AI summaryGrowth Committee notes 2025/26 outturn with major slippage on Net Zero Hub and Resilience budgets, most to be carried forward into 2026/27, and requests a member briefing.
Written from the decision and the officer reportPDF Pro
OutcomeNotedOutturn and 4 year budgets noted
MoneyLarge 25/26 slippageMost variance to be carried forward
What happens nextMember briefing on budgetsOfficers to brief Committee members
Who it affectsGrowth programme deliverySlippage carried forward to 26/27
What was decided
The Committee noted the outturn financial position of the Growth Committee's budgets for 2025/26 and Board approved carry forwards. Report P1
The Committee noted the 4 year budgets updated for approved carry forward, with Economic Growth budgets to be included from the Q1 26/27 budget update report. Report P1
Officers were asked to arrange a briefing session for Committee members on the budget and funding arrangements.
Why
The Combined Authority annually approves a budget for the forthcoming year as part of a 4 year Medium Term financial plan and reports the outturn to the relevant committee. Report 2.1
Two reporting changes start in 2026/27: Economic Growth budgets transfer in following the Business Board review, and Resilience budgets will be shown under a new Place heading alongside digital connectivity and Housing.
Several major programmes had delayed spend in 2025/26 because of new legislation, recruitment timescales, or reprofiled delivery into 2026/27. Report 3.3, 3.5
What happens next
Officers will arrange a briefing for Committee members on the budget and funding arrangements.
Economic Growth budgets will be incorporated into reports to the Committee from the Q1 26/27 budget update. Report P1
Resilience budgets will be presented under the new Place heading from 2026/27.
7,478k Resilience capital budget FY 25/26 Report P24
6,544k Resilience capital actual FY 25/26 Report P24
1,473k HUG2 A Capital variance FY 25/26 Report P29
1.554m Additional MHCLG funding for Spatial Development Strategy for 26/27 and 27/28 Report 3.3
Implications
Financial: No further financial implications beyond those set out in the main body of the report. Report P33
Legal: The Combined Authority is required to prepare a balanced budget in accordance with statutory requirements. Report P33
Other: From Q1 26/27 the Committee will receive Economic Growth budgets, and Resilience budgets will be shown under a new Place heading.
Who and where
Growth Committee members, who will receive a briefing on budget and funding arrangements
Cambridgeshire Fire and Rescue Service, which is delivering the Local Remediation Acceleration Plan Report 3.3
DESNZ, in relation to HUG2 closure and the final repayment Report 3.5, 4.4
MHCLG, as funder of the Spatial Development Strategy work Report 3.3
Natural Cambridgeshire, as recipient of the Nature and Environment Investment Fund allocation Report 4.2
Timeline
26 February 2025: Previous meeting received the 2025/26 budget performance to January 2026 Report 2.1
Q1 26/27: Economic Growth budgets to be included in in-year reports to the Committee
31 March 2025: End of the HUG2 programme delivery window Report 3.5, 4.4
2025/26 financial year (period to 31 March 2026): Outturn reporting period covered by this report Report 1.1, 3.1
May 2026: English Devolution and Community Empowerment Bill became an Act, allowing resilience plan work to be scoped Report 3.3
Plain English for the jargon
CPCA: Cambridgeshire and Peterborough Combined Authority
GSENZ Hub: Greater South East Net Zero Hub, for which the Combined Authority is the Accountable Body
LRAP: Local Remediation Acceleration Plan
SDS: Spatial Development Strategy
HUG2: Home Upgrade Grant phase 2
MHCLG: Ministry of Housing, Communities and Local Government
DESNZ: Department for Energy Security and Net Zero
FO: Forecast Outturn, as used in the budget tables
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
A To note the outturn financial position of the Growth Committee’s budgets for the financial year 25/26 and Board approved carry-forwards . B To note the Growth Committee’s budgets for the next 4 years updated for approved carry-forward and that those related to Economic Growth will be included from the Q1 26/27 budget update report. A To note the outturn financial position of the Growth Committee’s budgets for the financial year 25/26 and Board approved carry-forwards . B To note the Growth Committee’s budgets for the next 4 years updated for approved carry-forward and that those related to Economic Growth will be included from the Q1 26/27 budget update report. ACTION: 1. Officers to arrange a briefing session for Members on the Committee's budget and funding arrangements.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A To note the outturn financial position of the Growth Committee’s budgets for the financial year 25/26 and Board approved carry-forwards. B To note the Growth Committee’s budgets for the next 4 years updated for approved carry-forwards and that those related to Economic Growth will be included from the Q1 26/27 budget update report.
Strategic Objectives:
The proposals within this report fit under the following strategic objective(s):
☒ Growth ☒ Jobs ☐ Resilience
☐ Connectivity ☐ Homes ☒ Performance
1. Purpose
1.1To provide the outturn position for 2025/26 against the 2025/26 budgets. 1.2 The Combined Authority annually approves a budget for the forthcoming year as part of a 4-year Medium-Term financial plan.
Background
2.1At the last meeting on 26 February 2025, the Committee was provided with an analysis of the 2025/26 performance against budget to January 2026. This report provides an update covering up to March 2026. 2.2 Details of the Growth Committee budgets for the next 4 years are shown in appendix A. The Combined Authority is also the Accountable Body for the South East Net Zero Hub and their expenditure and budgets are also shown. 2.3 There are two changes to the budgetary reporting to the Committee in 2026/27, the Committee’s new terms of reference, and the changes to the CPCA’s management structure which was approved via the Staffing Committee in February. The current Terms of Reference of the Committee include responsibility for Growth related budgets in the CPCA, having transferred from the Business Board following the review of the Business Board in 2025/26. As such, from Q1, in-year budget reporting to the Committee will include the budgets within the Economic Growth area of the CPCA’s budgets. The second change, related to the new corporate structure, will be presentational with the Resilience budgets now sitting within the larger “Place” budget group along with digital connectivity and Housing. This is not a change to what the Committee will receive, it simply means there will be different headings
3. Revenue Expenditure
3.1A breakdown of income for the period to 31 March 2026 is set out in Table 1 below. Table 1
25/26 25/26 25/26 25/26 Growth Committee Resilience Income Budget FY Actual FY Variance FY Slippage
£k £k £k £k Biodiversity Net Gain -27 -27 0 0 Local Nature Recovery Strategy -136 -136 0 0 Spatial Development Strategy 0 -1,554 -1,554 1,554 Local Remediation Acceleration Plan (LRAP) -225 -225 0 0 Cambs Constabulary Solar Canopy (Renewables Fund) -700 -700 0 0 Resilience Total -1,088 -2,642 -1,554 1,554
25/26 25/26 25/26 25/26 Greater South Net Zero Hub Income Budget FY FO FY Variance FY Deferral
£k £k £k £k Community Energy Fund -1,280 -1,280 0 0 Social Housing Tech Assistance 0 -21 -21 0 Heat Network Zoning Implementation -70 -70 0 0 HUG2 A 23/24 A&A Costs 0 -32 -32 0 Local Net Zero Hubs Programme (S31 Grant) -1,420 -1,420 0 0 Net Zero GO -500 -500 0 0 GSENZ Hub Total -3,270 -3,323 -53 0
The main variance relates to the Spatial Development Strategy, the income here is a receipt in advance to fund the forthcoming Spatial Development Strategy. 3.2 A breakdown of the Resilience Revenue Expenditure for the period to 31 March 2026 is set below Table 2
Follow Growth Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting held on 23 June 2026 were approved as an accurate record. The Action Log was noted by the ...
Regional Energy Governance Proposals(Unanimous) A. To recommend to the Combined Authority Board to agree the proposal for the CPCA Area Energy Governance...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.