Decision of Executive Councillor for Housing i. Approved that the scheme was brought forward with an indicative capital budget for the scheme of £13,781,590 to cover all of the site assembly, construction costs, professional fees and associated other fees to deliver a scheme that meets an identified housing need in Cambridge City. ii. Authorise the Strategic Director in consultation with the Executive Councillor for Housing to approve variations to the scheme including the number of units and mix of property types and sizes outlined in this report. iii. Approved that the site was offered to CIP to progress in accordance with the CIP process which was approved at Strategy & Resources Committee on 9 th October 2017 subject to a value for money assessment to be carried out on behalf of the Council prior to entering into the Agreement for Lease set out in that process. iv. Delegated authority to the Strategic Director to commence Compulsory Purchase Order (CPO) proceedings on Leasehold properties to be demolished to enable the development should these be required. v. Delegated authority to the Strategic Director to serve initial Demolition Notices under the Housing Act 1985. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Manager, Housing Development Agency . The Committee welcomed the scheme. The Committee resolved ( by 4 votes to 0) to endorse the recommendation. The Executive Councillor approved the recommendation.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1The City Council has agreed a devolution deal with government to deliver 500 new Council homes over 5 years. These will be delivered as rented housing, let in accordance with the Council rent policy (where rent and service charges together do not exceed Local Housing Allowance levels). Homes will be owned and managed by Cambridge City Council and let on Cambridge City Council tenancies.
1.2Colville Road Phase 2 (70 – 80b Colville Road) was initially added to the rolling program at the 25th June 2013 Community Services Scrutiny Committee. The site is occupied by 24 households: 20 tenants and 4 leaseholders. The proposed indicative scheme will provide circa 60 new Council rented dwellings.
1.3The report seeks approval for a capital budget for the scheme based on the indicative capacity study which has been undertaken for the site
Report page no. 1 Agenda page no. and the outline appraisals referenced in this report and for the delivery route to be adopted.
1.4The indicative mix of the proposed scheme (see Appendix 2) will provide 60 Council rented homes (53 flats and 7 houses). The proposal includes a Housing First scheme. Overall the scheme will provide a net gain of 40 Council rented homes.
1.5The scheme is indicative and subject to further review and pre- application planning consultation
Recommendations
The Executive Councillor is recommended to:
2.2Approve the scheme is brought forward with an indicative capital budget for the scheme of £13,781,590 to cover all of the site assembly, construction costs, professional fees and associated other fees to deliver a scheme that meets an identified housing need in Cambridge City.
2.3Authorise the Strategic Director in consultation with the Executive Councillor for housing to approve variations to the scheme including the number of units and mix of property types and sizes outlined in this report.
2.4Approve that the site is offered to CIP to progress in accordance with the CIP process which was approved at Strategy & Resources Committee on 9th October 2017 subject to a value for money assessment to be carried out on behalf of the Council prior to entering into the Agreement for Lease set out in that process.
2.5Delegate authority to the Strategic Director to commence Compulsory Purchase Order (CPO) proceedings on Leasehold properties to be demolished to enable the development should these be required.
2.6Delegate authority to the Strategic Director to serve initial Demolition Notices under the Housing Act 1985.
Report page no. 2 Agenda page no. 3. Background
3.1There are a number of the Council’s key Corporate Objectives that this development opportunity addresses:
Tackling the City’s housing crisis.
3.1.1 Delivering the 500 new Council rented homes which are part of the Cambridgeshire and Peterborough Combined Authority devolution deal.
3.1.2 Delivering sustainable prosperity for Cambridge and fair shares for all.
3.1.3 Protecting essential services and transforming council delivery.
3.1.4 Tackling climate change and making Cambridge cleaner and greener.
3.2The site at 70 – 80b Colville Road is identified in the Development Rolling Programme.
3.2.1 The potential to redevelop this site was first highlighted in a report taken to the 25th June 2013 Community Services Scrutiny Committee when it was considered alongside Colville Road phase 1 and added to the rolling programme. The rationale for redevelopment of the block is based on the information on the existing condition of the block and cost to replace and the opportunity to deliver a significant number of new homes on this land.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.