Community Services Scrutiny Committee approved this item on Thursday 28 June 2012. Below is the council's own wording, with the papers it was decided on.
To consider the Southern Connections – Public Art Commission. Decision of Executive Councillor for Arts, Sport and Public Places The Executive Councillor resolved to: Financial i. Recommend this scheme (which is not included in the Council’s Capital & Revenue Project Plan) for approval by Council, subject to resources being available to fund the capital and revenue costs. ii. Notes that the total cost of the project is £107,446, funded from S106 developer contributions and a planning condition. iii. Note that there are no ongoing revenue implications arising from the project. Procurement iv. Approve the carrying out and completion of the procurement of the Southern Connections public art commission. Subject to: - The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. - The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reason for the As per the officer report Any alternative options considered and rejected: Not Applicable Scrutiny Considerations: The committee received a report from the Public Art Officer regarding South Fringes Art project. The committee made the following comments on the report i. The project was welcomed. ii. It was highlighted that not all members of the public would have mobile phones, or mobile phones which support the use of apps. The comment was noted. iii. It was agreed that Ward Councillors would be appropriately involved The Scrutiny Committee considered and endorsed the recommendations in the report by 4 votes to 0. The Executive Councillor for Arts, Sports and Public Places approved the recommendations. Conflicts of interest declared by the Executive Councillors (and any dispensations granted) N/A
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Executive Councillor for Arts, Sport and Public To: Places Report by: Nadine Black COMMUNITY SERVICES Scrutiny committee: 28/06/12 SCRUTINY COMMITTEE Wards affected: Trumpington and Market
Project Appraisal and Scrutiny Committee Recommendation Project Name: Southern Connections – A wayfinding public art commission
Recommendation/s Financial recommendations –
• The Executive Councillor is asked to recommend this scheme (which is not included in the Council’s Capital & Revenue Project Plan) for approval by Council, subject to resources being available to fund the capital and revenue costs. • The total cost of the project is £107,446, funded from S106 developer contributions and a planning condition. • There are no ongoing revenue implications arising from the project. Procurement recommendations: • The Executive Councillor is asked to approve the carrying out and completion of the procurement of the Southern Connections public art commission.
• Subject to: - The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. Page 2 of 13
- The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%.
1 Summary 1.1 The project
‘Southern Connections’, is a wayfinding project, which aims to highlight the routes from Addenbrooke's Hospital and the new developments in the Southern Fringe with Trumpington and beyond into the City Centre to encourage walking, cycling and leisure activity.
Target Dates: Start of procurement July 2012 Award of Contract October 2012 Start of project delivery November 2012 Completion of project November 2015
1.2Anticipated Cost Total Project Cost £107,446
Cost Funded from:
Funding: Amount: Details:
Reserves £
Repairs & Renewals £ Developer £82,446 See Appendix B Contributions Planning Condition from Other £25,000 Addenbrookes Access Road
Ongoing Revenue Cost
Year 1 £0 Year 1 is project Page 3 of 13
development
Ongoing £
1.3Procurement process For projects of this value the Contract Procedure Rules require a formal invitation to tender to at least 4 candidates after advertising. Whilst it is proposed to seek up to five competitive bids via a tender process, it is intended that the project will not be advertised (and an appropriate waiver will be sought for this). Southern Connections, requires careful thought about the kind of artist required to undertake it and their availability. Many suitable artists would not apply for the project through the advertising route, as they do not necessarliy repsond to advertising and are represented by a Gallery. Detailed research is necessary for the compilation of a long list (against some clear criteria). From this longlist between three and five artists will then be invited to tender (this is a common approach in the public art sector). Limited competition ensures that artist’s with experience and appropriate artistic practice, (which suits the project and who might not normally apply through advertising) can be identified and invited to bid for the project and also this can provide a quicker commissioning process because advertising a commission can result in may unsuitable artists applying to undertake the project. It ensures quality control of all candidates for the project from the outset. The Council has used a Limited Competition approach to commission the artists who are undertaking the Mill Road Cemetery and Snowy Farr projects.
2 Project Appraisal & Procurement Report
2.1Project Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.