Strategy and Resources Scrutiny Committee refused this item on Monday 17 January 2011. Below is the council's own wording, with the papers it was decided on.
As set out in the officer’s report Any alternative options considered and rejected: N/A Scrutiny Considerations The committee received a report from the Head of Tourism and City Centre Management regarding the City Centre Management Capital Grants Scheme. Clarification was requested on the level of budget. The Head of Tourism and City Centre Management confirmed that the proposed budget would reduce to £20k in the new financial year from £30k. It was noted that following the formation of “Love Cambridge”, it was always the intention for the level of budget to reduce over time. The Scrutiny Committee considered and approved the recommendations by 6 votes to 0. The Executive Councillor agreed the recommendation.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Recommendation
The Executive Councillor is recommended to: 1. Note the progress and achievements to date of the City Centre Management Capital Grants Scheme. 2. Include a bid of £20 K pa to be considered in the Budget Setting Report (BSR) to extend the programme to 2014/15 in accordance with the revised remit. 3. To review the programme again in 2014/15, subject to the extension of further funding
1 Programme Remit “The City Centre Management Programme is designed to provide pump- priming finance for capital schemes which improve the commercial and retail environment in the City Centre. The programme enables the Council to work in partnership with the private and voluntary sectors to ‘kick start’ projects that would not otherwise take place. The Council will seek matching external funding equal to the annual total of the programme.”
Cambridge City Council Medium Term Strategy, Sept 2009, pg 250
2 Review of Achievement of Project Objectives Background
From 1st April 1997 through to 31st March 2010 applications to the City Centre Management Capital Grants programme were considered and approved by the City Centre Management Executive Group, which was the representative body for the informal City Centre Partnership, first established in 1994. As the role of this partnership was to improve the vitality and viability of the city centre through partnership working, it proved to be a very effective vehicle for promoting and facilitating grant applications. Administration of the scheme was organised by the City Council’s City Centre Management team. On 1st April 2010 this informal partnership developed into an independent public/private partnership trading under the name of Love Cambridge. The key objectives of the move to an independent organisation were to strengthen the partnership and to provide a structure, which would provide shared governance amongst those involved.
Love Cambridge is a not for profit Company, limited by Guarantee, led by a board of directors who are drawn from a wide range of interests from across the city centre. As a membership organisation, it invites active involvement from all city centre organisations who are committed to working to help Cambridge build on its strengths and respond to its challenges through a culture of effective partnership working.
Following this change a report was taken to Asset Management Group on 21st May 2009 which recommended that all applications to the City Centre Management Grant programme should be put before the Love Cambridge Board to review. The role of the Board would then be to recommend grants to the City Council for approval. This recommendation was approved and since 1st April 2010 Love Cambridge has played the pivotal role in promoting the scheme and encouraging and facilitating applications.
It is important to note that as a result of a change in key personnel in the City Centre Management team at the end of 2006 and the availability of supporting documentation prior to this change, it is not possible to provide much detail on the projects supported by this programme prior to this date.
Achievements
Since its launch in 1997 the scheme has supported 53 projects. The majority of the projects can be grouped into the following 3 thematic areas:
Thematic Area Total Spend Number of Percentage projects spend of total £000 programme
Environmental £119.5 19 39% improvements
Christmas Lights £101.8 13 33%
Signage £62.8 9 21%
Miscellaneous £21.8 12 7%
Total £305.9 53 100% Environmental Improvement Schemes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.