CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cambridgeshire and Peterborough Combined Authority
Combined Authority Board, Wednesday 26 November 2025 at 10.00am

Single Assurance Framework Review – KD2025/045

Approved Committee 3 papers

AI summaryCambridgeshire and Peterborough Combined Authority Board approved an updated Single Assurance Framework that raises officer spending limits and speeds up project approvals, before submission to Government.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedWill be sent to Government for sign-off
MoneyNo material financial implicationsBut new delegation limits set at £500k and £2m
What happens nextSubmit to GovernmentMHCLG to review the framework after Board approval
Who it affectsCombined Authority projects and staffChanges how CPCA approves and runs programmes

What was decided

The Board approved the updated Single Assurance Framework at Appendix A, which will then be submitted to Government under the sign-off process for Local Assurance Frameworks. Report P1

Delegated approval thresholds were raised: Executive Directors can now approve business cases up to £500,000, and the Chief Executive's limit rises from £1m to £2m; the Funding Committee covers £2m to £5m and the Board covers over £5m.

Projects funded by ringfenced grants can now go straight to the business case stage with a shorter cover report, and all change request values will be cumulative.

Why

The Single Assurance Framework is intended to be reviewed annually as part of good governance, and the current version has been in operation for over a year. Report 2.1

Internal engagement and the Chief Executive Group backed higher delegation limits to move projects into delivery faster, with assurance and risk checks unchanged from current Green Book compliance.

A robust local assurance framework is required before the Authority can apply to become an established mayoral strategic authority and access wider devolution and an Integrated Settlement. Report 2.1

What happens next

The Monitoring Officer will make the required constitutional changes following Board approval, including aligning the Funding Committee's Terms of Reference with the new Framework.

A training schedule for CPCA and constituent council officers will be put in place after the decision.

A further Board report will come back after MHCLG review to confirm the SAF's status and any amendments needed for clearance; the Framework will also be updated once the Business Board arrangements review concludes. Report 2.1

The money

  • £500k New Executive Director delegation ceiling for business cases and timing change requests up to 3 months
  • £2m Raised Chief Executive delegation ceiling, previously £1m Report 3.1
  • £5m Upper limit for Funding Committee approval of concept and business cases

Options considered

  • Chosen: Preferred option: raise ED delegation to £500k and CEX delegation to £2m, with ringfenced grants going straight to business case. Based on consultation with Corporate Management Team and Chief Executive Group, which supported significantly higher delegation to speed delivery while retaining robust governance
  • Rejected: Earlier internal proposal of £100k Executive Director approval threshold. Chief Executive Group and Public Service Board feedback pushed for a much higher limit, suggesting £500k

Implications

  • Legal: The Single Assurance Framework is set out in the CPCA Constitution; the Monitoring Officer will make the required constitutional changes after Board approval, and MHCLG must clear the updated Framework. Report 2.1
  • Financial: Officers report no material financial implications; a more efficient framework should improve value for money across projects and services. Report P14
  • Equalities: No public health, environmental, climate change or other significant implications identified in the report.
  • Risk: Streamlining delegation levels does not change existing quality assurance or risk checks, which remain in line with Green Book compliance; monitoring of delegated decisions will continue to be reported to the Funding Committee and Board.
  • Governance: The Audit and Governance Committee recommended approval and asked for an explicit public communication plan in monitoring and evaluation, a periodic review of intended benefits, and an active feedback mechanism; officers confirmed these are addressed in the updated Framework.

Who and where

  • CPCA Executive Directors, Section 73 Officer, Monitoring Officer and Chief Executive, who gain new or expanded approval powers
  • Members of the Funding Committee and Combined Authority Board, who will see fewer low-value papers and focus on larger projects
  • Officers of CPCA and constituent councils, who will receive refresher training on the updated process
  • Project sponsors and partners seeking CPCA funding, including those bringing ringfenced grant bids

Timeline

  • November 2023: Original Single Assurance Framework approved by the Combined Authority Board and endorsed by MHCLG Report 3.1
  • July 2024: Removal of the best value notice, formally notified September 2024, supported by the SAF Report 3.1
  • 30 July 2025: Draft SAF proposals shared with the Corporate Management Team for engagement
  • 8 September: Review session with the Combined Authority Chief Executive Group and Cambridgeshire and Peterborough Public Service Board
  • 2025-11-26: Combined Authority Board approves the updated Single Assurance Framework for submission to Government Report P1

Plain English for the jargon

  • Single Assurance Framework (SAF): The Combined Authority's set of systems and processes for appraisal, assurance, risk and performance across the life of projects and programmes, also called a Local Assurance Framework
  • MHCLG: Ministry of Housing, Communities and Local Government, which must clear the framework
  • CPCA: Cambridgeshire and Peterborough Combined Authority
  • MTFP: Medium Term Financial Plan, the source of matched CPCA funding referenced in approval routes
  • S73 Officer: The Section 73 Officer, the Authority's chief finance officer responsible for proper financial administration
  • Ringfenced grant: Government funding earmarked for specific purposes, which the Authority has limited choice to redirect elsewhere
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

It was resolved to : A Approve the updated Single Assurance Framework (Appendix A), noting that it will then be submitted to Government in accordance with the sign off process for Local Assurance Frameworks
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Combined Authority Board

Recommendation

A To approve the updated Single Assurance Framework (Appendix A), noting that it will then be submitted to Government in accordance with the sign off process for Local Assurance Frameworks

Strategic Objectives:

The proposals within this report fit under the following strategic objective(s):

☒ Growth ☒ Jobs ☒ Resilience

☒ Connectivity ☒ Homes ☒ Performance A strengthened framework and procedure align to all the CPCA’s strategic objectives, this is because robust assurance management supports the effective and efficient delivery of the 2025-29 Corporate Plan.

1. Purpose

1.1The purpose of this report is to present the updated Single Assurance Framework (SAF) document to the Combined Authority Board for approval.

2. Proposal

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Single Assurance Framework Draft Clean Nov25Appendix A 1.2 MB Download
PDF
Options Considered inc Preferred Option (1)Appendix B 89 KB Download
PDF
Single Assurance Framework Review: KD2025/045Report 150 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 20 attended
PB
Paul Bristow Cambridgeshire and Peterborough Combined AuthorityChair, present
AB
Councillor Anna Bailey East Cambridgeshire District CouncilCommittee Member, present
CB
Councillor Chris Boden Fenland District CouncilCommittee Member, present
SC
Councillor Sarah Conboy Huntingdonshire District CouncilCommittee Member, present
LN
Councillor Lucy Nethsingha Cambridgeshire County CouncilCommittee Member, present
SQ
Councillor Shabina Qayyum Peterborough City CouncilCommittee Member, present
AS
Councillor Anna Smith Cambridge City CouncilCommittee Member, present
BS
Councillor Bridget Smith South Cambridgeshire District CouncilCommittee Member, present
NP
Nitin Patel Business BoardCommittee Member, present
DP
Darryl Preston Police and Crime CommissionerCo-Optee, apologies
RP
Robin Porter Central East Integrated Care BoardCo-Optee, apologies, sent representative
CM
Councillor Christopher Morris Cambridgeshire and Peterborough Fire AuthorityCo-Optee, present

All 20 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Single Assurance Framework Review – KD2025/045This decision
  2. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved
  3. Single Assurance Framework Business Case Approvals: Officer DecisionsNoted
  4. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved
  5. Single Assurance Framework Business Case Approvals: Officer DecisionsNoted
  6. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved

More from Cambridgeshire and Peterborough Combined Authority Combined Authority Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti... Approved Open
23 Sep 2026 Public QuestionsOne public question was received. The question is published . Decided Open
23 Sep 2026 Forward PlanIt was resolved to : A Approve the Forward Plan for September 2026 Approved Open
23 Sep 2026 CPCA Meetings CalendarIt was resolved to : A Approve the proposed amendments to the calendar of meetings for the 2026/27 Municipal Year B A... Approved Open
23 Sep 2026 Updates to the ConstitutionIt was resolved to : A Approve the changes to the Constitution as proposed in Sections 4 and 5 of the report and asso... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies