Provisional Carry Forward Requests, Capital Plan changes and project appraisals

Agreed Scrutiny 1 paper

Strategy and Resources Scrutiny Committee agreed this item on Monday 21 March 2011. Below is the council's own wording, with the papers it was decided on.

Item11/26/SR

Resolved

Decision of the Leader: The Leader resolved to i. Agree the provisional General Fund revenue carry forward requests, totalling £417,030 to be recommended to Council for approval, subject to the final outturn position. ii. Approve the following additions to the Capital Plan: From the Executive Councillor for Arts & Recreation: i. Additional funding of £60,000 from Developer Contributions for Public Art in respect of SC476 – Water Play Area Abbey Paddling Pool ii. Additional funding of £51,000 from Developer Contributions for Public Art in respect of SC487 and SC488 (Coleridge Recreation Ground – Landscaping and Informal Play) From the Executive Councillor for Housing: i. Provisional re-phasing of £4,624,000 of capital resources, from 2010/11 into 2011/12, as part of the Housing Capital Investment Plan, to be recommended to Council for approval, subject to the final outturn position. Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected : N/A Scrutiny Considerations: The committee received a report from the Director of Resources regarding provisional carry forward requests. Clarification was requested on the likelihood of the carry forwards being spent during the next financial year, and whether there would be a supplementary set of reports in the next scrutiny cycle. The Director of Customer and Community Services explained that the majority of the housing carry forward related to a single project (Brandon Court), which had been re-phased to align with the future plans for Ditchburn Place. The committee were also advised of the difficulty of precisely planning expenditure due to the length of the lead in times associated with the housing capital programme. The Director of Resources advised that all the carry forwards were subject to final outturn and further reports may be required in the next cycle. The Scrutiny Committee considered and approved the recommendations by 6 votes to 0. The Leader approved the recommendation.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Executive summary

1.1This report presents details of any anticipated variances from revenue budgets where resources are requested to be carried forward into the 2011/12 financial year in order to undertake or complete activities previously approved to take place in 2010/11. These have been reported, in this cycle, to the relevant Executive Councillors and Scrutiny Committees.

1.2Also included are specific recommendations regarding any new items or changes required to projects or funding in the Capital Plan.

1.3A number of project appraisals that required consideration prior to project commencement have been presented to the relevant Scrutiny Committees and approved by the respective Executive Councillors.

1.4Whilst there are no carry forward requests or changes to the capital plan for the portfolios that report to this Scrutiny Committee (Customer Services & Resources and Strategy Services), this report provides an overview for all portfolios as a whole.

Recommendations

The Leader is recommended:

a) To agree the provisional General Fund revenue carry forward requests, totalling £417,030 as detailed in Appendix A, to be recommended to Council for approval, subject to the final outturn position.

Report Page No: 1 b) Approve the following regarding the Capital Plan:

From the Executive Councillor for Arts & Recreation:

i) To approve additional funding of £60,000 from Developer Contributions for Public Art in respect of SC476 – Water Play Area Abbey Paddling Pool (as shown in the project appraisal submitted to the Community Services Scrutiny Committee on 17 March 2011)

ii) To approve additional funding of £51,000 from Developer Contributions for Public Art in respect of SC487 and SC488 (Coleridge Recreation Ground – Landscaping and Informal Play) (as shown in the project appraisal submitted to the Community Services Scrutiny Committee on 17 March 2011)

From the Executive Councillor for Housing:

iii) To agree the provisional rephasing of £4,624,000 of capital resources, from 2010/11 into 2011/12, as part of the Housing Capital Investment Plan, to be recommended to Council for approval, subject to the final outturn position.

Background

Revenue Outturn

3.1Appendix A sets out the provisional list of items for all portfolios, for which approval is sought to carry forward unspent budget from 2010/11 to the next financial year, 2011/12.

3.2Note that there are no carry forward requests for the portfolios that report to this Scrutiny Committee (Customer Services & Resources and Strategy Services).

Capital Outturn

3.3All capital schemes were reviewed as part of the budget process in January 2011 and the Capital Plan was amended to account for rephasing and anticipated over/underspends on individual schemes at this stage.

3.4Appendix B shows the capital schemes covered by the Housing Capital Investment Plan (Housing Revenue Account and Housing General Fund schemes funded from HRA resources). Any provisional requests to rephase additional resources from 2010/11 to 2011/12 Report Page No: 2 have been incorporated in the appendix and are explained in detail in the notes to the appendix.

3.5All these requests are provisional as they are subject to the final outturn position (net variances on revenue and capital spending), which will be reported to the next, June scrutiny committee cycle.

4. Implications

4.1The financial implications of approving the provisional carry forward of budget from the current year into 2011/12, will result in a reduced requirement in the use of reserves for the current financial year, with a corresponding increase in the use of reserves in 2011/12 and therefore no change to the reserves level that was agreed in the Budget-Setting report approved by Council in February 2011.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Provisional Carry Forward Requests, Capital Plan changes and project appraisalsReport 104 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
AT
Councillor Amanda TaylorChair, present
MB
Councillor Max BoyceVice-Chair, present
SA
Councillor Salah Al BanderCommittee Member, apologies, sent representative
RD
Councillor Robert Dryden Labour Spokes for Customer Services and ResourcesCommittee Member, present
LH
Councillor Lewis Herbert Labour Spokes for StrategyCommittee Member, present
IN
Councillor Ian Nimmo-SmithCommittee Member, present
GO
Councillor George OwersCommittee Member, present
RS
Councillor Raj ShahCommittee Member, present
TW
Councillor Tim WardCommittee Member, present
SB
Councillor Sarah BrownReserve, present as substitute

On this subject at Cambridge

Search all
  1. Provisional Carry Forward Requests, Capital Plan changes and project appraisalsThis decision
  2. 2023-24 General Fund Virements and Provisional Revenue Carry ForwardsAgreed
  3. HRA Provisional Carry Forwards 2023/24Agreed
  4. HRA Provisional Carry Forwards 2022/23Agreed

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open