Cycle Parking Project Appraisal

Approved Scrutiny 5 papers

Environment Scrutiny Committee approved this item on Tuesday 14 January 2014. Below is the council's own wording, with the papers it was decided on.

Item14/21/Env

Resolved

Decision The project aims to provide one thousand additional secure cycle parking spaces in the heart of the city centre. This is planned to be achieved through the provision of: · Localised on-street cycle parking throughout the city centre where space allows and the demand for cycle parking is high. · Introduction of a third undercover secure cycle park, similar to those at Park St and Grand Arcade car parks. The Officer’s report provided an appraisal of the remaining on-street proposals for the project. Feasibility work is currently underway to look at the options for a third undercover secure cycle park. Decision of Executive Councillor for Planning and Climate Change Financial recommendation i. Approved the commencement of the on-street cycle parking proposals detailed in this report, the funding for which is already included in the Council’s Capital & Revenue Project Plan. The total estimated cost of these on-street proposals is £115,000 funded from the City Centre Cycle Parking Project capital allocation SC549. Procurement recommendations ii. Approved the carrying out and completion of the procurement of the construction of the proposed cycle parking locations in accordance with the detailed drawings in Appendix B and C of this report relating to Peas Hill, Guildhall St, Jesus Lane, St Mary’s St and East Road. iii. Procurement subject to: · The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. · The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Project Delivery & Environment Manager. In response to Members’ questions the Project Delivery & Environment Manager said the following: i. Civil enforcement officers had recorded that only seven of nine disabled parking spaces were used in Jesus Lane, therefore bike parking was proposed in the area which would lead eight disabled parking spaces available. ii. The new Peas Hill street layout design aimed to mitigate the impact of illegal parking of disabled parking spaces by separating loading and parking areas. The design should also be an improvement on the current street layout eg more pavement space would be available in front of the café. iii. A variety of bike racks would be available across the city. iv. Undertook to clarify with County Council Highways Officers then advise Members why disabled parking spaces were not available in Guildhall Street. It was suggested that they may impact on traffic flow. The Chair decided that the recommendations highlighted in the Officer’s report should be voted on and recorded separately: The Committee endorsed recommendations ( i ), (ii) relating to Peas Hill, Guildhall St, St Mary’s St and East Road and (iii) unanimously. The Committee endorsed recommendation (ii) relating to Jesus Lane by 4 votes to 0. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

APPENDIX B Revised Proposals for Implementation NOTES LOCATION PLAN - GUILDHALL STREET (1:100) See drawing no 040-018/2600/001 for site location.

See drawing no 040-018/2600/002 for high capacity cycle stand specification and clearances.

Refer to statutory undertakers' plant location information plans, carry out radiodetection survey for underground services and mark on site before carrying out works.

Location of footway build-out, cycle stands and bollards to be marked/agreed on site with engineer before works commence.

KEY

Existing 'Sheffield Hoop' type cycle stand to be removed and set aside for reuse.

Existing noticeboard to be removed and set aside for reuse.

YO! Proposed high capacity cycle stand

28 no high capacity Proposed footway build-out in carriageway cycle racks Proposed 'Cambridge' bollard

SUSHI Existing bollards to be removed and disposed of off site 6 no Sheffield Hoop type "This map is reproduced from Ordnance Survey material cycle stands to be removed Controller of her Majesty's Stationary Office ” Crown with the permission of Ordnance Survey on behalf of the

copyright. Unauthorized reproduction infringes Crown copyright and may lead to prosecutions or civil proceedings." Cambridge City Council (Licence No. 100019730) 2013.

DO NOT SCALE Slot-drain maintenance chamber Figured dimensions must be taken in preference to scaled dimensions. Contractors, sub-contractors and suppliers must verify all dimensions on site before commencing any work or making any shop drawings. Discrepancies to be brought to the contract administrator's / landscape architect's attention. Existing downpipe outfall to be connected into new slot-drain Existing granite kerb to be taken up and set aside for reuse

REV AMENDMENTS DATE Slot-drain to be Marshalls Mono Slot Drain, or similar approved ENVIRONMENT STREETS & OPEN SPACES PROJECT DELIVERY

Precast concrete paving to match Granite setts in area to back of new kerb existing, adjacent surface from Approximate area to be 4.84m x 1.76m Simon Payne The Guildhall to columns, opposite Director of Environment CAMBRIDGE CITY COUNCIL PO BOX 700, Cambridge, CB1 0JH Slot-drain maintenance chamber Tel: (01223) - 457200 or 457201 Granite kerb to be connected to new channel gulley at new kerb face Project CAMBRIDGE CITY CENTRE CYCLE PARKING PROJECT Existing gulley to be filled with concrete and abandoned Drawing CYCLE STAND LOCATIONS Cambridge bollards GUILDHALL STREET

Channel gulley to be constructed at kerb face SITE 4 and connected to existing stormwater sewer DRAFT THE Inlet from slot drain to feed into gulley pot Scale: Date: As shown @ A3 18/10/2013 GUILDHALL Drawn by: Checked by: IHJ

Drawing No:

040-018/2600/008 LOCATION PLAN - PEAS HILL (NTS)

YO! SUSHI

Proposed Proposedhigh highcapacity capacitycycle cycle racks and footway construction previously previously consulted consulted upon upon

ST GEORGE HOUSE e assag ard's P St Edw Statue

FISHER TOURIST HOUSE INFORMATION

Peas Hill

Gu OFFICE THE Proposed seating

ild GUILDHALL

ha area for café

ll S (5m x 6m = 30m²)

tre CHURCH OF ST MARY THE GREAT

e t DIS AB

Gu LE D

ild DIS

ha AB LE D

ll Pl ac e THE COW age (PH) St Edward's Pass

LOADING ONLY ESSENSUALS

ONLY LOADING Proposed loading bay, 20.5 metres in length CAMBRIDGE ARTS THE CORN LED THEATRE DISAB

et EXCHANGE

Pa tre HAIRY

rso S ler ED

CANARY ee DISABL

n Wh

's C Proposed disabled parking bay CORN EX. BOX OFF. to accommodate 4 no. cars

ou ED DISABL

rt NO OD JIN BAR LE CALLY CO

G- LIN (no. G TH (no E P . 10

11 INT )

) AROMI SH OP

eet THE ANGEL THE BATH BOOKSHOP 't Str HOUSE (PH) ne ZIZZI Be (no. 15) NOTES LOCATION PLAN - PEAS HILL (1:200) See drawing no 040-018/2600/001 for site 8 no Sheffield Hoop type location. cycle stands to be removed See drawing no 040-018/2600/002 for high capacity cycle stand specification and clearances.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cycle Parking APPENDIX B /21/EnvAppendix 901 KB DownloadRead as text
PDF
Cycle Parking APPENDIX C /21/EnvAppendix 315 KB Download
PDF
Cycle Parking APPENDIX D /21/EnvAppendix 151 KB Download
PDF
Cycle Parking APPENDIX E /21/EnvAppendix 59 KB Download
PDF
Cycle Parking Project AppraisalAppendix 122 KB Download

At this meeting

Whole meeting
14/3/EnvMinutesOn the agenda 14/5/EnvaDelegation to South Cambridgeshire District Council 1: Prosecute Under the Environmental Protection Act 1990On the agenda 14/5/EnvbDelegation to South Cambridgeshire District Council 2: Enforcement Action Under the Environmental Protection Act 1990On the agenda 14/5/EnvcReported Overspend on Replacement of Grand Arcade Car Park Management SystemOn the agenda 14/5/EnvdParker’s Piece Lighting ProjectOn the agenda 14/5/EnveSplash Pad Projects and Revised use of Developer Contributions FundingOn the agenda 14/7/EnvPublic Places Portfolio Revenue and Capital Budgets 2013/14 (Revised), 2014/15 (Estimate) and 2015/16 (Forecast)Approved 14/9/EnvChanges to the River Moorings PolicyAgreed 14/10/EnvEnvironmental & Waste Services Portfolio Revenue and Capital Budgets 2013/14 (Revised), 2014/15 (Estimate) and 2015/16 (Forecast)Approved 14/11/EnvProposed Change to Subsidised Working with the County Council in Relation to Grass Cutting of VergesAgreed 14/12/EnvCharging for the Second Green Bin ServiceApproved 14/13/EnvCessation of the Pest Control ServiceApproved 14/14/EnvJesus Green Shared Cycle and Foot Path ImprovementsApproved 14/15/EnvPerne Road/Radegund Rd RoundaboutApproved 14/16/EnvPlanning & Climate Change Portfolio Revenue and Capital Budgets 2013/14 (Revised), 2014/15 (Estimate) and 2015/16 (Forecast)Approved 14/17/EnvSustainable City Grants 2014-15Approved 14/18/EnvConservation Area Appraisal for The KiteAgreed 14/19/EnvArticle 4 Directions - Public Houses and Buildings of Local InterestApproved 14/20/EnvArticle 4 Direction - Accordia EstateNoted
14/21/EnvCycle Parking Project AppraisalThis decision
14/22/EnvCambridge Local Plan 2014Approved

Who was there

9 of 9 attended
SK
Councillor Simon KightleyChair, present
PS
Councillor Paul SaundersVice-Chair, present
KB
Councillor Kevin Blencowe Labour Spokes for Planning and Climate ChangeCommittee Member, present
SB
Councillor Simon BrierleyCommittee Member, present as substitute
NG
Councillor Nigel GawthropeCommittee Member, present
CO
Councillor Carina O'Reilly Labour Spokes for Public PlacesCommittee Member, present
SR
Councillor Sian ReidCommittee Member, apologies, sent representative
PR
Councillor Peter Roberts Labour Spokes for Environmental and Waste ServicesCommittee Member, present
DT
Councillor Damien TunnacliffeCommittee Member, present

On this subject at Cambridge

Search all
  1. Cycle Parking Project AppraisalThis decision
  2. Cambridge Cycle Parking ProjectAgreed
  3. City Centre Cycle ParkingDecided
  4. Cambridge City Centre Cycle Parking ProjectAgreed

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies