Decision The Officer’s report set out the overall base revenue and capital budget position for the Planning and Climate Change Portfolio, as included in the Budget-Setting Report (BSR) 2014/15 to be considered at Strategy & Resources Scrutiny Committee on 20 January 2014. Decision of Executive Councillor for Planning and Climate Change The Executive Councillor resolved to: Review of Charges i. Approve the proposed charges for this portfolio’s services and facilities, as shown in Appendix A of the Officer’s report. Capital ii. Approve, where relevant, project appraisals as shown in Appendix D. iii. Seek approval from the Executive to carry forward resources from 2013/14, as detailed in Appendix C, to fund re-phased capital spending. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Accountant (Services). The Committee resolved by 4 votes to 0 to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1The following report details the budget proposals which relate to this portfolio that are included in the Budget-Setting Report (BSR) 2014/15 to be considered at Strategy & Resources Scrutiny Committee on 20 January 2014.
1.2This report also includes any recommendations concerning the review of charges, project appraisals and capital re-phasing for schemes in the Capital & Revenue Projects Plan for this portfolio.
Recommendations
The Executive Councillor is recommended to:
Review of Charges:
a) Approve the proposed charges for this portfolio’s services and facilities, as shown in Appendix A to this report.
Capital:
b) Approve, where relevant, project appraisals (shown in Appendix D).
Report Page No: 1 c) Seek approval from the Executive to carry forward resources from 2013/14, as detailed in Appendix C, to fund re-phased capital spending.
Background
3.1The overall BSR to Strategy & Resources Scrutiny Committee on 20 January 2014 will include a review of all the factors relating to the overall financial strategy that were included in the Mid-Year Financial Review (MFR) 2013, considered at Council on 24 October 2013.
3.2Further work may be required on detailed budgets therefore delegation to the Section 151 Officer will be sought from Council for authority to finalise changes, for example those relating to technical adjustments to departmental administration, support service and central costs, in accordance with the CIPFA Service Reporting Code of Practice for Local Authorities (SeRCOP).
Budget Proposals
3.3Council will consider budget proposals at its meeting on 27 February 2014. Detailed proposals are included in the appendices listed on the table below.
Appendix Proposal Type Included A Scale of Fees & Charges B Budget Proposals C Capital & Revenue Projects Plan re-phasing D Project Appraisals
Capital
3.4Appendix C shows the latest position against the 2013/14 Capital & Revenue Projects Plan at November 2013 for projects within this portfolio, with variances explained in detail in the accompanying notes.
Report Page No: 2 4. Implications
All budget proposals have a number of implications. A decision not to approve a revenue bid will impact on managers’ ability to deliver the service or scheme in question and could have staffing, equal opportunities, environmental and/or community safety implications. A decision not to approve a capital or external bid will impact on managers’ ability to deliver the developments desired in the service areas.
Implication Comment Financial implications of budget proposals are a Financial summarised in the Budget-Setting Report 2014/15. b Staffing See text above. Equality Impact Assessments have been conducted on all budget proposals where there is a significant service change proposed and, where relevant, will be Equal c reported to each Scrutiny Committee. A consolidated Opportunities Assessment for the Council’s Budget Setting Report will be submitted to the Executive at its meeting on 23 January 2014. Where relevant, officers have considered the environmental impact of budget proposals which are annotated as follows: +H / +M / +L: to indicate that the proposal has a d Environmental high, medium or low positive impact. Nil: to indicate that the proposal has no climate change impact. -H / -M / -L: to indicate that the proposal has a high, medium or low negative impact. Budget Details of the results of the 2013 survey can be found e Consultation on the internet at: http://alturl.com/h9jgw Community See text above. f Safety
Background papers
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.