Housing Scrutiny Committee, Thursday 26 September 2019 at 5.30pm

Update on the Programme to Build new Council Homes Funded Through the Combined Authority

Noted Scrutiny 4 papers

Housing Scrutiny Committee noted this item on Thursday 26 September 2019. Below is the council's own wording, with the papers it was decided on.

Item19/42/HSC

Resolved

Decision i. The report provided an update on the programme to deliver 500 Council homes with funding from the Combined Authority. ii. All 500 homes had now been identified and the HDA was focusing its efforts on delivering the schemes in the programme. iii. The Council now had 162 Council rented homes being built on site and was forecasting a further 176 due to start by the end of financial year 2019/20. iv. 14 homes of the City Council programme had now been completed across three sites. v. There had been a change in the approach to contract arrangements for schemes developed by the Cambridge Investment Partnership which is detailed in Appendix 3. Decision of Executive Councillor for Housing i. Noted the continued progress on the delivery of the Combined Authority programme. ii. Noted the funding structure for the Combined Authority programme . iii. Approved the revised approach to land transactions for schemes developed by the Cambridge Investment Partnership as described in Appendix 3. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Housing Development Agency . Officers confirmed that a Housing Tour for all Members of the Committee would be arranged shortly. The Head of Housing Development Agency said the following in response to Members’ questions: i. Confirmed the tenure mix across the Mill Road site as single tenure block with the blocks mixed across the site. ii. Confirmed that a planning application was expected shortly for the Meadows site. iii. Stated that the utility cost across the Mill Road site would be at a flat rate and that the Council was seeking the best rate for the standing charges. The Strategic Director (FB) stated the following in response to Members’ questions: i. Confirmed that the team had worked very hard to progress sites as quickly as possible. ii. Stated that the clustering policy was currently under review. iii. The tenure mix across new sites was seeking to establish mixed and diverse communities but needed to be flexible to suit different locations. Councillor Executive Councillor for Housing stated that any transfer funding required to progress the Meadows Scheme would be small. The Committee resolved by 4 votes to 0 to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Executive summary

1.1This report provides an update on the programme to deliver 500 Council homes with funding from the Combined Authority.

1.2All 500 homes have now been identified and the HDA is focusing its efforts on delivering the schemes in the programme.

1.3The Council now has 162 Council rented homes being built on site and is forecasting a further 176 due to start by the end of financial year 2019/20.

1.414 homes of the City Council programme have now been completed across three sites.

Report page no. 1 Agenda page no. 1.5 There has been a change in the approach to contract arrangements for schemes developed by the Cambridge Investment Partnership which is detailed in Appendix 3.

Recommendations

The Executive Councillor is recommended to:

2.1Note the continued progress on the delivery of the Combined Authority programme.

2.2Note the funding structure for the Combined Authority programme.

2.3Approve the revised approach to land transactions for schemes developed by the Cambridge Investment Partnership as described in Appendix 3.

Background

3.1In June 2019, the Housing Scrutiny Committee was provided with a report showing progress against the Combined Authority target of 500 Council rented homes.

3.2The report confirmed that the 500 home target is now forecast to be exceeded with a total programme outturn of 537 homes net gain.

3.3The Housing Development team have progressed the identified schemes as forecast with some minor revisions to the overall programme, raising the current total outturn to 546 homes.

4. Combined Authority

4.1The Council’s housing programme is part funded by a £70million grant from the Cambridgeshire & Peterborough Combined Authority.

Report page no. 2 Agenda page no. 4.2 Quarterly grant claims are made to the Combined Authority in arrears. Cambridge City Council drew down £2,291,290 in the first Quarter of 2019/20 and is forecasting a further £18,824,136 of grant drawdown by end March 2020.

4.3To date Cambridge City Council has drawn down £16,427,192 with the remaining £53,572,809 due to be drawn down by financial year end 2021/22

4.4Provision of a quarterly report from Cambridge City Council against the £70m programme is one condition of the original grant from the Combined Authority. The most recent report to the Combined Authority was made on the 3rd of April 2019 and replicated the information provided to the Housing Scrutiny Committee on the 12th March 2019.

5. Delivery Programme

5.1The delivery programme provided in June 2019 included 537 (net gain) Council homes to be delivered on named sites through the devolution programme. The committee noted some minor alterations to individual scheme outturns but otherwise the programme was on track.

5.2Since June the development of all named housing schemes has been progressed (see items 7 and 8). Further revisions to forthcoming schemes have since been made. The programme outturn is now 546 Council rented homes (net gain) due to an increase of seven homes on the design of the proposed scheme at Colville Road Phase 2 and the planning approval of the combined sheme at Mill Road.

5.3In June the final scheme in the 500 Programme, the redevelopment of Campkin Road, was approved by Housing Scrutiny Committee. The entire 500 programme is therefore approved with a capital budget allocated. All but five schemes have now received planning permission and only two have yet to be submitted for planning approval.

Report page no. 3 Agenda page no. 5.4 Appendix 1 shows the current programme, which now shows the total market housing provided as well as the net gain of Council homes. Appendix 2 shows the approved budgets per scheme and the net cost to the Council’s Housing Revenue account.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2019 09 26 HSC programme report: Appendix 1 /42/HSCAppendix 423 KB Download
PDF
2019 09 26 HSC programme report: Appendix 2 /42/HSCAppendix 352 KB Download
PDF
2019 09 26 HSC programme report: Appendix 3 /42/HSCAppendix 110 KB Download
PDF
Update on the Programme to Build new Council Homes Funded Through the Combined AuthorityReport 1.1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 17 attended
MT
Councillor Mike Todd-JonesChair, present
GB
Councillor Gerri BirdVice-Chair, apologies
RC
Councillor Rod Cantrill Lib Dem Spokes for HousingCommittee Member, present
GH
Councillor Grace HadleyCommittee Member, apologies
JM
Councillor Josh MatthewsCommittee Member, present
KP
Councillor Katie PorrerCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
BT
Councillor Baiju ThittalaCommittee Member, present
SB
Councillor Sophie BarnettCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, apologies
DB
Diane Best Leaseholder RepresentativeCo-Optee, present

All 17 on the meeting page

On this subject at Cambridge

Search all
  1. Update on the Programme to Build new Council Homes Funded Through the Combined AuthorityThis decision
  2. Combined Update on the Programme to Build New Council Homes Funded Through the Combined Authority and Work Toward Development of the New Council Housing Programme**Noted
  3. Update on the Programme to Build new Council Homes Funded Through the Combined AuthorityNoted
  4. Update on the Programme to Build new Council Homes Funded Through the Combined AuthorityNoted
  5. Update on the Programme to Build new Council Homes Funded Through the Combined AuthorityNoted
  6. Update on the Programme to Build New Council Homes Funded Through the Combined AuthorityNoted

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies