Strategy and Resources Scrutiny Committee, Monday 8 October 2018 at 5.00pm

Cambridge Northern Fringe East

Noted Scrutiny 1 paper

Strategy and Resources Scrutiny Committee noted this item on Monday 8 October 2018. Below is the council's own wording, with the papers it was decided on.

Item18/57/SR

Resolved

Decision of the Executive Councillor for Finance and Resources i. Noted the current status of the Housing Infrastructure Fund (HIF) bid, the continued engagement with Homes England and wider partners on the development of the business case, and the intention to submit a business case in December 2018, with the expectation of receiving a final outcome decision in early 2019. ii. Approved the appointment of the preferred bidder, U&I, as the Master Developer for the core site, subject to final contracting as referred in 2.3. iii. Approved the establishment of a joint venture with Anglian Water, in line with the confidential draft heads of terms appended to this report in Appendix 4 iv. Delegated to the Strategic Director, in consultation with the Exec Cllr and in line with legal and financial advice: a. Approval of the final Joint Venture Agreement b. Subsequent approval of the Master Development Agreement with U&I c. The development and submission of the business case for HIF funding d. The progression, in line with the MDA requirements, of the development of a business plan covering the core site within six months of the contract being awarded. v. Noted the timescales related to the HIF funding, and the progression of the associated planning framework with SCDC and the proposed consent route, which require agreement with the local planning authorities and partners as to the appropriate arrangements to meet the timescales involved. vi. Noted that all contractual commitments to the MDA and Joint Venture Agreement at this stage are only approved subject to the HIF outcome. vii. Agreed to provide a further progress report to this Committee following final confirmation of the HIF outcome. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Strategic Director. The Committee made the following comments in response to the report: i. Noted the division of roles that the council had, one as a developer and the other as a decision maker for planning applications and asked for assurances that there would be a clear separation between the two roles. ii. Asked what the relationship was between the Area Action Plan (AAP) and the Masterplan for the site. iii. Asked if there were any clawback arrangements regarding the HIF bid if it was successful. iv. Asked if the Council had considered what would happen if the Water Recycling Centre could not be relocated. v. Asked if a planning application could be submitted to underpin the HIF application. vi. Asked when a ‘plan B’ option for the development of the area around the Water Recycling Centre site would be taken forward if the HIF bid was not successful. vii. Asked what the costs would be for the council if the HIF bid was unsuccessful. The Strategic Director said the following in response to Members’ questions: i. The Council was mindful of its role as part-landowner and the County Council would be the local planning authority for any future application to move the water treatment works. The Council would work with all parties involved to ensure the most appropriate development was brought forward on the site. ii. The AAP set the framework for the large development area and brought all the landowners and developers together. The Masterplan would be developed alongside the AAP to bring specific development with the AAP area forward. iii. The Department for Communities and Local Government (DCLG) stated in their expression of interest and business case documentation that the grant was not provided freely, there were levels of uplift and how this would be utilised. iv. There was a level of risk with the work being put into the HIF bid that it may not be successful, however the quality of the work that had gone into the bid was hoped to be good enough to ensure a successful outcome. v. A planning application could not be submitted to accompany the HIF bid because this required a site for the relocation of the water recycling centre to be identified and this piece of work (identification of a preferred site) was currently being undertaken. vi. Commented that if the HIF bid was not successful then there would be no funding available to relocate the water recycling centre. It was understood that the water recycling centre did not need to relocate as it had sufficient capacity on site to be able to upgrade its facilities when / if the time arose. vii. Had tried to reduce the amount of costs for the HIF bid for example some of the work was undertaken in-house for example the OJEU process and legal agreements had been put in place that were conditional upon a successful HIF bid. The Executive Councillor for Strategy and External Partnerships commented that: i. He commended the work that had been done by the Strategic Director and her team, Anglian Water, South Cambridgeshire District Council the Combined Authority and other partners. Half a million pounds had been budgeted for the work undertaken on the project this year. He wanted to ensure that the MHCLG worked to the projects timescales and provided a decision on the HIF bid by February 2019 so that the city council did not spend money un-necessarily. The Water Recycling Centre site was a brownfield site which had complications however it was hoped to build 40% affordable housing on the site which equated to approximately 2000 houses. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Executive summary

1.1The Cambridge Northern Fringe East (CNFE) site, situated south of the A14, west of the science park and north of the Cambridge business park, is one of the last large scale brownfield development regeneration sites suitable for housing development in Cambridge. The location beside the A14, Cambridge North Station, the guided bus way and the Chisholm Trail, make this a highly accessible and sustainable location. The whole CNFE area encompasses around one square kilometre within the City and South Cambridgeshire.

1.2The core site of around 49ha, (about 50% of the whole CNFE area) is owned by Anglian Water Authority and Cambridge City Council and is located within Cambridge City Council boundary. It currently houses the Cambridge Water Recycling Centre (CWRC). The relocation of this is key to unlocking the potential both for this site and for the wider area, but the cost of relocation has rendered potential development unviable in previous years.

1.3The launch of a national Housing Infrastructure Fund (HIF) programme round in the autumn of 2017 offered an immediate opportunity to address this issue. A successful outcome for the bid for funding for the relocation of the CWRC would provide the potential to progress this unique strategic site through a comprehensive mixed use development.

1.4A report to this committee in March 2018 received approval to progress the OJEU procurement for the Master Developer and to establish the Heads of Terms for a Joint Venture

1.5Current activity has been focussed in 4 main areas:

 Progressing the HIF bid  Procuring a master developer for the core site, subject to final contracting once the Joint Venture is formed and to the HIF outcome  Initiating the issues and options stage of the Area Action Plan covering the wider site allocation of Cambridge Northern Fringe East  Establishing an agreed joint venture delivery vehicle and governance structure, with the intention of formalising these once HIF bid outcome is confirmed

1.6This report is intended to update the Executive Councillor and Committee on the current status and proposals for the site and to recommend next steps actions.

2.0Recommendations The Executive Councillor is recommended to: 2.1 Note the current status of the HIF bid, the continued engagement with Homes England and wider partners on the development of the business case, and the intention to submit a business case in December 2018, with the expectation of receiving a final outcome decision in early 2019. 2.2 Following the OJEU procurement process, to approve the appointment of the preferred bidder, U&I, as the Master Developer for the core site, subject to final contracting as referred in 2.3. 2.3 To approve the establishment of a joint venture with Anglian Water, in line with the confidential draft heads of terms appended to this report in Appendix 4 2.4 Delegate to the Strategic Director, in consultation with the Exec Cllr and in line with legal and financial advice:  Approval of the final Joint Venture Agreement  Subsequent approval of the Master Development Agreement with U&I  The development and submission of the business case for HIF funding  The progression, in line with the MDA requirements, of the development of a business plan covering the core site within six months of the contract being awarded.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cambridge Northern Fringe EastReport 1.2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
SB
Councillor Sophie BarnettChair, present
DB
Councillor Dave BaigentVice-Chair, present
TB
Councillor Tim Bick Lib Dem Spokes for Strategy & External PartnershipsCommittee Member, present
JD
Councillor Jamie DalzellCommittee Member, present
KG
Councillor Kelley GreenCommittee Member, present
MS
Councillor Mike SargeantCommittee Member, present
LH
Councillor Lewis HerbertExecutive Councillor, present
RR
Councillor Richard RobertsonExecutive Councillor, present

On this subject at Cambridge

Search all
  1. Cambridge Northern Fringe EastThis decision
  2. Cambridge Northern Fringe East - Equality Impact AssessmentAgreed
  3. Cambridge Northern Fringe Issues and Option 2Approved
  4. Cambridge Northern Fringe EastNoted
  5. Cambridge Northern Fringe East Area Action Plan – Issues and Options Consultation FeedbackNoted
  6. Cambridge Northern Fringe East Area Action Plan - Issues and OptionsNoted

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies