Housing Scrutiny Committee, Wednesday 16 January 2019 at 5.30pm

New Social Housing – Meadows Centre & Buchan Street

Approved Scrutiny 3 papers

Housing Scrutiny Committee approved this item on Wednesday 16 January 2019. Below is the council's own wording, with the papers it was decided on.

Item19/8/HSC

Resolved

Decision The report proposed a redevelopment of The Meadows and Buchan Street sites, to provide much-needed Council rented housing, and a new community centre. It proposed adding these sites to the Council’s Rolling Programme of Housing development, making the resources for the redevelopment available, and working with centre users, neighbours, staff and others to ensure the design of the new homes and community centre provides well for the local community. Decision of Executive Councillor for Communities: i. Approved the rationalisation of two community centres into a new community hub in line with the Community Centres Strategy (June 2017), in order to make land available for much needed Council housing; The development process will ensure that a community centre remains open throughout the redevelopment period; and that local residents and centre users are engaged in the detailed design of the new community facility. Decision of Executive Councillor for Housing: i. Approved the addition of Meadows and Buchan Street sites to the Rolling Programme, to enable detailed design and project work to proceed ii. Approved the indicative mix of the proposed scheme, subject to design and planning, to include a mix of Council rented housing, as set out below: Meadows Buchan 1B2P Flat (Housing First) 2 2B4P Flat (Housing First) 1 1B2P Flat 58 6 2B4P Flat 27 5 3B5P House 0 7 Totals 85 21 Community Centre GIA 1583m2 Retail space GIA 148m2 iii. Recommended to Council the inclusion of an indicative budget of £26,379,880 in the Housing Capital Programme (to be presented to Council in the HRA BSR). iv. ­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­ Authorised the Strategic Director, delegation exercised in consultation with the Executive Councillor, Chair and Spokes following future business planning, to seek approval from the Secretary of State for use of HRA resources to fund part of the cost of the Community Centre and commercial unit (on the basis that this would aid the release of land for much needed housing in line with national government policy), subject to this being viable within a revised HRA business plan, and to vary the contributions recommended from the Housing Revenue Account and the General Fund in the light of the decision. v. Approved that the site is offered to CIP to progress in accordance with the CIP process which was approved at Strategy & Resources Committee on 9th October 2017 subject to a value for money assessment to be carried out on behalf of the Council prior to entering into the Agreement for Lease set out in that process. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Manager, Housing Development Agency . The Committee made the following comments in response to the report: i. Thanked officers for work over a number of years that had brought this project to the point of delivery. ii. Expressed regret at the loss of green space. iii. Concerns were raised about conflicting demands for parking and the level of provision for the new housing units. The Manager, Housing Development Agency said the following in response to Members’ questions: i. The new facility would be slightly larger than the combined size of the two existing community facilities. ii. Stated that the remaining green space would require better management to ensure the full benefit was achieved. iii. The proposed building would cross the City /South Cambs boundary and planning permissions would need to take this into account. iv. Sports England was expected to approve the plans. v. Existing users would be given priority when allocating resources in the new facility. The Executive Councillor for Communities confirmed that a range of consultations had taken place and the resulting scheme was intended to meet as much need as possible. Councillor Cantrill expressed concerns that an application was being submitted to the Secretary of State regarding the use of HRA funds for the community building when full business case had not been completed. He asked for an assurance that this Committee would have sight of the business case before such an application was submitted. Councillor Cantrill proposed an amendment to delete recommendation 2.2.4. Authorise the Strategic Director to seek approval from the Secretary of State for use of HRA resources to fund part of the cost of the Community Centre and commercial unit (on the basis that this would aid the release of land for much needed housing in line with national government policy), subject to this being viable within a revised HRA business plan, and to vary the contributions recommended from the Housing Revenue Account and the General Fund in the light of the decision. The Strategic Director suggested additional wording to recommendation 2.2.4 could achieve the desired level of scrutiny. Councillor Cantrill withdrew the proposed amendment to delete recommendation 2.2.4 and proposed the following amended wording (additional text in bold): Authorise the Strategic Director, subject to final approval from the Housing Scrutiny Committee, to seek approval from the Secretary of State for use of HRA resources to fund part of the cost of the Community Centre and commercial unit (on the basis that this would aid the release of land for much needed housing in line with national government policy), subject to this being viable within a revised HRA business plan, and to vary the contributions recommended from the Housing Revenue Account and the General Fund in the light of the decision. The amendment was lost by 3 votes to 4. Following Committee discussions, the following amendment to recommendation 2.2.4 was proposed: Authorise the Strategic Director, delegation exercised in consultation with the Executive Councillor, Chair and Spokes following future business planning, to seek approval from the Secretary of State for use of HRA resources to fund part of the cost of the Community Centre and commercial unit (on the basis that this would aid the release of land for much needed housing in line with national government policy), subject to this being viable within a revised HRA business plan, and to vary the contributions recommended from the Housing Revenue Account and the General Fund in the light of the decision. This amendment was carried by 4 votes to 0. The Committee resolved (by 4 votes to 0) to endorse the recommendation 2.1.1. The Executive Councillor for Communities approved the recommendation. The Committee resolved (by 4 votes to 0) to endorse the recommendation 2.2.1 to 2.2.6 (as amended) The Executive Councillor for Housing approved the recommendations.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Executive summary

1.1This report proposes a redevelopment of The Meadows and Buchan Street sites, to provide much-needed Council rented housing, and a new community centre. It proposes adding these sites to the Council’s Rolling Programme of Housing development, making the resources for the redevelopment available, and working with centre users, neighbours, staff and others to ensure the design of the new homes and community centre provides well for the local community.

1.2In February 2017, the City Council agreed a devolution deal with government to deliver 500 new Council homes over 5 years. In order to deliver these homes the council requires suitable sites to deliver new rented housing, let in accordance with the Council rent policy.

1.3In 2017, the Council completed a review of community provision, and approved a Community Centres Strategy. This identified that Meadows and Buchan community centres serve a high need area of the city, but that their proximity provides an opportunity to rationalise two centres into one hub, whilst making land available for new council housing. On 29th June 2017 the Community Services Scrutiny Committee approved a feasibility study to consider the potential for redevelopment.

1.4The feasibility study has now concluded, and this report presents the proposal to deliver approximately 106 homes across the two sites, together with a new, more flexible community hub and retail/commercial. The programme for the provision of the new community Centre will ensure continuity of service to the community . Detailed engagement with local people will be required on design, and in relation

Report page no. 1 Agenda page no. to the proposal to build much-needed housing to meet local needs on Buchan Street.

Recommendations

2.1The Executive Councillor (Communities) is recommended to

2.1.1 Approve the rationalisation of two community centres into a new community hub in line with the Community Centres Strategy (June 2017), in order to make land available for much needed Council housing; The development process will ensure that a community centre remains open throughout the redevelopment period; and that local residents and centre users are engaged in the detailed design of the new community facility.

2.2The Executive Councillor (Housing) is recommended to:

2.2.1 Add the Meadows and Buchan Street sites to the Rolling Programme, to enable detailed design and project work to proceed;

2.2.2 Approve the indicative mix of the proposed scheme, subject to design and planning, to include a mix of Council rented housing, as set out below

Meadows Buchan 1B2P Flat (Housing First) 2 2B4P Flat (Housing First) 1 1B2P Flat 58 6 2B4P Flat 27 5 3B5P House 0 7 Totals 85 21

Community Centre GIA 1583m2 Retail space GIA 148m2

2.2.3 Recommend to Council the inclusion of an indicative budget of £26,379,880 in the Housing Capital Programme (to be presented to Council in the HRA BSR).

2.2.4 Authorise the Strategic Director to seek approval from the Secretary of State for use of HRA resources to fund part of the cost of the Community Centre and commercial unit (on the basis that this would aid the release of land for much needed housing in line with national government policy), subject to this being viable within a revised HRA business plan, and to vary the contributions recommended from the Housing Revenue Account and the General Fund in the light of the decision.

2 2.2.5 Authorise delegated authority to the Strategic Director in consultation with the Executive Councillor to: approve variations to the schemes including the number of units and tenure mix of property types required to obtain planning approval and sizes outlined in this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Meadows & Buchan Appendix 1 Location Map /8/HSCAppendix 1 MB Download
PDF
Meadows & Buchan Appendix 2 Proposals /8/HSCAppendix 4.7 MB Download
PDF
New Social Housing: Meadows Centre & Buchan StreetReport 336 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 15 attended
MT
Councillor Mike Todd-JonesChair, present
GB
Councillor Gerri BirdVice-Chair, present
RC
Councillor Rod Cantrill Lib Dem Spokes for HousingCommittee Member, present
NM
Councillor Nicky MasseyCommittee Member, present
CM
Councillor Colin McGertyCommittee Member, present
CP
Councillor Cheney PayneCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
BT
Councillor Baiju ThittalaCommittee Member, apologies, sent representative
SB
Councillor Sophie BarnettCommittee Member, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, present
DB
Diane Best Leaseholder RepresentativeCo-Optee, present
KH
Kay Harris Tenant RepresentativeCo-Optee, present

All 15 on the meeting page

On this subject at Cambridge

Search all
  1. New Social Housing – Meadows Centre & Buchan StreetThis decision
  2. New Social Housing – Colville Road 2Approved
  3. New Social Housing, Community Centre and Commercial Units on Akeman StreetApproved
  4. New Social Housing on Markham Close Garage SiteApproved
  5. New Social Housing on Gunhild Way Garage SiteApproved
  6. New Social Housing on Housing Revenue Account Infill Site at Wulfstan WayNoted

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies