a special Community Services Scrutiny Committee Meeting for approval.
3.3Further details of the scheme that officers have worked up with Kier, the successful tenderer from the procurement process outlined in the October 2010 Committee report, are set out below.
3.4The Project
The redevelopment of Seymour Court will provide 21 Affordable Housing flats for people over the age of 55 that will be owned and managed by City Homes. The 21 flats comprise;
2 no. 1 bed, 2 person flats 16 no. 2 bed, 4 person flats 2 no. 2 bed, 3 person fully wheelchair accessible flats 1 no. 2 bed, 4 person flat over garages dwelling
There will also be market housing on the site that will be sold at Kier’s risk and comprises 7 no. 2 bed, 4 person houses, 4 no. 3 bed, 5 person houses and 4 no. 4 bed, 7 person houses – a total of 15 houses.
Therefore the redevelopment is made up of 36 dwellings, 58% Affordable Housing and 42% market housing.
The land the market housing will be built on will be transferred freehold to Kier at nil value. (It is the Council’s policy to dispose of land at nil value to housing associations to facilitate new Affordable Housing). This allows Kier to propose an extremely low build cost to the Council in comparison to the actual cost of building the 21
Report Page No: 2 Affordable Housing dwellings. The Council will retain freehold ownership of the Affordable Housing land.
Seymour House is a building at the centre of Seymour Court that is currently leased to the County Council and occupied by health and social care staff. Negotiations are under way to relocate the staff and agreement has been reached for this to happen by the end of June 2011.
3.5Project Aims and Objectives.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.