Resolved (unanimously to accept the officer recommendation (as amended) to: i. Authorise an enforcement notice under S172 of the Town and Country Planning Act 1990 (as amended) in respect of a breach of planning control, namely the unauthorised operational development consisting of the erection of a roof dormer at 45 Elfleda Road specifying the steps to comply and the period for compliance set out in paragraphs 5.2 and 5.3 of the Officer’s report, for the reasons contained in paragraph 5.4. ii. Authorise the Head of Planning Services (after consultation with the Head of Legal Services) to draft and issue the enforcement notice. iii. Delegate authority to the Head of Planning Services (after consultation with the Head of Legal Services) to exercise the Council’s powers to take further action in the event of noncompliance with the enforcement notice.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
PLANNING ENFORCEMENT CONTROL ENFORCEMENT NOTICE REPORT
45 Elfleda Road, Cambridge Unauthorised operational development relating to the erection of a roof dormer
SUMMARY A planning enforcement investigation has identified unauthorised development at the above address, namely the erection of a roof dormer without planning permission. The development is not acceptable because it is considered to be out of keeping with the property and local area.
RECOMMENDATION That enforcement action is authorised in respect of the breach of planning control to serve an enforcement notice.
1 INTRODUCTION
This report seeks delegated authority to serve an Enforcement Notice to address the unauthorised development at 45 Elfleda Road, Cambridge, namely, “Without planning permission the erection of a roof dormer.” See appendix A for site plan.
2 PLANNING HISTORY Reference Description Outcome
13/0265/FUL First floor side extension Perm
14/1998/FUL Loft conversion Application invalid at time
Report Page No: 1 Agenda Page No: of writing report
3 BACKGROUND / TIMELINE OF ENFORCEMENT INVESTIGATION 3.1 Officers received a complaint in October 2014 advising that a roof dormer was under construction that may require planning permission.
3.2A site inspection was made in which it was confirmed that the works undertaken failed to benefit from permitted development by virtue of its size and also the materials used which significantly alter the external appearance of the dwelling, and as such requires formal planning permission.
3.3Officers considered that the works as built would be unlikely to be supported if an application were to be submitted. A letter was sent inviting an application for an amended scheme/proposal.
3.4No application was received within the period originally requested and officers therefore contacted the owners to advise that formal action was being considered.
3.5Contact was received from the owners in which they stated that the works had been constructed under permitted development. Advice was given as to why the works failed to benefit from the provisions and an extension was given to allow an application to be made.
3.6An application was received on 13.12.2014 but required further information to validate it. Two letters have been sent chasing the outstanding information.
3.7To date the application remains invalid and the drawings that have been submitted show the dormer as built, which officers have already advised is unlikely to be supported and therefore refused.
3.8Officers have tried to resolve the breach of planning control informally. A number of months have passed and the dormer is substantially complete.
3.9Officers have advised the owner of 45 Elfleda Road that this report has been prepared for members to consider the service of an Enforcement Notice for the unauthorised operational development.
3.10Particular consideration has been given to the steps to comply. The steps require the full removal of the dormer as, by virtue of the
Report Page No: 2 Agenda Page No: materials used not matching the existing dwelling, it cannot be reduced to comply with permitted development allowances.
4 ASSESSMENT AGAINST PLANNING POLICY AND OTHER MATERIAL CONSIDERATIONS 4.1 The National Planning Policy Framework states:
‘Para 207 Effective enforcement is important as a means of maintaining public confidence in the planning system. Enforcement action is discretionary, and local planning authorities should act proportionately in responding to suspected breaches of planning control. Local planning authorities should consider publishing a local enforcement plan to manage enforcement proactively, in a way that is appropriate to their area. This should set out how they will monitor the implementation of planning permissions, investigate alleged cases of unauthorised development and take action where it is appropriate to do so.’
4.2National Planning Policy Guidance states:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.