Budget and Performance Report

Noted Committee 1 paper

AI summaryCambridgeshire and Peterborough Combined Authority Transport Committee noted the 2025/26 transport budget position to September 2025. Revenue spend was £3.4m below profile and capital £22.9m behind, with £27.5m of capital expected to slip into 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the financial position of the Transport Division
Money£27.5m capital slip expectedCapital programme expected to slip into 2026/27
What happens nextUpdated forecast at next meetingBus franchising review to conclude in early 2026
Who it affectsTransport Division, partner councils, passengersDelivery of capital and revenue transport programmes

What was decided

The committee noted the financial position of the Transport Division for the 2025/26 financial year to September 2025. Report P1

The report is aligned with the strategic objectives of Growth, Jobs and Performance. Report P4, P5

Why

The Combined Authority is required by law to prepare a balanced budget and to track performance against it. Report P16

Income and expenditure have been monitored against the 2025/26 profiled budget for the period to 30 September 2025. Report 1.1, 2.1

Material variances in both revenue and capital have emerged and need to be reported to the committee.

What happens next

The trend in concessionary fare passenger numbers will be reviewed and an updated forecast reported at the committee's next meeting.

The bus franchising review is expected to conclude in early 2026, after which the development of bus franchising forecast will be reassessed. Report P13

Around £27.5m of capital funding will be reprofiled into future years, with significant sums slipping into 2026/27. Report P13

The money

  • -38,921 Transport income year to date (actual, £k) Report 3.1
  • -89,460 Transport income forecast outturn (£k), £18,599 below budget due to Peterborough Station Quarter delay Report 3.1
  • 8,793 Transport revenue expenditure year to date (actual, £k) Report P12
  • -3,404 Revenue expenditure underspend against budget year to date (£k) Report P12
  • -2,307 Revenue forecast outturn variance (£k), of which £1,555k to slip into 2026/27 Report P12
  • 2,550 Transport capital expenditure year to date (actual, £k) Report P13
  • -22,885 Capital expenditure variance against budget year to date (£k) Report P13
  • -27,659 Capital forecast outturn variance (£k), with £27,514k to be deferred Report P13

Implications

  • Financial: Officers state there are no direct financial implications arising from noting the report; the variances reflect timing rather than lost funding in most cases. Report P16
  • Legal: The Combined Authority remains under a statutory duty to prepare a balanced budget.
  • Other: Concessionary fare passenger numbers remain below pre-Covid levels, and the impact of the pre-9.30am change has not yet been seen.

Who and where

  • Transport Division of the Combined Authority Report P1
  • Partner authorities receiving highways maintenance grants
  • Bus passengers, including concessionary fare users and under-25s
  • Peterborough City Council, as delivery partner for Peterborough Station Quarter Report P13

Timeline

  • Period to 30 September 2025: Financial reporting period covered by the report Report 1.1, 2.1, 3.1, 4.1
  • Early 2026: Bus franchising pathways review expected to conclude Report P13
  • After the Christmas embargo period: March junction improvement construction now expected to start Report P13
  • Near the end of 2025/26: Peterborough Station Quarter construction expected to start Report P13
  • 2027: A10 upgrade Outline Business Case to be submitted to the Department for Transport Report P13

Plain English for the jargon

  • BSIP+: Bus Service Improvement Plan Plus, a Government grant programme
  • LTCP: Local Transport and Connectivity Plan
  • LEVI: Local Electric Vehicle Infrastructure fund
  • FBC: Full Business Case
  • OBC / SOBC: Outline Business Case / Strategic Outline Business Case
  • DfT: Department for Transport
  • PCC: Peterborough City Council
  • CPCA: Cambridgeshire and Peterborough Combined Authority
  • LUF: Levelling Up Fund
  • FO / FY / YTD: Forecast Outturn, Financial Year, Year To Date
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

RESOLVED A. To note the financial position of the Transport Division for the Financial Year 25/26 to September 2025.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Transport Committee

Recommendations

A Note the financial position of the Transport Division for the financial year 25/26 to September 2025

Strategic Objectives:

The proposals within this report fit under the following strategic objective(s):

☒ Growth ☒ Jobs ☐ Resilience

☐ Connectivity ☐ Homes ☒ Performance

1. Purpose

1.1To provide an update of the financial position for 2025/26 and to provide analysis against the 2025/26 budgets, up to the period ending September 2025.

Background

2.1This report provides an update of the performance against budget up to the period ending September 2025. Tables show approved budgets. 3. Revenue Income and Expenditure

3.1A breakdown of the Transport income for the period to 30 September 2025 is set out in Table 1 below. 25/26 25/26 25/26 25/26 25/26 25/26 Actual Budget Varianc Budget Varianc Transport Income FO FY YTD YTD e YTD FY e FY £k £k £k £k £k £k Highways Maintenance and Pothole Fund -21,060 -21,060 0 -42,120 -42,120 0 Bus Service Improvement Plan (BSIP+) -10,179 -10,179 0 -10,179 -10,179 0 Public Transport - Bus Service Operators -409 -409 0 -411 -409 2 Grant Active Travel 5 0 0 0 -1,607 -1,607 0 Peterborough Station Quarter 0 0 0 -20,597 -2,000 18,597 Transport capacity grant -410 -410 0 -819 -819 0 Transport Levy -6,863 -6,863 0 -13,727 -13,727 0 Total Transport Income -38,921 -38,921 0 -89,460 -70,861 18,599 Table 1

3.2The income received to date in the year is £39m in line with the profiled budget. 3.3 The forecast outturn is lower than budget to match expenditure in delivery of Peterborough Station quarter, which has been delayed, as explained below. 3.4 A breakdown of the Transport Revenue Expenditure for the period to 30 September 2025 is set out in Table 2 below.

25/26 25/26 25/26 25/26 25/26 25/26 25/26 Actual Budget Variance Budget FO Variance Transport Revenue Expenditure Deferral YTD YTD YTD FY FY FY

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget and Performance ReportReport 183 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 18 attended
RJ
Richard JeremyOfficer, expected
CB
Councillor Chris Boden Mayor's RepresentativeChair, present
KT
Councillor Katie Thornburrow Cambridge City CouncilCommittee Member, present
AB
Councillor Alex Beckett Cambridgeshire County CouncilVice-Chair, present
AS
Councillor Alan Sharp East Cambridgeshire District CouncilCommittee Member, present
CS
Councillor Chris Seaton Fenland District CouncilCommittee Member, present
SW
Councillor Sam Wakeford Huntingdonshire District CouncilCommittee Member, present
PM
Councillor Peter McDonald South Cambridgeshire District CouncilCommittee Member, present
AE
Councillor Angus Ellis Peterborough City CouncilCommittee Member, present
RS
Rebecca Stephens Business BoardCo-Optee, apologies
JN
Councillor Jon Neish Overview and Scrutiny Committee RapporteurGuest, expected
SS
Councillor Simon Smith Cambridge City CouncilSubstitute

All 18 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Budget and Performance ReportThis decision
  2. Budget and Performance Report - Drawdown of Transport Capacity GrantApproved
  3. Budget and Performance ReportNoted
  4. Budget & Performance ReportNoted
  5. Budget and Performance ReportNoted
  6. Budget and Performance ReportNoted

More from Cambridgeshire and Peterborough Combined Authority Transport Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of the previous meetingThe minutes of the meeting on 17 June 2026 were approved as an accurate record. The Action Log was noted by the Commi... Approved Open
9 Sep 2026 Forward PlanA. That the Combined Authority Forward Plan be noted A. That the Combined Authority Forward Plan be noted. ACTION: 1.... Noted Open
9 Sep 2026 Developer Funding Governance(Unanimous) A. To note the CPCA action plan to improve governance and delivery of developer funding for bus services ... Noted Open
9 Sep 2026 Bus Services Reimagined – Final Service Change ProposalsA. To note the outcome of the contracted bus services review, including the evidence base, consultation feedback and ... Noted Open
9 Sep 2026 Local Transport Delivery Plan(Unanimous) To recommend to the Combined Authority Board that they: A. Approve the (LTDP) – Cambridgeshire County Cou... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies