Single Assurance Framework: Reporting of Major Project Performance and Risk

Noted Committee 2 papers

Funding Committee noted this item on Monday 21 October 2024. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

The Investment Committee resolved to: A. Note the performance against major projects supported by Cambridgeshire and Peterborough Combined Authority (CPCA) B. Note the summary of the wider CPCA project landscape The Investment Committee resolved to: A. Note the performance against major projects supported by Cambridgeshire and Peterborough Combined Authority (CPCA) B. Note the summary of the wider CPCA project landscape
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Funding Committee

Recommendations

A To note performance reports on the Major Projects and programmes, wider CPCA Project landscape changes and risks.

Strategic Objective(s):

The proposals within this report fit under the following strategic objective(s): X Achieving ambitious skills and employment opportunities X Achieving good growth X Increased connectivity X Enabling resilient communities X Achieving Best Value and High Performance The SAF is a set of systems and processes designed to provide the CPCA with a consistent approach to appraisal, assurance, risk and performance, throughout the lifecycle of projects and programmes. It is focused on ensuring accountability, probity, transparency and legal compliance – and critically, value for money of investments. It covers the full end to end lifecycle of projects and programmes that place a financial liability on the CPCA.

1. Purpose

1.1To note major projects performance and risk data. 2. Proposal

2.1The CPCA are accountable for delivering in a complex and changing environment. How we manage the investment process is critical to the successful delivery of strategic aims. To meet the standards set by Government – such as the English Devolution Accountability Framework (EDAF) - we needed a specific Assurance Framework that shows how we will meet best value requirements and ensuring we are spending public money in the most effective way. In addition, the SAF was a key objective from the Improvement Programme and is a way of demonstrating that the CPCA has responded to concerns raised by Government through the Best Value Notice.

2.2Most Complex major projects performance data and risks Programmes and Projects are classed as Most Complex when a Combined Authority Funded programme or project is considered most significant in terms of value, strategic fit and where there would be significant impact if there was a failure to deliver. There are six major projects listed: • Peterborough Station Quarter • University of Peterborough • Net Zero Programme (Home Upgrade Grant 2) • Bus Reform Programme • Adult Education Provision • Market Town Masterplans Of the major projects three are rated as Green and on target, where there is a high level of confidence in successful delivery: • University of Peterborough • Adult Education Provision • Market Town Masterplans Two major projects are rated as Amber, where without action, successful delivery may be adversely impacted. For both areas actions have been highlighted within Appendix 1. • Peterborough Station Quarter • Bus Reform Programme One major project is rated as Red, where without action, successful delivery is highly unlikely. The details for this and associated actions is set out in Appendix 1. • Net Zero programme (Home Upgrade Grant 2) Further details are available in Appendix 1 for all schemes listed above setting out the risks and mitigations.

Background

3.1The Combined Authority Single Assurance Management Framework and Procedure was reviewed at 08 September Audit & Governance Committee and approved 20 September Combined Authority Board. Work continues in embedding the Framework and Procedure, including through training for officers.

3.2The Framework notes that the Programme Management Office are responsible for ensuring that the SAF process is maintained, updated and that performance and risks are regularly reviewed with the Executive Director of Resources, Corporate Management Team, Investment Committee, Audit and Governance Committee and CPCA Board. 3.3 The Investment Committee has the following key functions in support of the Performance Management Framework:

• to review the Major Projects performance including risk

Appendices

4.1Appendix 1: Most Complex Programmes & Projects Report Q2- August

5. Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Most Complex Programmes and Projects Report Q2: AugAppendix 1 140 KB Download
PDF
Single Assurance Framework: Reporting of Major Project Performance and RiskReport 160 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 30 attended
NJ
Dr Nik Johnson MayorChair, present
SS
Councillor Simon Smith Cambridge City CouncilCommittee Member, present
LN
Councillor Lucy Nethsingha Cambridgeshire County CouncilCommittee Member, present
AS
Councillor Alan Sharp East Cambridgeshire District CouncilCommittee Member, apologies
DH
Councillor Dr Haq Nawaz Fenland District CouncilCommittee Member, present
SW
Councillor Sam Wakeford Huntingdonshire District CouncilCommittee Member, present
NT
Councillor Nick Thulbourn Peterborough City CouncilCommittee Member, present
JW
Councillor John Williams South Cambridgeshire District CouncilCommittee Member, present
AK
Al Kingsley Business BoardCommittee Member, present
NP
Nitin Patel Business BoardCommittee Member, present
AS
Councillor Anna Smith Deputy MayorSubstitute
EM
Councillor Elisa Meschini Cambridgeshire County CouncilSubstitute

All 30 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Single Assurance Framework: Reporting of Major Project Performance and RiskThis decision
  2. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved
  3. Single Assurance Framework Business Case Approvals: Officer DecisionsNoted
  4. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved
  5. Single Assurance Framework Business Case Approvals: Officer DecisionsNoted
  6. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved

More from Cambridgeshire and Peterborough Combined Authority Funding Committee

All decisions
MeetingDecisionOutcome
7 Sep 2026 Minutes of the previous meetingThe minutes of the meeting held on 3 August 2026 were approved. Approved Open
7 Sep 2026 Single Assurance Framework Business Case Approvals: Funding Committee Decisions(Unanimous) A. To recommend that the Combined Authority Board approve the Full Business Case and £24,465,000 for Acti... Approved Open
7 Sep 2026 Single Assurance Framework Business Case Approvals: Officer DecisionsA. To note the Officer Decisions for projects under the Single Assurance Framework delegation from Funding Panels hel... Noted Open
7 Sep 2026 Closure of Subsidiary Cambridgeshire and Peterborough Business Growth Company Limited(Unanimous) A. To recommend that the Combined Authority Board approve the Shareholder documentation as appended at Ap... Approved Open
7 Sep 2026 Work ProgrammeA. To note the Funding Committee’s . Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies