Budget and Performance Report

Noted Committee 1 paper

AI summaryCambridgeshire and Peterborough Combined Authority Skills Committee noted the Skills Division's 2025/26 financial position to September 2025, with income £1.5m above budget and forecast expenditure £0.4m over budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFinancial position to September 2025 noted
Money£0.4m forecast overspendExpenditure forecast £0.4m over budget; income £1.5m above
What happens nextNot stated
Who it affectsSkills Division and providersAdult education, bootcamps and skills programmes

What was decided

The Committee noted the financial position of the Skills Division for the financial year 2025/26 to September 2025. Report P1

Why

The report fits the Combined Authority's strategic objectives of growth, jobs and performance. Report P5, P6, P9

Income to September 2025 was £12.8m, 53% of the £24.2m annual budget, with a forecast £1.5m above budget due to extra Adult Education Budget and Connect to Work funding. Report 2.1

Expenditure was lower than budget to date but is forecast at £0.4m above budget by year end, driven by an £0.8m increase for Connect to Work offset by a £0.4m reduction in Free Courses for Jobs. Report 2.1, 2.4

The money

  • £12.8m Skills income received to September 2025 Report 2.1
  • £24.2m Overall Skills grant income budget for 2025/26 Report 2.1
  • £1.5m Forecast income above budget for the year Report 2.1
  • £12.4m Adult Education Budget income received
  • £0.4m Forecast expenditure overspend against budget Report 2.1, 2.4
  • £0.8m Forecast increase for Connect to Work Report 2.1, 2.4
  • £0.4m Forecast reduction for Free Courses for Jobs Report 2.1, 2.4

Implications

  • Financial: No additional financial implications beyond those described in the main body of the report. Report P16
  • Legal: The Combined Authority is required to prepare a balanced budget in line with statutory requirements.

Who and where

  • Adult education and skills training providers paid from Skills Division budgets Report 2.4
  • Learners on Adult Education Budget, Bootcamps, Youth Guarantee Trailblazer, Free Courses for Jobs and Connect to Work programmes Report 2.4

Timeline

  • To 30th September 2025: Year-to-date actuals reported
  • End of 2025/26: Bootcamp Wave 6 advance funding still expected; Youth Guarantee Trailblazer spend expected to catch up Report 2.4

Plain English for the jargon

  • AEB: Adult Education Budget
  • CPCA: Cambridgeshire and Peterborough Combined Authority
  • FCFJ: Free Courses for Jobs
  • UKSPF: UK Shared Prosperity Fund
  • CEC: Careers and Enterprise Company
  • YTD: Year to date
  • FO: Forecast outturn
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

A. To note the financial position of the Skills Division for the financial year 2025/26 to September 2025. A. To note the financial position of the Skills Division for the financial year 2025/26 to September 2025.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Skills Committee

Recommendations

A Note the financial position of the Skills Division for the financial year 2025/26 to September 2025

Strategic Objective(s):

The proposals within this report fit under the following strategic objective(s):

☐ Connectivity

☒ Growth

☒ Jobs

☐ Homes

☐ Resilience

☒ Performance

1. Purpose

1.1To provide an update of the financial position for 2025/26 up to the period ending September 2025

2. Revenue Income and Expenditure

2.1SUMMARY Income: To September 2025 the CPCA has received funds of £12.8m. This is 53% of the overall budget for the year of £24.2m. The forecast is £1.5m above budget, this is due to extra fund for AEB and Connect to Work. Expenditure: Spent to June 2025 is £2.3m lower than budget to date. The underspend is mainly due to the Youth Guarantee Trailblazer (£1.8m) where delivery has started later than planned. The forecast is set at £27.7, £0.4m over budget. This is due to the increase of funds for Connect to Work (£0.8m) offset by a reduction in Free Courses For Jobs (£0.4m). 2.2 Income headlines CPCA has received £12.8m to September 2025, equating to 53% of the income, most of it comes from the Adult Education Budget (£12.4m). Actual to date is £1.7m lower than budget. This is due to delay in receiving the advance funding for Bootcamp Wave 6, which is still expected by the end of the year. The forecast is £1.5m (6%) above budget, this is due to extra funding for AEB and Connect to Work. 2.3 Table 1 Skills Grant Income 25/26 25/26 25/26 25/26 25/26 25/26 Actual Budget Variance Budget FO FY Variance YTD Act to Bud FY FY Deferra Skills Grant Income for the period YTD to 30th September 2025 £k l £k £k £k £k £k £k

Adult Education Budget -12,411 -11,856 -555 -11,856 -12,411 -555 0 AEB Level 3 Courses -134 -738 604 -738 -738 0 0 Bootcamp Wave 5 0 0 0 -2,291 -2,291 0 0 Bootcamp Wave 6 0 -1,816 1,816 -3,886 -3,886 0 0 CEC Career Hub -45 -52 6 -322 -322 0 0 Connect to Work -100 0 -100 0 -895 -895 0 Youth Guarantee Trailblazer -73 0 -73 -5,160 -5,160 0 0 Total Skills Grant Income -12,764 -14,461 1,698 -24,253 -25,702 -1,450 0

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget and Performance ReportReport 134 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 18 attended
LN
Councillor Lucy Nethsingha Mayor's RepresentativeChair, present
SW
Councillor Sam Wakeford Huntingdonshire District CouncilVice-Chair, apologies, sent representative
AN
Councillor Antoinette Nestor Cambridge City CouncilCommittee Member, apologies
MG
Councillor Mark Goldsack East Cambridgeshire District CouncilCommittee Member, present
IB
Councillor Ian Benney Fenland District CouncilCommittee Member, apologies, sent representative
KC
Councillor Katy Cole Peterborough City CouncilCommittee Member, present
EW
Councillor Eileen Wilson South Cambridgeshire District CouncilCommittee Member, present
CH
Charlotte Horobin Business BoardCo-Optee, present
KD
Katy Davies Business BoardCo-Optee, present
LV
Councillor Lucius Vellacott Overview and Scrutiny Committee RapporteurGuest, in attendance
AB
Councillor Alex Bulat Overview and Scrutiny Committee GuestGuest, in attendance
DH
Councillor Dr Haq Nawaz Fenland District CouncilCommittee Member, present as substitute

All 18 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Budget and Performance ReportThis decision
  2. Budget and Performance Report - Drawdown of Transport Capacity GrantApproved
  3. Budget and Performance ReportNoted
  4. Budget & Performance ReportNoted
  5. Budget and Performance ReportNoted
  6. Budget and Performance ReportNoted

More from Cambridgeshire and Peterborough Combined Authority Skills Committee

All decisions
MeetingDecisionOutcome
14 Sep 2026 Declaration of InterestsCouncillor Davey declared an interest by virtue of his role as a Director of Cambridgeshire United Football Club. Decided Open
14 Sep 2026 Minutes of the previous meetingThe Minutes of the meeting held on 15 June 2026 were approved as an accurate record. The Action Log was noted by the ... Approved Open
14 Sep 2026 Public QuestionsNo public questions were received. Decided Open
14 Sep 2026 Forward PlanA To note the CPCA’s Forward Plan for September 2026. Noted Open
14 Sep 2026 Director's Highlight ReportA. To note the contents of the report. Noted Open