Combined Update on the Programme to Build New Council Homes Funded Through the Combined Authority and Work Toward Development of the New Council Housing Programme**
NotedScrutiny3 papers
Housing Scrutiny Committee noted this item on Tuesday 16 March 2021. Below is the council's own wording, with the papers it was decided on.
Decision The Officer’s report provided an update on the programme to deliver 500 Council homes by March 2022 with funding from the Combined Authority, along with the new programme work for 2022-2032. Decision of Executive Councillor for Housing i. Noted the continued progress on the delivery of the Combined Authority programme. ii. Noted the work undertaken to date toward development of the new housing programme for 2022-2032. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee made the following comments in response to the report: i. Was there an update on Kingsway Medical Centre conversion? ii. Can Committee be updated with the Anstey Way and Ventress Close model of having a Custodian on-site. The officers said the following in response to Members’ questions: i. The Kingsway Medical Centre project was still on hold awaiting final settlement with insurers following the flat fire. ii. A report back to committee on the use of the Custodian model will be provided in due course. Post meeting the Head of Housing proposed that as a full review of Housing First is planned by the end of 2021-22, and by this time there will hopefully be employed a number of custodians (as opposed to the one currently employed) the Council will be in a better position to evaluate the role’s efficacy as part of a wider HF review. Therefore to bring a report to June 22 committee which covers all aspects of Housing First. The Committee resolved by 5 votes to 0 to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor .
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report provides an update on the programme to deliver 500 Council homes by March 2022 with funding from the Combined Authority, along with the new programme work for 2022-2032.
1.2130 Homes have now been completed across 11 sites under the City Council programme, with 75 being net new Council homes.
1.3The Council currently has 451 new Council rented homes being built on site, with a further 16 Starts to fall within 2021/2022 under the current programme.
1.4The HDA has thus reached 526 recorded Starts on site and has successfully met and exceeded the 500 homes target. (105.2% of target).
Report page no. 1 Agenda page no. 1.5 The Sustainable Housing Design Guide principles were approved by HSC in January 2021 and are now adopted for the new programme. The updated guide will be published on the City Councils website.
Recommendations
The Executive Councillor is recommended to:
2.1Note the continued progress on the delivery of the Combined Authority programme.
2.2Note the work undertaken to date toward development of the new housing programme for 2022-2032.
Background
3.1This is a quarterly report showing progress on the City Councils Development programme ambitions.
4. Combined Authority
4.1The Council’s housing programme is part funded by a £70 million grant, which to date has been paid via the Cambridgeshire & Peterborough Combined Authority in arrears, with the exception of a direct advance payment of £17,000,000 from MHCLG in March 2020.
4.2Quarterly grant claims are made in arrears against the Devolution funding to the Combined Authority. There is £53,000,000 to be claimed from the Combined Authority with £28,208,605 claimed to date. Of the £17,000,000 that was paid directly to the City Council from MHCLG for 2020/21, £9,644,361 has been invested to date. Cambridge City Council anticipates drawing down / utilizing a further £6,228,232 by the end of the current financial year.
4.3To date Cambridge City Council has drawn down / utilized a total of £37,852,966 of Devolution funding, with the remaining £32,147,034 due to be drawn down / utilized by financial year end 2023/24.
4.4MHCLG and the Combined Authority remain in discussion around the target date for the starts on site for this programme along with their own £100m housing programme. We have been keeping MHCLG up to date
Report page no. 2 Agenda page no. with our progress which based on current projections will meet the 2021 date.
5. Delivery Programme
5.1The delivery programme update provided in January 2021 confirmed that the devolution programme consisted of 542 Council Homes.
5.2Appendix 1 shows the current programme, indicating total market housing provided as well as the net gain of Council homes. Appendix 2 shows the approved budgets per scheme and the net cost to the Council’s Housing Revenue account.
6. Profile of Start on Sites
6.1The start on site profile for the 500 devolution programme is shown in table 1. This is based on all the named schemes being delivered.
6.2The total starts on site currently stand at 526, or 105.2% of the total programme target of 500 homes, ahead of the targeted deadline of 31 March 2022.
6.3The combined Authority continue to hold discussions with MHCLG to clarify programme expectations related to completion dates, however as we have now met our target this no longer affects the Council.
6.4As below, the overall programme currently shows an outturn of 542 new homes commencing construction by March 2022.
Table 1: Start on Site Forecast Profile
Progress to 500 starts on site 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 Starts by year 2 159 162 203 16 0 Cumulative total 2 161 323 526 542 542
7. Scheme details
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Combined Update on the Programme to Build New Council Homes Funded Through the Combined Authority and Work Toward Development of the New Council Housing Programme**Report
21/21/HSCCombined Update on the Programme to Build New Council Homes Funded Through the Combined Authority and Work Toward Development of the New Council Housing Programme**This decision
Combined Update on the Programme to Build New Council Homes Funded Through the Combined Authority and Work Toward Development of the New Council Housing Programme**This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.