Housing Scrutiny Committee, Tuesday 18 June 2019 at 5.30pm

Update on the Programme to Build New Council Homes Funded Through the Combined Authority

Noted Scrutiny 3 papers

Housing Scrutiny Committee noted this item on Tuesday 18 June 2019. Below is the council's own wording, with the papers it was decided on.

Item19/33/HSC

Resolved

Decision of the Executive Councillor for Housing i. Noted the continued progress on the delivery of the Combined Authority programme. ii. Noted the funding structure for the Combined Authority programme. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Housing Development Agency. In response to questions and comments from the Committee the Strategic Director and Head of Housing Development said the following: i. The Council had its own sustainability housing standard which all dwellings across the housing programme met or exceeded. ii. The Council’s standard surpassed the national sustainability requirements. iii. Each development was treated differently regarding sustainability, as each site had different constraints and requirements. iv. The Mill Road development had a 19% improvement on the sustainability building regulations. This was due to certain factors such as a fabric first approach, solar panels, heat and power systems which would reduce admissions significantly. v. Electric vehicle charging points would be installed on certain developments. vi. Stopping the use of fossil fuels on a development would be a long term project for officers to investigate. vii. Passive house standards was impacted by the site constrained as well as type of homes built. viii. It was not currently possible to deliver a passive house standard on higher level apartments. ix. Reiterated the Councils build programme had been designed to meet a high level of sustainability. x. The consultation process on the Meadows and Buchan Street development had been voluntary. This was in advance of the statutory consultation process which would follow. xi. Over three thousand leaflets had been distributed to advertise the Meadows and Bucham Street public consultation. Posters had been displayed throughout the area and advertised online. The exhibition finished at 9.00pm for people to attend after work. xii. A follow up meeting was then arranged to discuss concerns raised at the exhibition which covered the loss of open space. xiii. In respect of the Cromwell Road development the plans put forward had been for 295 houses, which was above the Supplementary Planning Document (SPD) proposal of 225 houses. The profit margin was lower for the council’s joint venture partner compared to what they would have received developing the site themselves. xiv. Had listened to public consultation on the Meadows and Bucham Scheme. Officers were currently working with architects on how to enhance the public open space; therefore no clear response could have been given to the public speaker. The public consultation was still open on this matter. xv. The demand for housing in the area which the Meadows and Bucham Street stood was one of the highest in the city. xvi. The relationship with the Cambridge Investment Partnership (CIP) was 50/50 joint venture but set up as an independent company. All of the accounting was by open book and had audited accounts The Committee resolved by 5 votes to 0 to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Executive summary

1.1This report provides an update on the programme to deliver 500 Council homes with funding from the Combined Authority.

1.2All 500 homes have now been identified and the HDA is focusing its efforts on delivering the schemes in the programme.

1.3The Council now has 147 Council rented homes being built on site and is forecasting a further 296 to start in 2019/20. The first completions are programmed for August 2019.

Recommendations

The Executive Councillor is recommended to:

Report page no. 1 Agenda page no. 2.1 Note the continued progress on the delivery of the Combined Authority programme.

2.2Note the funding structure for the Combined Authority programme.

Background

3.1In March 2019, the Housing Scrutiny Committee was provided with a report showing progress against the Combined Authority target of 500 Council rented homes.

3.2The report confirmed that the 500 home target is now forecast to be met with a total programme outturn of 536 homes.

3.3In the past two months the Housing Development team have progressed the identified schemes as forecast with some minor revisions to the overall programme, raising the current total outturn to 537 homes.

4. Combined Authority

4.1The Council’s housing programme is part funded by a £70million grant from the Cambridgeshire & Peterborough Combined Authority.

4.2Quarterly grant claims are made to the Combined Authority in arrears. Cambridge City Council drew down £13,551,727 in financial year 2018/19, slightly short of the forecast drawdown of £13,686,542.

4.3To date Cambridge City Council has drawn down £14,135,901 with the remaining £55,864,098 due to be drawn down by financial year end 2021/22

Report page no. 2 Agenda page no. 4.4 Provision of a quarterly report from Cambridge City Council against the £70m programme is one condition of the original grant from the Combined Authority. The most recent report to the Combined Authority was made on the 3rd of April 2019 and replicated the information provided to the Housing Scrutiny Committee on the 12th March 2019.

5. Delivery Programme

5.1The delivery programme provided in March 2019 included 536 (net gain) Council homes to be delivered on named sites through the devolution programme. The committee noted some minor alterations to individual scheme outturns but otherwise the programme was on track.

5.2Since March the development of all named housing schemes has been progressed (see items 7 and 8). Further revisions to forthcoming schemes have since been made. The programme outturn is now 537 homes, due to an increase of 5 units on the prospective scheme at Campkin Road. A second feasibility stage scheme delivering 4 units has been removed from the programme. The resources which were intended to be used for this scheme have been re-allocated in the HRA to the Campkin Road scheme pending HSC approval.

5.3The Campkin Road scheme is now the only scheme in the programme which has not received approval for a capital budget from the Housing Scrutiny Committee. The report detailing the Campkin Road scheme and requesting approval for a capital budget has been submitted to the HSC alongside this report.

5.4Appendix 1 shows the current programme, which now shows the total market housing provided as well as the net gain of Council homes. Appendix 2 shows the approved budgets per scheme and the net cost to the Council’s Housing Revenue account.

Report page no. 3 Agenda page no. 6. Profile of Start on Sites

6.1The start on site profile for the 500 devolution programme is shown in table 1. This is based on all the named schemes being delivered.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2019 06 18 HSC programme report Appendix 1 /33/HSCAppendix 426 KB Download
PDF
2019 06 18 HSC programme report Appendix 2 /33/HSCAppendix 360 KB Download
PDF
Update on the Programme to Build New Council Homes Funded Through the Combined AuthorityReport 949 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 17 attended
MT
Councillor Mike Todd-JonesChair, apologies
GB
Councillor Gerri BirdVice-Chair, present
RC
Councillor Rod Cantrill Lib Dem Spokes for HousingCommittee Member, present
GH
Councillor Grace HadleyCommittee Member, present
PL
Councillor Peter LordCommittee Member, apologies
KP
Councillor Katie PorrerCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
BT
Councillor Baiju ThittalaCommittee Member, present
CM
Councillor Colin McGertyCommittee Member, present
CO
Councillor Carina O'ReillyCommittee Member, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, present
DB
Diane Best Leaseholder RepresentativeCo-Optee, present

All 17 on the meeting page

On this subject at Cambridge

Search all
  1. Update on the Programme to Build New Council Homes Funded Through the Combined AuthorityThis decision
  2. Combined Update on the Programme to Build New Council Homes Funded Through the Combined Authority and Work Toward Development of the New Council Housing Programme**Noted
  3. Update on the Programme to Build new Council Homes Funded Through the Combined AuthorityNoted
  4. Update on the Programme to Build new Council Homes Funded Through the Combined AuthorityNoted
  5. Update on the Programme to Build new Council Homes Funded Through the Combined AuthorityNoted
  6. Update on the Programme to Build New Council Homes Funded Through the Combined AuthorityNoted

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open