Community Services Scrutiny Committee, Thursday 16 October 2014 at 2.30pm

CLAY FARM COMMUNITY CENTRE

Approved Scrutiny 1 paper

Community Services Scrutiny Committee approved this item on Thursday 16 October 2014. Below is the council's own wording, with the papers it was decided on.

Item14/55/CS

Resolved

Decision The Clay Farm Community Centre project was considered by the Community Services Scrutiny Committee in January 2012 and the Executive Councillor for Community Development and Health, approved that the project should proceed. The project had now reached the stage where tenders had been received to build the new Community Centre. Due to build cost inflation the budget for the project had increased significantly although the increased contribution required from the Council was more marginal. This was because of the partnership nature of the project and because funding for the project comes from a number of sources, much of which was building cost index linked. Nevertheless, as the project had reached a key point and in view of the budget variation it was felt appropriate for the Committee to scrutinise the project again at this stage. Decision of Executive Councillor for Community, Arts and Recreation The Executive Councillor resolved: i. to approve the revised budget for the project of £10,950,000. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of the Strategic Housing regarding Clay Farm Community Centre. He clarified why this report had been submitted late and the importance of making this decision in a timely and open fashion. He explained that cost had risen but so had contributions from partners to the project. Members noted that the increase in borrowing requested from the Council under consideration was £3.02m rather than the original figure of £2.8m. The Committee made the following comments in response to the report: i. Members expressed satisfaction with the report and understood the need for the increase. ii. Stated that the project was worthwhile. The Committee resolved unanimously to endorse the recommendation. The Executive Councillor approved the recommendation. The Committee requested that the minutes noted their appreciation for the contribution that the Head of Community Development had made during his time with the Council and wished him well for the future.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Community Services Scrutiny Committee

Executive summary

This project was considered by the Customer and Community Services Committee in January 2012 and the Executive Councillor approved that the project should proceed. The project has reached the stage where tenders have been received to build the new Community Centre. Due to build cost inflation the budget for the project has increased significantly although the increased contribution required from the Council is more marginal. This is because of the partnership nature of the project and because funding for the project comes from a number of sources, much of which is building cost index linked. Nevertheless, as the project has reached a key point and in view of the budget variation it was felt appropriate for the Committee to scrutinise the project again at this stage.

Recommendations

The Executive Councillor is recommended to approve the revised budget for the project of £10,950,000.

Report Page No: 1 3. Background

The City Council is leading the partnership project to provide the new multi- use Community Centre at the heart of Clay Farm. The Community Centre will sit on City Council land and therefore the City Council is the lead partner. Other partners include the local General Practice backed by the NHS; the County Council; and bpha (Affordable Housing provider). A representative from Trumpington Residents Association is part of the partnership Project Group.

Situated at centre of the Southern Fringe Growth site, the Clay Farm Community Centre will be a high profile building that reflects the Council’s objectives to promote high quality and sustainable development. By the time the Centre is built in Spring 2016 about 40% (2000) of the new homes on the Southern Fringe will be occupied.

The following facilities were required to be provided in the new Clay Farm Community Centre from the outset of the project.

• a community centre: comprising a multi-use hall with sprung floor, suitable for performance and exhibition, and flexible meeting rooms • a community café large enough to be viable • a youth wing with games area, band & DJ room, and space for craft activities. • a public library with internet access and areas for lending and reading materials • a health centre with consultation rooms for eight general practitioners, flexible spaces for primary care support services, waiting areas, and a minor surgery suite • residential accommodation – up to 20 affordable flats • touchdown facilities and accommodation for police and social services and other providers • car parking for essential staff and emergency vehicles with external areas for community use

The Design Code for this part of the Southern Fringe development calls for a building of between three and five storeys in this location. In order to achieve the height and stature required the concept for the building is for the community facilities to occupy the ground and first floors; the Health Centre to occupy the second floor; with the Affordable Housing units on floors three and four.

The following approvals have been agreed to-date;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CLAY FARM COMMUNITY CENTREReport 103 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
ZM
Councillor Zoe MoghadasChair, present
DR
Councillor Dan RatcliffeVice-Chair, present
YA
Councillor Ysanne AustinCommittee Member, present
DB
Councillor Dave BaigentCommittee Member, present
SR
Councillor Sian Reid Lib Dem Spokes for Community, Arts and RecreationCommittee Member, present
AR
Councillor Andrea Reiner Lib Dem Spokes for City Centre and Public PlacesCommittee Member, present
PS
Councillor Peter SarrisCommittee Member, present
AS
Councillor Ann SinnottCommittee Member, present

On this subject at Cambridge

Search all
  1. CLAY FARM COMMUNITY CENTREThis decision
  2. Review of Shared Ownership Housing at Virido, Clay FarmApproved
  3. 17/1461/REM: Cycleway/footway - Land Adjacent to Cambridge Guided Busway and Adjacent to existing plantation within abode 1 (Parcels 10, 11 and 12), Clay Farm, Trumpington, Cambridge.Decided
  4. 16/2149/REM: Land between 125 and 129 Shelford Road and Clay Farm Parcel 12CApproved
  5. AI/JS/39/117: Clay Farm development, Public Footpath 117- running along the rear of Foster Road propertiesApproved
  6. Review of Governance Arrangements for Clay Farm Community CentreAgreed

More from Cambridge Community Services Scrutiny Committee

All decisions
MeetingDecisionOutcome
15 Mar 2018 Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a... Refused Open
15 Mar 2018 Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover... Approved Open
15 Mar 2018 Annual Update on the Work of our Strategic Partnerships - Communities PortfolioDecision The Officer’s report provides an update on the work of the Health and Wellbeing Board and Children’s Trust a... Agreed Open
18 Jan 2018 Policy for Use of Events on Parks and Open SpaceDecision The hosting of events on city parks and open spaces had become increasingly popular with both local and nati... Approved Open
18 Jan 2018 S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies