Decision This project appraisal proposes the re-laying of an existing cycleway across Jesus Green. The footpath would be widened from 2.6 metres to 3.5 metres, and use specialist construction techniques to reduce the potential damage to trees. Lighting columns would also be aligned to one side of the cycle path, and new lanterns installed by the County Council. Decision of Executive Councillor for Planning and Climate Change Financial recommendation i. A pproved the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan. The total cost of the project is estimated at £ 165,570. Procurement recommendations ii. Approved the carrying out and completion of the procurement of the construction of the proposed cycle way improvements, ground de-compaction and lighting works in accordance with the detailed drawings in Appendix A of the Officer’s report. Officers have, using the Braintree Framework Agreement, identified a preferred contractor subject to the approval of the Officer’s report. iii. Procurement subject to: · The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. · The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations Committee did not request this item for pre-scrutiny. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Project Appraisal and Scrutiny Committee Recommendation
Project Name: Jesus Green Footpath / Cycleway improvements Executive Councillor for Planning and Climate To: Change Report by: DIRECTOR OF ENVIRONMENT – SIMON PAYNE Scrutiny committee: ENVIRONMENT 14th January 2014 MARKET Wards affected:
Recommendations Financial recommendations
The Executive Councillor is asked to approve the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan. The total cost of the project is estimated at £ 165,570 £150,000.00 of which will be funded from the Capital Joint Cycleway Programme (PR007). £ 15,570 will be funded from the West/Central Environmental Improvement Programme. There are no on-going revenue implications arising from the project.
1.0Procurement recommendations:
The Executive Councillor is asked to approve the carrying out and completion of the procurement of:
1.1The construction of the proposed cycle way improvements, ground de-compaction and lighting works in accordance with the detailed drawings in Appendix A of this report. Officers have, using the Braintree Framework Agreement, identified a preferred contractor subject to the approval of this report. 1.2 And subject to:
- The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract.
- The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%.
Project Name: Jesus Green Footpath/Cycleway Improvements 1 Summary 1.1 The project
This project appraisal proposes the re-laying of an existing cycleway across Jesus Green. The footpath would be widened from 2.6 metres to 3.5 metres, and use specialist construction techniques to reduce the potential damage to trees. Lighting columns would also be aligned to one side of the cycle path, and new lanterns installed by the County Council.
Target Dates: Delivery April/May 2014 Start of procurement Underway Award of Contract March 2014 Start of project delivery April 2014 April/May 2014 Completion of project April 2015* Date that project output is April/May 2014 expected to become operational (if not same as above) * End of contractual retention period 1.2 Anticipated Cost Total Project Cost £ 165,570
Cost Funded from:
Funding: Amount: Details: Joint Capital Cycleways Capital Programme £ 150,000 Programme PR007 West Central funds EIP funds £ 15,570 PV007
1.3Procurement process If approved, the procurement route will be a continuation of use of the Braintree Framework agreement, which has been used to this point to establish project costs through a competitive quotation process. A preferred contractor has already been identified, and is willing to proceed with the works, subject to the required permissions which are as follows:
Planning permission (Requirement to be confirmed) Temporary Traffic Regulation Order for works to a Public Right of Way 2 Project Appraisal & Procurement Report
2.1The site
Jesus Green is one of the major public open spaces in the City of Cambridge. Dissecting the park, from Jesus Green Lock to the South Eastern entrance way access from Victoria Avenue. The below map shows the section of footpath/cycleway to be widened and improved.
Image 1 The extent of the cycleway for re-surfacing and widening
The condition of the existing cycle path is poor, with ground movement and use causing extensive cracking of the surface and failure at the edges. There is also extensive rutting and compaction of the ground either side of footpath caused by the repeated tracking of vehicles, pedestrians and bicycles on areas around the footpath, which indicates that the footpath is clearly too narrow for its current level of use.
The quality of lighting has also been monitored by the County Council, who have confirmed that is within scope of their existing improvements programme to upgrade lanterns along this cycle path. 2.2 The proposal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.