Cambridge City Council
Strategy and Resources Scrutiny Committee, Monday 19 March 2018 at 5.00pm

Cambridge Northern Fringe East

Noted Scrutiny 1 paper

Strategy and Resources Scrutiny Committee noted this item on Monday 19 March 2018. Below is the council's own wording, with the papers it was decided on.

Item18/24/SR

Resolved

Decision The report was intended to update the Executive Councillor and the Committee on the current status and proposals for the site and to recommend next steps. Decision of Executive Councillor for Strategy and Transformation i . To note the current status, indicative proposals and target timescales for the programme and the continued engagement with Homes England on progression with the HIF bid. ii. Approved the timeline for the Master Developer tender process and delegate the final approval to the Strategic Director, in consultation with the Executive Councillor and Opposition Spokesperson, noting that the decision to run a procurement in order to identify a master developer, was in consultation with the Leader, recognising that the offer was not certain at point of tender. iii. To establish the terms for an appropriate joint venture vehicle, working with the Strategic Director, Anglian Water and advisers, subject to HIF bid outcome. iv. Noted the proposed timetable for preparing the CNFE Area Action Plan for the proposed wider boundary area (contained in paragraph 4.2.6 and appendix 2a), which is programmed to run in tandem with the HIF bid and with the subsequent regulatory process required for relocation of the Cambridge Water Recycling Centre. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Strategic Director. The Committee made the following comments in response to the report: i. Questioned whether 7600 homes would be able to be built and delivered on the site. ii. Requested that Opposition Councillors were included to develop the Area Action Plans. iii. Questioned where the water treatment plant would relocate to if the Housing Infrastructure Fund (HIF) bid was successful. The Strategic Director and the Group Property Director from Anglian Water said the following in response to Members’ questions: i. The HIF bid put forward a proposal of 5000 houses on the core site which was owned partly by Anglian Water and partly by the City Council but it was hoped that if the core site got approval that this would be a catalyst to build further housing. Anglian Water and the City Council did not own land beyond the core site and therefore the housing figures above 5000 houses were speculative figures. ii. Confirmed that if the HIF bid was successful then officers planned to do more work and involve Opposition Councillors. iii. Confirmed that if the HIF bid was successful Anglian Water would have to go through a process to look for alternative sites to relocate to. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Executive summary

1.1The Cambridge Northern Fringe East (CNFE) site (see Appendix 2), situated south of the A14, west of the science park and north of the Cambridge business park, is one of the last large scale brownfield development regeneration sites suitable for housing development in Cambridge. The location beside the A14, Cambridge North Station, the guided bus way and the Chisholm Trail, make this a highly accessible and sustainable location. The whole CNFE area encompasses around one square kilometre within the City and South Cambridgeshire.

1.2The core site of around 49ha, (about 50% of the whole CNFE area) is owned by Anglian Water Authority and Cambridge City Council and is located within Cambridge City Council boundary. It currently houses the Cambridge Water Recycling Centre (CWRC). The relocation of this is key to unlocking the potential both for this site and for the wider area, but the cost of relocation has rendered potential development unviable in previous years.

1.3The launch of a national Housing Infrastructure Fund (HIF) programme round in the autumn of 2017 offered an immediate opportunity to address this issue. A successful outcome for the bid for funding for the relocation of the CWRC would provide the potential to progress this unique strategic site through a comprehensive mixed use development.

1.4The Council and Anglian Water are committed to developing and agreed joint vision for the core site through the area action plan to promote a new and innovative quarter for Cambridge, creating a high quality and attractive and sustainable place to live, work, learn and play through a high density residential and mixed use development graced by impressive design and public realm, networked into the city.

1.5The HIF bid is still in progress, with the outcome of the expression of interest stage expected in March, and the final outcome expected before the end of 2018. At this time the Council and Anglian Water are focussing on ensuring that they are well prepared to progress the major programme required, once the HIF outcome is confirmed, as deliverability is a key criteria for HIF success.

1.6With this in mind, current activity is focussed in 4 main areas:

 Progressing the HIF bid  Procuring a master developer for the core site, subject to HIF outcome  Initiating development of the Area Action Plan covering the wider site allocation of Cambridge Northern Fringe East  Establishing an agreed joint venture delivery vehicle and governance structure, with the intention of formalising these once HIF bid outcome is confirmed

1.7This report is intended to update the Executive Councillor and Committee on the current status and proposals for the site and to recommend next steps actions.

Recommendations

The Executive Councillor is recommended to:

2.1Note the current status, indicative proposals and target timescales for the programme and the continued engagement with Homes England on progression with the HIF bid.

2.2To approve the timeline for the Master Developer tender process and delegate the final approval to the Strategic Director, in consultation with the Executive Councillor and Opposition Spokesperson, noting that the decision to run a procurement in order to identify a master developer, was in consultation with the Leader, recognising that the offer was not certain at point of tender.

2.3To establish the terms for an appropriate joint venture vehicle, working with the Strategic Director, Anglian Water and advisers, subject to HIF bid outcome.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cambridge Northern Fringe EastReport 1.2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
SB
Councillor Sophie BarnettChair, present
DB
Councillor Dave BaigentVice-Chair, present
TB
Councillor Tim Bick Lib Dem Spokes for Strategy & TransformationCommittee Member, present
RC
Councillor Rod Cantrill Lib Dem Spokes for Finance and ResourcesCommittee Member, present
PS
Councillor Peter SarrisCommittee Member, present
AS
Councillor Ann SinnottCommittee Member, present

On this subject at Cambridge

Search all
  1. Cambridge Northern Fringe EastThis decision
  2. Cambridge Northern Fringe East - Equality Impact AssessmentAgreed
  3. Cambridge Northern Fringe Issues and Option 2Approved
  4. Cambridge Northern Fringe EastNoted
  5. Cambridge Northern Fringe East Area Action Plan – Issues and Options Consultation FeedbackNoted
  6. Cambridge Northern Fringe East Area Action Plan - Issues and OptionsNoted

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies