Resolved
A. To note the Chief Executive business case decisions for projects less than £1m under the Single Assurance Framework. A. To note the Chief Executive business case decisions for projects less than £1m under the Single Assurance Framework.
Funding Committee noted this item on Monday 21 October 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
A. To note the Chief Executive business case decisions for projects less than £1m under the Single Assurance Framework. A. To note the Chief Executive business case decisions for projects less than £1m under the Single Assurance Framework.
A To note the Chief Executive business case decisions for projects less than £1m under the Single Assurance Framework.
Strategic Objective(s):
The proposals within this report fit under the following strategic objective(s): X Achieving ambitious skills and employment opportunities X Achieving good growth X Increased connectivity X Enabling resilient communities X Achieving Best Value and High Performance The SAF is a set of systems and processes designed to provide the CPCA with a consistent approach to appraisal, assurance, risk and performance, throughout the lifecycle of projects and programmes. It is focused on ensuring accountability, probity, transparency and legal compliance – and critically, value for money of investments. It covers the full end to end lifecycle of projects and programmes that place a financial liability on the CPCA.
1. Purpose
1.1Under the SAF arrangements approved by the Combined Authority Board at its meeting on 20 September 2023, the Chief Executive has delegated authority to approve project investments of less than £1m in total for which the funding is within the approved Medium Term Financial Plan. 1.2 This report sets out the projects which have been approved by the Chief Executive in accordance with the delegated authority from the Board and is for noting. 2. Proposal
2.1Management of the CPCA’s investment priorities, plans and processes is critical to the successful delivery of its strategic aims and maximising the benefits to the region. To meet the standards set by Government – such as the English Devolution Accountability Framework (EDAF) - we needed a specific Assurance Framework that shows how we will meet best value requirements and ensuring we are spending public money in the most effective way. In addition, the SAF was a key objective from the Improvement Programme and is a way of demonstrating that the CPCA has responded to concerns raised by Government through the Best Value Notice.
2.2The table below sets out all Chief Executive that have been made under delegated authority as part of the SAF arrangements and this are listed in the table below. Investment Panel CEX Approval Business Case Funding Approval Date Dates 17/07/2024 22/08/2024 Schools Low Carbon Heating £363,000
29/08/2024 05/09/2024 Biodiversity £350,000
2.3The following paragraphs provide a summary of each of the projects.
2.4Schools Low Carbon Heating This project is to provide match funding for three schools low carbon heating projects at Huntingdon Nursery (HDC), St Philip’s Cambridge (Cambridge) and Townley Primary School (Fenland). For clarity:
• The County Council’s low carbon heating programme has identified 13 schools where investment in heating systems will reduce carbon as well as providing new systems to be installed. 10 of these schools in the programme are fully funded by the County Council and external funding secured through the Public Sector Decarbonisation Fund
• CPCA investment of £363k would secure a further £421k of external funding from Government to enable the full programme i.e. all 13 schools to proceed and to support progress towards achieving Net Zero, a key priority for the CPCA.
• The PSDS grant funding has to be spent this financial year 2024/25.
The CPCA contribution of £363k is towards a total project cost of £1.647m, with other funding from the County Council (£0.708m), PSDS grant (£421k), the Diocese of Ely (£101k) and a small loan facility (£54k).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Single Assurance Framework Business Case Approvals: Chief Executive Officer DecisionsDecisions | 172 KB | DownloadRead as text |
Follow Funding Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | Minutes of the previous meetingThe minutes of the meeting held on 3 August 2026 were approved. | Approved | Open |
| 7 Sep 2026 | Single Assurance Framework Business Case Approvals: Funding Committee Decisions(Unanimous) A. To recommend that the Combined Authority Board approve the Full Business Case and £24,465,000 for Acti... | Approved | Open |
| 7 Sep 2026 | Single Assurance Framework Business Case Approvals: Officer DecisionsA. To note the Officer Decisions for projects under the Single Assurance Framework delegation from Funding Panels hel... | Noted | Open |
| 7 Sep 2026 | Closure of Subsidiary Cambridgeshire and Peterborough Business Growth Company Limited(Unanimous) A. To recommend that the Combined Authority Board approve the Shareholder documentation as appended at Ap... | Approved | Open |
| 7 Sep 2026 | Work ProgrammeA. To note the Funding Committee’s . | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.