A. To note the outturn financial position of the Committee for the financial year 24/25 and Board approved carry-forwards . B. To note the current budget for the next 4 years updated for approved carry-forwards pending any review of the Corporate Plan and Budget.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A Note the outturn financial position for this committee for the financial year 24/25 and Board approved carry-forwards. B Note the current budget for the next 4 years updated for approved carry-forwards pending any review of the Corporate Plan and Budget.
Strategic Objective(s):
The proposals within this report fit under the following strategic objective(s): x Achieving ambitious skills and employment opportunities x Achieving good growth x Achieving best value and high performance
1. Purpose
1.1To provide the outturn position for 2024/25 against the 2024/25 budgets. 1.2 The Combined Authority annually approves a budget for the forthcoming year as part of a 4-year Medium-Term financial plan.
Background
2.1At the last meeting on 26 February 2025, the Committee was provided with an analysis of the 2024/25 performance against budget to January 2025. This report provides an update covering up to March 2025. 2.2 Details of the budgets for the next 4 years are shown in appendix A. 3. Revenue Expenditure
3.1A breakdown of the Environment and Sustainable Communities division income for the period to 31 March 2025 is set out in the table below.
24/25 24/25 24/25 Variance Environment and Sustainable Communities Climate Income Budget FY Actual FY
£k £k £k Biodiversity Net Gain -54 -27 -27 Local Nature Recovery Strategy -144 -144 0 Climate Total -198 -171 -27
24/25 24/25 24/25 Variance (Accountable Body) Greater South East Net Zero Hub Income Budget FY Actual FY £k £k £k Community Energy Fund -1,401 -1,589 188 Community Energy Capacity Building -150 0 -150 DESNZ Regional Skills Pilot -9 -48 39 GSE Energy Hub 0 -76 76 HUG2 A Revenue 23/24 0 -2,944 2,944 GSE Local Energy Advice Demonstrator -1,970 -1,969 -1 GSE Net Zero Hub -3,320 -4,117 797 Social Housing Technical Assistance Fund -18 -40 22 GSE Public Sector Decarbonisation -400 -400 0 GSENZ Hub Total -7,268 -11,183 3,915
The variances against budget are predominantly related to reduced project expenditure set out in the revenue and capital sections below.
3.2A breakdown of the Committee Climate, Nature and Spatial Planning Revenue Expenditure for the period to 31 March 2025 is set out in Table 2 below.
24/25 24/25 24/25 24/25 Environment and Sustainable Communities Climate Variance Approved Budget FY Actual Revenue Expenditure FY Slippage £k £k £k £k Biodiversity Net Gain Grant 27 47 20 - Climate Action Plan and Delivery 70 158 88 - Fenland Soil 60 60 0 - Constituent Authority Biodiversity Contribution 350 50 -300 300 Doubling Nature Metrics 91 0 -91 91 Greater Cambridge Chalk Stream Project 26 26 0 - Huntingdonshire Biodiversity for all 150 145 -5 5 Local Nature Recovery Strategy 144 265 121 - Natural Cambridgeshire 130 120 -10 - Non Statutory Spatial Plan 130 140 10 - Climate Evidence and Data 98 51 -47 47 Climate Action 102 106 4 - Future Fens 70 8 -62 63 Local Energy Plan 10 10 0 - Climate Total 1,458 1,186 -272 506 3.3 Constituent Authority Biodiversity Contribution – this budget was approved to provide support (for delivery over the period to December 2025) for constituent authorities where they have received new responsibilities in relation to the promotion and monitoring of biodiversity. The specific activity is to commission biodiversity audits. Grant funding agreements are sealed with six of seven authorities (Fenland outstanding). In 2024/25, £50K was claimed and we have already received invoices for £150K in FY2025/26 that have been processed. The remaining £150K budget will be drawn down on completion of the required milestones.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting held on 23 June 2026 were approved as an accurate record. The Action Log was noted by the ...
Regional Energy Governance Proposals(Unanimous) A. To recommend to the Combined Authority Board to agree the proposal for the CPCA Area Energy Governance...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.