Resolved
Resolved (unanimously) to note and accept the conclusions in [name removed] independent review of the Marque development, and its recommendations.
Planning noted this item on Wednesday 4 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved (unanimously) to note and accept the conclusions in [name removed] independent review of the Marque development, and its recommendations.
BRIEF FOR THE INDEPENDENT REVIEW OF THE MARQUE SCHEME, HILLS ROAD CHERRY HINTON ROAD JUNCTION, CAMBRIDGE
1. Objectives for the review:
That the review of the final construction of the Marque scheme identifies learning and lessons and addresses the following questions:
a - What can be learnt from the processes and decisions that led to the final design and construction of the Marque b - How have improved processes implemented since the first Marque application in 2005 addressed (i) improved delivery on major development particularly tall buildings, and (ii) how will such improved processes support delivery after Local Plan adoption c - Are the circumstances of this case unique (in comparison to other similar schemes in the city) or are further measures needed to assist the council in delivering successful major developments and tall buildings in future.
2. Content of the review:
The review will need to address these key questions:
the processes that led in between 2005 and 2008 to the original approval for the screen and building design, and what was actually agreed, including given the different views about whether the final building is consistent to that approval the role of the Conservation and Design Panel, the planning case officer and the Urban Design Team in such applications technical advice on innovative construction options, in this case the screen design and planned material and support management of multi-year applications including when developers undertake major renegotiation and value engineering, and where sites with planning applications are sold on delegation and delivery on 'non material amendments', including in this case the Judicial Review and the impact of multiple NMAs eg on the east facing side of the building impact of the design on future residents of the Marque including those with restricted views, and future screen upkeep costs s106 delivery of public art to ensure value for money public benefit from developer-controlled 1% schemes difficulties in delivering 'Management Agreement' conditions including public access Member involvement transparency and scrutiny from 2005 to 2014.
3. Outcomes from the review
The Council is looking for a final written report structured to address the review objectives set out in 1 above, covering the investigation of the issues set out in 2 above. The reviewer will be asked to present the review findings to the Planning Committee and answer questions from Members on their conclusions.
4. Schedule of the review
The review shall be completed within 3 months of the commission being accepted.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BRIEF FOR THE INDEPENDENT REVIEW OF THE MARQUE SCHEME /46/PlanReport | 69 KB | DownloadRead as text |
PDF |
Barry Shaw Report /46/PlanReport | 2 MB | Download |
PDF |
The Marque Scheme ReviewReport | 121 KB | Download |
Follow Planning at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Nov 2026 | 26/02186/FUL Coldham's Common, Pool Way, Whitehill RoadResolved (by 7 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... | Decided | Open |
| 24 Jun 2026 | 25/04187/FUL Hanover Court and Princess CourtResolved (by 4 votes to 3) to grant the application for planning permission in accordance with the Officer recommenda... | Agreed | Open |
| 24 Jun 2026 | 25/03323/FUL 73 Newmarket RoadResolved (4 votes to 4 – and on the Chair’s casting vote) to grant the application for planning permission in accorda... | Agreed | Open |
| 24 Jun 2026 | 26/01081/FUL 9, 11, 15 and 17 Ashfield RoadResolved (by 6 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... | Decided | Open |
| 24 Jun 2026 | 26/01400/FUL 1, 2, 3, 4, 11, 12 The GreenResolved (by 5 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.