Decision This report provided an update on the housing development programme. Decision of Executive Councillor for Housing i. Noted the continued progress on the delivery of the Combined Authority programme. ii. Noted the work undertaken to date toward development of the new housing programme for 2022-2032. iii. Delegated authority to the Section 151 officer to start the process to set- up a housing company as a Registered provider with a full report of the details of this proposal to be brought to a future committee. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of the Housing Development Agency . The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report provides an update on the housing development programme.
1.2148 Homes have been completed across 13 sites under the City Council programme, with 88 being net new Council homes. A further 16 modular “pod” homes have now been completed across 3 further sites.
1.3The Council currently has 438 net new Council rented homes being built on site, with a further 16 new homes remaining to reach Start on Site under the current programme.
1.4107 new affordable and 62 replacement and market sale homes are currently approved schemes as a first stage of the new 1000 homes housing programme, with 54 new affordable and 33 replacement being considered as part of this committee cycle.
1.5The Councils bid to Homes England to become a Strategic Partner has not been successful, but discussions are continuing with Homes England about ways in which they can support the programme.
2.1Note the continued progress on the delivery of the Combined Authority programme.
2.2Note the work undertaken to date toward development of the new housing programme for 2022-2032.
2.3Delegate authority to the Section 151 officer to start process of the set- up of a housing company as a Registered provider with a full report of the detail of this proposal to be brought to a future committee.
3. Reporting This is a quarterly report showing progress on the City Councils Development programme ambitions.
4. £70m funding programme MHCLG
4.1The Council’s housing programme is part funded by a £70 million grant, which to date has been paid via a combination of the Cambridgeshire & Peterborough Combined Authority and directly by MHCLG. At the time of writing this report, all of the £70 million has been received, with £38 million via the Combined Authority and £32 million directly from MHCLG.
4.2Until the end of 2020/21 quarterly grant claims were made in arrears against the Devolution funding to the Combined Authority.
4.3As at 31 March 2021 £41,859,663.36 of the funding has been utilised in the delivery of new homes, with £28,140,336.64 held in balances to fund the completion of the programme from April 2021 onwards.
5. Delivery Programme
5.1The delivery programme update provided in June 2021 confirmed that the devolution programme consisted of 542 Council Homes with a further 104 homes identified for the new programme
Report page no. 2 Agenda page no. 5.2 Appendix 1 shows the current programme, indicating total market housing provided as well as the net gain of Council homes. Appendix 2 shows the approved budgets per scheme and the net cost to the Council’s Housing Revenue account.
6. Profile of Start on Sites
6.1The start on site profile for the 500 devolution programme is shown in table 1. The total starts on site currently stand at 526, or 105.2% of the total programme target of 500 homes, ahead of the targeted deadline of 31 March 2022.
6.2As below, the 500 programme currently shows an outturn of 542 new homes commencing construction by March 2022. 6.3 The new 1000 homes programme is additionally progressing, and 107 net new council homes have been approved by the Executive Councillor.
Table 1: Start on Site Forecast Profiles
500 Programme Progress to 500 starts on site 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 Starts by year 2 159 162 203 16 0 Cumulative total 2 161 323 526 542 542
1000 Programme Progress to 1000 2021/ 2022/ 2023/ 2024/ 2025/ 2026/ 2027/ 2028/ 2029/ starts on site 22 23 24 25 26 27 28 29 30 Starts by year 90 17 Cumulative total 90 107 107 107 107 107 107 107 107
7. Scheme details
7.1Schemes Completed: Net gain 88 Affordable homes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.