A. To note the financial position of the Environment and Sustainable Communities Division for the financial year 24/25 to the end of the third quarter, December 2024. B. To recommend to the Investment Committee that up to £100k additional capital funding be allocated from the Climate Capital fund to the Opportunity Fund to ensure the original £1m is fully allocated as set out in section 5. C. To note the financial forecast to year end in 31 March 2025. A. To note the financial position of the Environment and Sustainable Communities Division for the financial year 24/25 to the end of the third quarter, December 2024. B. To recommend to the Investment Committee that up to £100k additional capital funding be allocated from the Climate Capital fund to the ... view the full minutes text for item 10.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A Note the financial position of the Environment and Sustainable Communities Division for the financial year 24/25 to the end of the third quarter, December 2024. B To recommend to the Investment Committee that up to £100k additional capital funding be allocated from the Climate Capital fund to the Opportunity Fund to ensure the original £1m is fully allocated as set out in section 5. C Note the financial forecast to year end in 31 March 2025
Strategic Objective(s):
The proposals within this report fit under the following strategic objective(s): X Achieving ambitious skills and employment opportunities X Achieving good growth X Achieving best value and high performance
1. Purpose
1.1To provide an update of the performance against budget for the third quarter, up to the period ending December 2024. 1.2 To provide an overview of the budget forecast to end of the financial year, 31 March 2025. 1.3 To consider a steer to the Investment Committee on 10 March to enable the maximum deployment of the Climate Opportunity Fund. 2. Background
2.1In the Medium-Term Financial Plan (MTFP), the Combined Authority Board set a budget of £29.2m for activities directly overseen by the Environment and Sustainable Communities Committee in the five year period from 2024 to 2029. Appendix 1 sets out the current revenue and capital budgets within the Committee’s remit for 2024-25 to 2027-28, as approved by the CA Board in January 2024, and updated for subsequent Board decisions and funding announcements.
2.2The Committee also receives reports from the Greater South East Net Zero Hub (GSENZH) as part of the Combined Authority’s Accountable Body role for the Hub. GSENZH is responsible for government funding totalling £64.2m over the same period, delivered across 140 local authorities of the south east region.
2.3Table 1 shows the capital budget within the terms of reference of the Committee. Two climate projects (Peat Affected Roads and Connecting Cambridgeshire) are recorded in the MTFP under other sub- headings and are shown as such on the Table. This Table excludes capital grant controlled by GSENZH (£27.7m). Table 1: E&SC Capital budget (£’000s) 2024/25 2025/26 2026/27 2027/28 2028/29 Subtotal Climate 3,445 5,469 3,235 3,517 0 12,149 Climate (Transport) 25 150 1,275 50 0 1,500 Climate (Digital) 0 500 0 0 0 500 Housing 7,469 3,173 0 0 0 10,642 TOTAL 10,939 9,292 4,510 3567 0 28,308
2.5Previous decisions and approvals mean that all the capital allocation in 24/25 is committed, and a significant proportion of 25/26. £1.325m of capital is uncommitted and available to be allocated against priorities in 25/26. The entirety of the £10.6m housing capital is committed against schemes currently in delivery.
3.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting held on 23 June 2026 were approved as an accurate record. The Action Log was noted by the ...
Regional Energy Governance Proposals(Unanimous) A. To recommend to the Combined Authority Board to agree the proposal for the CPCA Area Energy Governance...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.