Replacement of Corn Exchange House Lighting

Approved Scrutiny 1 paper

Community Services Scrutiny Committee approved this item on Thursday 15 March 2012. Below is the council's own wording, with the papers it was decided on.

Item12/31/CS

Resolved

The proposal is to replace the existing lights with a LED lighting system, which is more energy efficient and will therefore lead to a reduction in both running costs and carbon emissions. Decision of Executive Councillor for Arts, Sport and Public Places The Executive Councillor resolved to: Financial recommendations I. Recommend this scheme (which is not included in the Council’s Capital & Revenue Project Plan) for approval by Council, subject to resources being available to fund the capital and revenue costs. II. The total cost of the project is £40,000, funded from repair and renewal funding and a grant from the Climate Change Fund. III. There are no adverse revenue implications arising from the project. The bid to the Climate Change Fund identifies savings from lighting efficiency which when realised will be returned to the Council. Procurement recommendations IV. Approve the procurement of replacement and upgraded house lighting for the Corn Exchange at a total cost of £40,000. V. Subject to permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reason for the The general house lighting system in the Corn Exchange auditorium needs replacing. The existing system was installed over 15 years ago and is rapidly becoming life expired. Any alternative options considered and rejected: As an alternative, the existing lighting system could be replaced on a ‘like-for-like’ basis, for example with metal halide fittings and tungsten halogen floodlights. This option would be cheaper (est. cost of around £14,000) but would not deliver the ongoing cost and carbon savings that will be achieved through a LED lighting solution. Scrutiny Considerations: Not applicable. The Executive Councillor for Arts, Sport and Public Places approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) N/A
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Community Services Scrutiny Committee

Page 1 of 7

Cambridge City Council

To: Executive Councillor for Arts, Sport and Public Places Report by: Cultural Facilities Manager, Steve Bagnall Relevant scrutiny COMMUNITY SERVICES committee: Wards affected: None

Project Appraisal and Scrutiny Committee Recommendation Project Name: Corn Exchange House Lighting LED Upgrade

Recommendation/s Financial recommendations – The Executive Councillor is asked to recommend this scheme (which is not included in the Council’s Capital & Revenue Project Plan) for approval by Council, subject to resources being available to fund the capital and revenue costs. • The total cost of the project is £40,000, funded from repair and renewal funding and a grant from the Climate Change Fund. • There are no adverse revenue implications arising from the project. The bid to the Climate Change Fund identifies savings from lighting efficiency which when realised will be returned to the Council.

Procurement recommendations: The Executive Councillor is asked to approve the procurement of replacement and upgraded house lighting for the Corn Exchange at a total cost of £40,000. • Subject to permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Page 2 of 7

Summary 1.1 The project

Target Dates: Start of procurement February 2012 Award of Contract March 2012 Start of project delivery July 2012 Completion of project August 2012

1.2The Cost Total Project Cost £ 40,000

Cost Funded from:

Funding: Amount: Details:

Reserves £

Repairs & Renewals £14,300 27708 8189 Developer £ Contributions Other £25,700 Climate Change Fund

Ongoing Revenue Cost No maintenance contract Year 1 £ required Ongoing £

1.3The Procurement The supply of LED lighting equipment is a relatively specialist area for which the Council does not have an Approved List. The equipment purchase element exceeds £30,000 therefore a formal invitation to tender including a specification will be issue to at least four candidates approved by the Head of Service. An advertisement will be used as necessary to source such appropriate candidates. Three quotes will be obtained from Page 3 of 7

suitable electrical contractors for the electrical installation element of the project.

2 Project Appraisal & Procurement Report

2.1The Project The general house lighting system in the Corn Exchange auditorium needs replacing. The existing system was installed over 15 years ago and is rapidly becoming life expired.

The proposal is to replace the existing lights with a LED lighting system, which is more energy efficient and will therefore lead to a reduction in both running costs and carbon emissions. Furthermore, under the existing system, there are currently more light fittings than required by today’s standards. Therefore, as part of the lighting upgrade, the number of light fittings will be reduced, which will further reduce costs and emissions.

As an alternative, the existing lighting system could be replaced on a ‘like-for-like’ basis, for example with metal halide fittings and tungsten halogen floodlights. This option would be cheaper (est. cost of around £14,000) but would not deliver the ongoing cost and carbon savings that will be achieved through a LED lighting solution.

A successful bid has been made to the Climate Change Fund which will fund the uplift in costs incurred by the LED element. Identified revenue savings in utility consumption will be returned to the Council from A&R budgets. Based on current event activity in the Corn Exchange the saving is estimated to be around £5000 per year.

2.2Aims & objectives To continue to provide suitable and cost-effective lighting for the Council’s premier entertainment venue, whilst at the same time reducing the Council’s energy use, costs and carbon emissions.

This proposal will support the Council’s corporate objective to be ‘A city in the forefront of low carbon living.’ Page 4 of 7

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Replacement of Corn Exchange House LightingReport 149 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
SK
Councillor Susannah KerrChair, present
SK
Councillor Simon KightleyVice-Chair, present
SA
Councillor Salah Al BanderCommittee Member, present
AB
Councillor Andy BlackhurstCommittee Member, present
SB
Councillor Sarah BrownCommittee Member, present
ZM
Councillor Zoe Moghadas Labour Spokes for Arts, Sport and Public PlacesCommittee Member, present
CO
Councillor Carina O'Reilly Labour Spokes for Community Development and HealthCommittee Member, present
AR
Councillor Andrea ReinerCommittee Member, present
MT
Councillor Mike Todd-Jones Labour Spokes for HousingCommittee Member, present
DB
Diane Best HMB Co-optee - Leaseholder RepresentativeCo-Optee, present
TD
Tom Dutton Primary Care Trust RepresentativeCo-Optee, expected
BH
Brian Haywood HMB Co-optee - Tenant RepresentativeCo-Optee, apologies

All 13 on the meeting page

On this subject at Cambridge

Search all
  1. Replacement of Corn Exchange House LightingThis decision
  2. Replacement of the Corn Exchange passenger liftApproved

More from Cambridge Community Services Scrutiny Committee

All decisions
MeetingDecisionOutcome
15 Mar 2018 Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a... Refused Open
15 Mar 2018 Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover... Approved Open
15 Mar 2018 Annual Update on the Work of our Strategic Partnerships - Communities PortfolioDecision The Officer’s report provides an update on the work of the Health and Wellbeing Board and Children’s Trust a... Agreed Open
18 Jan 2018 Policy for Use of Events on Parks and Open SpaceDecision The hosting of events on city parks and open spaces had become increasingly popular with both local and nati... Approved Open
18 Jan 2018 S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies