Decision The report provided an update on the programme to deliver 500 Council homes with funding from the Combined Authority. Decision of Executive Councillor for Housing i. Noted the continued progress on the delivery of the Combined Authority programme. ii. Noted the funding structure for the Combined Authority programme. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Housing Development Agency . The Head of Housing Development Agency said the following in response to Members’ questions: i. Confirmed that the number of fully adapted properties to be delivered exceeds the initial targets. The remaining properties in the programme would be built to lifetime’s homes standards and would be adapted at a future date to suit the occupant’s needs. ii. Hill was a respected and trusted delivery partner who shared the council’s high standards. iii. The majority of the properties in the pipeline would be 1 and 2 bedroom units as this had previously been identified as the type of properties in highest demand. Larger properties could be delivered on some schemes subject to evidence of demand. Councillor McGerty questioned why the small site on the corner of Hill’s Avenue had not been included in the programme. Office’s confirmed that the estimated development cost per unit cost was too high. It was suggested that the site could be used temporarily as a community garden as it was currently an eyesore. The Strategic Director (SH) undertook to investigate this option. The Committee resolved by 5 votes to 0 to endorse the recommendations. The Executive Councillor approved the recommendations.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report provides an update on the programme to deliver 500 Council homes with funding from the Combined Authority.
1.2Following some minor revisions to the housing schemes outlined in the January report, the total Council housing programme now shows 536 homes.
1.3The Council now has 132 Council rented homes being built on site with first completions programmed for August 2019.
Recommendations
The Executive Councillor is recommended to:
Report page no. 1 Agenda page no. 2.1 Note the continued progress on the delivery of the Combined Authority programme.
2.2Note the funding structure for the Combined Authority programme.
Background
3.1In January 2019, the Housing Scrutiny Committee was provided with a report showing progress against the Combined Authority target of 500 Council rented homes.
3.2The report confirmed that the 500 home target is now forecast to be met with a total programme outturn of 535 homes.
3.3In the past two months the Housing Development team have progressed the identified schemes as forecast with some minor revisions to the overall programme.
4. Combined Authority
4.1The Council’s housing programme is part funded by a £70million grant from the Cambridgeshire & Peterborough Combined Authority.
4.2Quarterly grant claims are made to the Combined Authority in arrears. Cambridge City Council is forecast to draw down £13,686,542 in financial year 18/19, for a total expenditure by financial year end of £14,270,717.
4.3Provision of a quarterly report from Cambridge City Council against the £70m programme is one condition of the original grant from the Combined Authority. The most recent report to the Combined Authority was made on the 6th of February 2019 and replicated the information provided to the Housing Scrutiny Committee on the 16th January.
5.1The delivery programme provided in January 2019 included 535 (net gain) Council homes to be delivered on named sites through the devolution programme. The Committee also approved capital budgets for major development sites at the Meadows Centre & Buchan Street and Colville Road, as well as the purchase of the S106 affordable housing provision within a private sector housing development at Clerk Maxwell Road.
5.2Since January the development of all named housing schemes has been progressed (see items 7 and 8). Following revisions to existing schemes, the programme is now set to deliver 536 new homes with the option to pursue 277 additional homes on a range of prospective sites.
5.3Appendix 1 shows the current programme, which now shows the total market housing provided as well as the net gain of Council homes. It also includes the approved budgets per scheme and the net cost to the Council’s Housing Revenue account.
6. Profile of Start on Sites
6.1The start on site profile for the 500 devolution programme is shown in table 1. This is based on all the named schemes being delivered (including those added to the rolling programme in January 2019)
6.2The Housing Development team are continuing to over-programme and explore additional sites to allow for slippage of existing schemes and allow others to come forward should additional funding opportunities present themselves.
6.3As below, the overall programme shows an outturn of 536 new homes commencing construction by March 2022.
Report page no. 3 Agenda page no. Table 1: Start on Site Forecast Profile Year 2017/8 2018/19 2019/20 2020/21 2021/22 Pipeline (actual) (forecast) schemes Number of starts 2 132 311 91 0 277 Cumulative total 2 134 445 536 536 813
7. Start on Sites Achieved 2018/19
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.