Community Services Scrutiny Committee approved this item on Thursday 28 June 2012. Below is the council's own wording, with the papers it was decided on.
To consider the project appraisal for the replacement of the Corn Exchange Passenger Lift. Decision of Executive Councillor for Arts, Sport and Public Places: The Executive Councillor resolved to: Financial i. Recommend this scheme (which is not included in the Council’s Capital & Revenue Project Plan) for approval by Council, subject to resources being available to fund the capital and revenue costs. ii. Note that total cost of the project is £14,500, funded from repair and renewal budgets. iii. Note that there are no ongoing revenue implications arising from the project. Procurement iv. Approve the carrying out and completion of the procurement of a replacement passenger lift for the Corn Exchange. The cost is expected to be £14.500.Subject to the permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reason for the As per the officer report Any alternative options considered and rejected: Not Applicable Scrutiny Considerations: Not applicable. The Executive Councillor for Arts, Sport and Public Places approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) N/A
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
To: Executive Councillor for Arts, Sport and Public Places Report by: Cultural Facilities Manager, Steve Bagnall Relevant scrutiny COMMUNITY SERVICES committee: Wards affected: None
Recommendation/s Financial recommendations – • The Executive Councillor is asked to recommend this scheme (which is not included in the Council’s Capital & Revenue Project Plan) for approval by Council, subject to resources being available to fund the capital and revenue costs. • The total cost of the project is £14,500, funded from repair and renewal budgets. • There are no ongoing revenue implications arising from the project.
Procurement recommendations: The Executive Councillor is asked to approve the carrying out and completion of the procurement of a replacement passenger lift for the Corn Exchange. The cost is expected to be £14.500. Subject to the permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%.
D:\MODERNGOV\DATA\PUBLISHED\INTRANET\C00000176\M00000539\AI00006138\$YIWWAIYT.DOC Page 2 of 8
1 Summary To replace the existing passenger and disabled lift in the Corn Exchange which is no longer reliable and therefore fit for purpose.
1.1The project
Target Dates: Start of procurement June 2012 Award of Contract July 2012 Start of project delivery July 2012 Completion of project August 2012
1.2The Cost Total Project Cost £ 14,500
Cost Funded from:
Funding: Amount: Details:
Reserves £
Repairs & Renewals £14,500 Developer £ Contributions Other £
Ongoing Revenue Cost No change to existing Year 1 £ Council Kone maintenance contract Ongoing £
1.3The Procurement Initial indicative quotes have been obtained and 3 quotes will be obtained from suitable suppliers for the project. Page 3 of 8 2 Project Appraisal & Procurement Report
2.1The Project The Corn Exchange passenger lift provides the only disabled and wheelchair access to the normal wheelchair positions in the Corn Exchange. The lift is increasingly unreliable and after a number of maintenance call outs and repairs is now at the end of it’s useful life.
2.2Aims & objectives The aim is to ensure that disabled customers can access the Corn Exchange and that the facilities offered comply with disability access legislation.
2.3Major issues for stakeholders & other departments 2.4 Summarise key risks associated with the project The following risks may occur if the project does not proceed: Inability to offer Wheelchair and disabled access to events at the Corn Exchange.
2.5Financial implications a. Appraisal prepared on the following price base: 2011/12 2.6 Capital & Revenue costs
(a) Capital £ Comments Building contractor / works Purchase of vehicles, plant 14,500 & equipment Professional / Consultants fees IT Hardware/Software Other capital expenditure Total Capital Cost 14,500 Page 4 of 8
2.10Staff required to deliver the project This project will largely be delivered via external contractors. Some planning input will be provided by the Corn Exchange technical team.
2.11Dependency on other work or projects Not Applicable
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.