AI summaryCambridgeshire and Peterborough Combined Authority Board noted Q2 2025/26 budget performance and approved a £3m capital virement from the Creative Industries project to the Local Growth Plan Delivery Fund.
Written from the decision and the officer reportPDF Pro
OutcomeNotedMove capital from Creative Industries to Local Growth Plan Delivery Fund
Money£3m capital virementFrom Creative Industries project to Local Growth Plan Delivery Fund
What happens nextBudget 2026/27 and MTFP reportAlso on this Board agenda, covers rephasing of capital budgets
Who it affectsAll Combined Authority strategic objectivesAffects revenue and capital programmes and project delivery
What was decided
The Board noted the Combined Authority's financial performance based on actual expenditure to 30 September 2025. Report P1
The Board approved the reprioritisation and virement of £3m capital from the Creative Industries project to the Local Growth Plan Delivery Fund. Report P1
Why
The report set out year-to-date income and expenditure to the end of September 2025 and full-year forecasts for 2025/26, and the materiality threshold for variances is £200k revenue and £500k capital. Report 1.1, P6
Following discussions with Cambridge City Council, the £3m Creative Industries capital allocation is being removed and reconsidered once the scheme design is further developed. Report 7.1
What happens next
The Creative Industries project is to be removed from the capital programme and the £3m moved to the Local Growth Plan Delivery Fund, taking it to £18.3m.
Capital rephasing proposals, including £20m for bus depots, £2.7m for bus network improvements and £6m for the BP Roundabout, are addressed in the 2026/27 budget and MTFP report on the same agenda.
The money
£3m Capital virement from Creative Industries to Local Growth Plan Delivery Fund
£18.3m Local Growth Plan Delivery Fund total after the £3m reallocation
£4,098k Total revenue forecast underspend against approved budgets
£4.290m Year-to-date underspend on the Local Net Zero Accelerator programme in the GSE Net Zero Hub
£12.930m Overall year-to-date revenue underspend
£29.945m Capital variance prior to rephasing, an increase of £28.402m since Q1
£28.132m Place and Connectivity capital forecast underspend, including £19.932m at Peterborough Station Quarter
£3.795m Active Travel England capital grant for the Capital Consolidation Fund full business case Report 6.3
£0.727m A16 Norwood change request increase from STA budget Report 6.4
£0.1m MHCLG Rough Sleeping Prevention and Recovery Grant Report 6.5
£2.988m Resources and Performance income forecast overachievement, including c£3.0m Treasury Management income Report 5.1
Options considered
Chosen: Approve virement of £3m capital from Creative Industries to Local Growth Plan Delivery Fund. Cambridge City Council discussions concluded the funding can be removed and reconsidered once scheme design is further developed
Rejected: Retain the £3m Creative Industries capital allocation. Under review since the September Board meeting and no longer supported following discussions with Cambridge City Council Report 7.1
Implications
Financial: A £3m virement is required between capital headings, and the Combined Authority is required to maintain a balanced budget under statutory requirements. Report P29
Legal: Monitoring is carried out in line with the Cambridgeshire and Peterborough Combined Authority Order 2017 and the Combined Authorities Financial Order 2017.
Climate: A number of projects in delivery or planned have direct Environmental and Climate Change benefits.
Other: A number of projects in delivery or planned have direct Public Health benefits.
Who and where
All Combined Authority strategic objectives and programme delivery Report P3
Cambridge City Council, as partner in the Creative Industries scheme Report 7.1
Cambridgeshire County Council and Peterborough City Council as active travel delivery partners Report 6.3
Constituent councils and a delivery charity receiving the Rough Sleeping Prevention and Recovery Grant Report 6.5
Timeline
as at 30 September 2025: Cut-off for year-to-date actuals reported in this paper Report 1.1, 3.1
2025/26: Financial year covered by the budget monitoring report Report 1.1, P6
3 November 2025: Funding Committee meeting whose decisions are reported here
2025/26 financial year: Local Net Zero Accelerator expected to complete, with possible c£280k slippage into 2026/27 under discussion with DESNZ
2026/27: Start of the next financial year covered by the MTFP 2026-2030 report on this agenda
Plain English for the jargon
Virement: Transfer of budget between approved headings
YTD: Year to date
DESNZ: Department for Energy Security and Net Zero
GSE: Greater South East
LCWIP: Local Cycling and Walking Infrastructure Plan
SAF: Strategic Assurance Framework
STA: Subject to Approval budget, pending business case
MTFP: Medium Term Financial Plan
MHCLG: Ministry of Housing, Communities and Local Government
CPCA: Cambridgeshire and Peterborough Combined Authority
DfT: Department for Transport
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13
Resolved
It was resolved to : A Note the financial performance of the Combined Authority based on the actual expenditure as at 30 September 2025. B Approve the reprioritisation and virement of £3m capital from the Creative Industries project to the Local Growth Plan Delivery Fund as set out in section 7.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A To note the financial performance of the Combined Authority based on the actual expenditure as at 30 September 2025. B To approve the reprioritisation and virement of £3m capital from the Creative Industries project to the Local Growth Plan Delivery Fund as set out in section 7.
Strategic Objective(s):
The proposals within this report impact on all of the Combined Authority’s strategic objectives as understanding the budget available for 2025/26 and the current forecasts against it allows the continuation of the delivery of the Authority’s programmes in an efficient manner, and within its means.
1. Purpose
1.1This report provides the Board with an update on the income and expenditure received to the end of September 2025 and forecasts of financial performance to the end of the financial year 2025/26. 1.2 It also requests the Board to approve the reallocation of £3m capital funding from the Creative Industries scheme, removing it from the capital programme, to the Local Growth Plan Delivery Fund in light of further discussions following the corporate review of projects reported in September.
Background
Budget Update 2.1 This report presents the year to-date actual expenditure and associated budgets along with the full year budgets and outturn forecasts for the 2025/26 financial year. 2.2 The figures presented in the body of the report and Appendix 1 show the spend against those budgets which have been approved to spend by the Board, or relevant Committee, and are thus being actively delivered against, Appendix 2 sets out the project budgets which have been allocated subject to business case approval and shown as “Subject to Approval”. 2.3 The materiality threshold above which expenditure outturn variances for the year are required to provide a specific explanation within Appendix 3 are £200k for all revenue budgets and £500k for capital projects. 2.4 The budget update report also includes a summary of the position against the thematic funds and reports the investment decisions approved by the Chief Executive and Funding Committee as part of the delegated authority provided through the Strategic Assurance Framework (SAF). This is set out in Section 6 of the report. 2.5 As a general rule of thumb, where a budget is showing a year to-date (YTD) variance, but is not forecasting a variance at year end, this should indicate that the timing of actual expenditure within the year has not matched to what was expected when the budget was profiled at the start of the year but that this will even out and there will not be an overall over- or under-spend at the end of the year.
3. Revenue Expenditure Position
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Combined Authority Board at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.