Community Services Scrutiny Committee refused this item on Thursday 13 January 2011. Below is the council's own wording, with the papers it was decided on.
Current changing facilities were very dated, were not DDA compliant, and did not provide the experience expected by today’s sports user. The Mai Thai Restaurant also required dedicated storage to help it fully comply with current legislation. Any alternative options considered and rejected: As set out in the officer’s report. Scrutiny Considerations: The Committee received a report from the Recreation Services Manager. In response to member’s questions the Recreation Services Manager confirmed the following: i. The scheme had already received planning permission. ii. A procurement exercise would need to be undertaken. iii. The Mai Thai Restaurant would be funding their element of the extension. The Executive Councillor for Arts and Recreation reiterated the Councils commitment to sport in the city. He noted that this scheme and the funding proposed for Parkside Pools was an example of this commitment. The Scrutiny Committee considered and endorsed the recommendations in the report by 6 votes to 0 (unanimous). The Executive Councillor for Arts and Recreation approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensations granted): None
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Working in partnership with the Mai Thai Restaurant, this project is the refurbishment and extension of Hobbs Pavilion (on Parkers Piece) to provide the City Council three new changing rooms, a multi purpose room, new grounds keeper room and equipment storage areas, and for the restaurant an additional secure and hygienic food storage facility.
C:\DOCUME~1\BURGE1G\LOCALS~1\TEMP\XPGRPWISE\PA - HOBBS PAVILION V1.2.DOC Item xx Page 2 of 8
Target Start date March / April 2011 Target completion date May/June 2011
1.2The Cost Total Capital Cost £ 240,000
Capital Cost Funded from:
Funding: Amount: Details:
Reserves £0 N/a
Repairs & Renewals £ 0 N/a
Section 106 £ 240,000 Formal Open Space
Other £ 0.00 N/a
Revenue Cost
Year 1 £0
Ongoing £0
1.3The Procurement The Council will be undertaking a procurement exercise for the structural building works, the fitting out of the changing rooms, multi function room and grounds keeper facilities. This will include the Mai Thai Restaurant’s build out to extend the pavilion as structural works will affect both sides of the property and a joint works programme will therefore be required.
Capital Project Appraisal & Procurement Report
1.4What is the project? The Mai Thai Restaurant plans to extend the Pavilion to upgrade their facilities including construction of dedicated storage facilities
C:\DOCUME~1\BURGE1G\LOCALS~1\TEMP\XPGRPWISE\PA - HOBBS PAVILION V1.2.DOC Item xx Page 3 of 8
compliant with current food safety regulations. The Council has the opportunity to develop their potential in Hobbs Pavilion by rearranging the internal structure and updating the facilities to improve the changing rooms, create a multi-use room, and provide improved accommodation for grounds staff.
The refurbishment will upgrade the changing rooms, providing disabled access to the facilities, and create a multi purpose room that can be used by clubs, the Council and the restaurant. New facilities and storage space will also be created for the permanent grounds staff on Parkers Piece.
Current changing facilities are very dated, are not DDA compliant, and do not provide the experience expected by today’s sports user. The refurbishment would provide three changing facilities that will include new changing areas, showers and toilet facilities, all incorporating energy saving features. They will also provide modern changing accommodation that will be DDA compliant.
Other rooms within the current building are not regularly used and would be converted into a multi-purpose/ function/ conference room. The clubs will be able to use the space as a meeting room to host after game refreshments, the Council as a meeting/ conference room, and the restaurant as a private function space.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.