Cambridge City Council
Housing Scrutiny Committee, Tuesday 19 June 2018 at 5.30pm

New Social Housing, Community Centre and Commercial Units on Akeman Street

Approved Scrutiny 3 papers

Housing Scrutiny Committee approved this item on Tuesday 19 June 2018. Below is the council's own wording, with the papers it was decided on.

Item18/25/HSC

Resolved

Decision The report sought approval for the delivery route and a revised capital budget for a Housing Revenue Account (HRA) site at 74-82 Akeman Street. The scheme was based on the indicative capacity study which had been undertaken for the site and the outline appraisals referenced as detailed in the Officer’s report. Decision of Executive Councillor for Housing i. Noted the indicative mix of the proposed scheme to include a mix of affordable housing (8 one bedroom flats and 6 two bedroom flats), 3 replacement commercial units and a replacement community centre. ii. Noted the replacement of 82 Akeman Street with a City Council managed centre which was approved as priority as part of the Community Centres Strategy as the evidence base supports it being a strategically important centre due to its area of high need for outreach iii. Approved the indicative capital budget for the scheme of £3,731,180 to cover all of the construction costs, professional fees and associated fees to deliver a scheme that meets an identified housing need in Cambridge City as well as re-providing the community spaces and commercial units. An indicative budget of £4,118,680 was included in the Housing Capital Investment Plan approved in January 2018, recognising the desire to be in a positon to proceed with the higher density scheme. iv. Approved that the site was offered to Cambridge Investment Partnership ( CIP) to progress for development to deliver a scheme which will meet the strategic aims of the Council in the delivery of new social housing. The scheme would be developed in accordance with the CIP process which was approved at Strategy & Resources Committee on 9 th October 2017. v. Noted that the Executive Councillor had a delegated authority to approve the transfer of land to CIP for the redevelopment of the site at a later date. This would be subject to CIP demonstrating that its development proposal meets the Council’s strategic aims for the site and the development and delivery milestones are in accordance with the CIP Approvals Process agreed at Strategy & Resources Committee on 9 th October 2017. vi. Approved the cost of the community centre re-provision in line with Local Plan policy 5/11 (Protection of Existing Facilities), to be met from the HRA as part of the overall scheme cost, as there would be a planning requirement (as part of the Local Plan) to re-provide this to allow the housing development to proceed. vii. Approved the cost of the commercial provision to be met from the HRA, as the existing commercial offering on the site is HRA owned, with the assumption that the ongoing revenue stream would also fall to the HRA to replace that lost through the vacation and demolition of the existing provision. Consideration had been given to the General Fund acquiring the commercial units either at the outset or in the future, and the Officer’s report recommended this option was considered in the future, if deemed appropriate, with all the required transactions and resulting impact between the two funds fully quantified Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Housing Development Officer. The Committee made the following comments in response to the report: i. Welcomed the assurance that existing tenants would be able to return to the site if they choose to do so. ii. Discussed concerns that existing commercial traders were not guaranteed the return and if they choose to do so would face higher rents. iii. Stated that they were small traders who provided a service to the community. In response to Members’ questions Strategic Director (Fiona Bryant) confirmed that the Hill Group would deliver the build in a timely fashion. They would recruit staff as required for the various sites they were delivering across the area. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendation.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Executive summary

1.1The City Council has agreed a devolution deal with government to deliver 500 new Council homes over 5 years. These will be delivered as rented housing, let in accordance with the Council rent policy (where rent and service charges together do not exceed Local Housing Allowance levels). Homes will be owned and managed by Cambridge City Council and let on Cambridge City Council tenancies.

1.2In 2016 the Strategy and Resources Scrutiny Committee approved the setting up of the Cambridge Investment Partnership (CIP) as a mechanism for the Council to bring forward assets for development to provide sites for the delivery of new homes. This partnership brings with it the advantage of the experience and resources of the development partners and was established in January 2017.

Report page no. 1 Agenda page no. 1.4 At the Strategy & Resources Scrutiny Committee held on 9th October 2017 a mechanism for the development and delivery of sites with CIP was agreed and is being adopted for a number of sites.

1.5The City Council has alternative procurement and delivery options which it is currently exploring and utilising for the delivery of affordable housing on sites in the City.

1.6This report provides a revised scheme, with increased density, for the HRA site at 74-82 Akeman Street. The first iteration of the scheme, delivering 10 residential units was presented to Housing Scrutiny Committee in January 2016, with updates as part of the HRA Budget Setting Report and Development Programme in January 2018.

1.7The development was approved in principle in January 2016; with a commitment to return with a revised scheme once the outcome of the Community Centre provision review was available, ensuring that account was taken of any need for community facility provision in the area.

1.8The report seeks approval for the delivery route and a revised capital budget for the scheme based on the indicative capacity study which has been undertaken for the site and the outline appraisals referenced in this report.

Recommendations

The Executive Councillor is recommended to:

2.1Note the indicative mix of the proposed scheme to include a mix of affordable housing (8 one bedroom flats and 6 two bedroom flats), 3 replacement commercial units and a replacement community centre.

2.2Note the replacement of 82 Akeman Street with a City Council managed centre which was approved as priority as part of the Community Centres Strategy as the evidence base supports it being a strategically important centre due to its area of high need for outreach

Report page no. 2 Agenda page no. 2.3 Approve the indicative capital budget for the scheme of £3,731,180 to cover all of the construction costs, professional fees and associated fees to deliver a scheme that meets an identified housing need in Cambridge City as well as re-providing the community spaces and commercial units. An indicative budget of £4,118,680 was included in the Housing Capital Investment Plan approved in January 2018, recognising the desire to be in a positon to proceed with the higher density scheme.

2.4Approve that the site is offered to CIP to progress for development to deliver a scheme which will meet the strategic aims of the Council in the delivery of new social housing. The scheme will be developed in accordance with the CIP process which was approved at Strategy & Resources Committee on 9th October 2017.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2016.11.18_Akeman Street Location Plan /25/HSCPlan 6.8 MB Download
PDF
New Social Housing, Community Centre and Commercial Units on Akeman StreetReport 755 KB DownloadRead as text
PDF
Terrier Plan: Akeman Street 15.10.08 /25/HSCReport 1.2 MB Download

At this meeting

Whole meeting

Who was there

13 of 15 attended
MT
Councillor Mike Todd-JonesChair, present
GB
Councillor Gerri BirdVice-Chair, present
RC
Councillor Rod Cantrill Lib Dem Spokes for HousingCommittee Member, present
CM
Councillor Colin McGertyCommittee Member, present
CP
Councillor Cheney PayneCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
BT
Councillor Baiju ThittalaCommittee Member, present
KT
Councillor Katie ThornburrowCommittee Member, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, present
DB
Diane Best Leaseholder RepresentativeCo-Optee, present
KH
Kay Harris Tenant RepresentativeCo-Optee, present
JM
John Marais Tenant RepresentativeCo-Optee, apologies

All 15 on the meeting page

On this subject at Cambridge

Search all
  1. New Social Housing, Community Centre and Commercial Units on Akeman StreetThis decision
  2. New Social Housing – Meadows Centre & Buchan StreetApproved
  3. New Social Housing – Colville Road 2Approved
  4. New Social Housing on Markham Close Garage SiteApproved
  5. New Social Housing on Gunhild Way Garage SiteApproved
  6. New Social Housing on Housing Revenue Account Infill Site at Wulfstan WayNoted

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies