Cambridgeshire and Peterborough Combined Authority
Combined Authority Board, Wednesday 18 March 2026 at 10.00am

Q3 2025/26 Budget Monitoring Report - KD2025/023

Noted Committee 4 papers

AI summaryCombined Authority Board noted Q3 2025/26 financial performance and approved carry-forwards of £4.433m revenue and £10.966m capital from 2025/26 into 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRevenue £4.433m and capital £10.966m moved into 2026/27
Money£4.433m revenue, £10.966m capitalPlus £3.127m revenue and £8.235m capital subject to approval
What happens nextOutturn report at June BoardFinal variances after year-end closure on 3 June 2026
Who it affectsCombined Authority programmes and partnersSkills Bootcamps, transport schemes, energy projects affected

What was decided

The Board noted the financial performance of the Combined Authority based on actual expenditure as at 31 December 2025, against approved revenue and capital budgets. Report P1, 3.1, 4.1

The Board approved provisional carry-forward of £4.433m of approved revenue budgets and £3.127m of subject to approval revenue budgets from 2025/26 into 2026/27. Report P1, 3.1

The Board approved provisional carry-forward of £10.966m of approved capital budgets and £8.235m of subject to approval capital budgets from 2025/26 into 2026/27. Report P1, 4.1

Why

Officers identified projects and programmes with budget in 2025/26 that will not be spent by the end of March, and asked the Board to carry the funds forward so delivery can continue without a funding gap between year-end and the next Board meeting on 3rd June 2026. Report 1.1, 3.1, 4.1

Revenue forecast underspend of £10.424m is driven by Skills Bootcamp Wave 5 (£1.823m), Wave 6 (£2.038m), AEB Innovation Fund (£0.610m), Connect to Work (£0.438m), UK Shared Prosperity Fund (£0.651m), and slippage on Active Travel revenue (£1.112m). Report 3.1

Capital forecast underspend of £12.167m, down from £29.945m at quarter 2, is largely from Strategic Transport (£10.438m) covering Fletton Quays Footbridge, Active Travel schemes, A141 & St Ives, and March Junction Improvements, plus the HUG2 Energy Hub (£1.473m). Report 4.1

What happens next

Officers will produce a final outturn report with material variance explanations following the year-end closure and accruals process, due to the Board on 3rd June 2026. Report 3.1, 4.1

Projects requesting slippage will be required to reprofile budgets across the project lifetime, with whole-lifetime budgets included in the June outturn report and any material delivery changes brought forward through the Strategic Assurance Framework change control process. Report 4.1

The Department for Education has confirmed at least £15m for skills capital projects to 2029/30, of which £12.5m was received in February; the balance will be reflected in the outturn once funding notifications arrive. Report 5.1, 5.2

The money

  • £4.433m Provisional carry-forward of approved revenue budgets from 2025/26 into 2026/27 Report 3.1
  • £3.127m Subject to approval revenue budgets to be carried forward into 2026/27 Report 3.1
  • £10.966m Provisional carry-forward of approved capital budgets from 2025/26 into 2026/27 Report 4.1
  • £8.235m Subject to approval capital budgets to be carried forward into 2026/27 Report 4.1
  • £10.424m Total revenue forecast underspend for 2025/26 Report 3.1
  • £12.167m Total capital forecast underspend for 2025/26, down from £29.945m at quarter 2 Report 4.1
  • £14.305m Year to date revenue underspend against profiled budget as at 31 December 2025 Report 3.1
  • £3.618m Year to date capital variance against budget as at 31 December 2025 Report 4.1
  • £10.438m Strategic Transport capital underspend, including Fletton Quays Footbridge £3.674m, Active Travel Schemes £3.288m, A141 & St Ives £2.280m, March Junction Improvements £0.559m Report 4.1
  • £1.432m Forecast drawdown on reserves to fund passenger transport services in 2025/26, down from £2.957m approved in the 25-26 Medium-Term Financial Plan Report 3.1

Options considered

  • Chosen: Note the Q3 financial performance and approve the carry-forward requests (as recommended by officers). Allows continued delivery of in-flight projects between year-end and the next Board meeting on 3rd June 2026 without a funding gap Report P1, 3.1, 4.1

Implications

  • Financial: The Combined Authority must prepare a balanced budget under the Cambridgeshire and Peterborough Combined Authority Order 2017 and Combined Authorities Financial Order 2017; this report monitors performance against the financial targets set in January 2025 through the budget setting process. Report P30, P31
  • Financial: Skills Bootcamp Wave 5 has reduced grant income by £1.363m and Wave 6 by £2.038m linked to programme underspends, with a further in-year UK SPF shortfall of £0.803m as funds slip into 2026/27. Report 5.1, 5.2
  • Financial: Treasury income is forecast to increase by £1.066m due to higher cash balances and interest rates not falling as quickly as expected. Report 5.1, 5.2
  • Risk: Officers flag an increasing risk of Local Net Zero Accelerator spend slipping into 2026/27 beyond the c£3.4m currently discussed with DESNZ, although an extended project end-date of September 2026 has been agreed with no funding cliff-edge. Report 3.1
  • Equalities: A number of projects in delivery or planned have direct Public Health benefits, and others have direct Environmental and Climate Change benefits. Report P30, P31
  • Other: There are no direct financial implications in the report itself, and no other significant implications identified by officers. Report P31

Who and where

  • Combined Authority programmes and project delivery teams across Economy and Growth and Place and Connectivity Report 3.1, 4.1
  • Department for Energy Security and Net Zero (DESNZ) in respect of the Local Net Zero Accelerator extension to September 2026 Report 3.1
  • Department for Science, Innovation and Technology (DSIT) for the Regulator Pioneers Fund Round 4 and Regulatory Platform Pilot reprofile Report 6.1, 6.2, 6.5
  • Department for Work and Pensions (DWP) regarding the Connect to Work procurement delay Report 3.1
  • MHCLG regarding UK Shared Prosperity Fund and an Expression of Interest for early payment of Spatial Development Strategy funding Report 3.1, 5.1, 5.2
  • Fenland District Council, which will fund the budget shortfall for the Fenland Civil Parking Enforcement project Report 6.1, 6.2, 6.8
  • Cambridge Regional College, whose Further Education Cold Spots projects have revised scopes and delivery dates Report 6.1, 6.2, 6.13

Timeline

  • 31st December 2025: Year to date actuals measured for the Q3 budget monitoring report Report 1.1, 3.1
  • 5th January (Funding Committee): Last Funding Committee meeting before this report; only officer decisions since Report 6.1, 6.2
  • February (received): £12.5m of the £15m Department for Education skills capital funding received, not reflected in December actuals Report 5.1, 5.2
  • Before end of March 2026: Anticipated initial funding from MHCLG for the Spatial Development Strategy if the Expression of Interest is successful Report 5.1, 5.2
  • 18 March 2026: Combined Authority Board meeting at which the Q3 carry-forward decisions were taken
  • 3rd June 2026: Next Combined Authority Board meeting; final outturn report and material variance explanations to be provided Report 3.1, 4.1
  • September 2026: Extended end-date agreed with DESNZ for the Local Net Zero Accelerator programme Report 3.1

Plain English for the jargon

  • MTFP: Medium-Term Financial Plan, the multi-year budget approved in January 2026
  • SAF: Strategic Assurance Framework, the process for approving business cases and changes
  • STA: Subject to Approval budgets allocated to projects pending a business case
  • HUG2: Home Upgrade Grant phase 2, an energy efficiency retrofit programme
  • GSE Net Zero Hub: Greater South East Net Zero Hub, a regional programme run by the Combined Authority
  • AEB: Adult Education Budget
  • UK SPF: UK Shared Prosperity Fund
  • LEVI: Local Electric Vehicle Infrastructure funding from the Department for Transport
  • DESNZ: Department for Energy Security and Net Zero
  • DSIT: Department for Science, Innovation and Technology
  • MHCLG: Ministry of Housing, Communities and Local Government
  • DWP: Department for Work and Pensions
  • YTD: Year to date financial position as at 31 December 2025
  • GFA: Grant Funding Agreement, the formal contract for funded projects
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

It was resolved to: A Note the financial performance of the Combined Authority based on the actual expenditure as at 31 December 2025. B Approve the provisional carry-forward requests from 2025/26 into 2026/27 as set out in paragraphs 3.8 and 4.10.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Combined Authority Board

Recommendations

A To note the financial performance of the Combined Authority based on the actual expenditure as at 31 December 2025. B Approve the provisional carry-forward requests from 2025/26 into 2026/27 as set out in paragraphs 3.8 and 4.10.

Strategic Objective(s):

☒ Growth ☒ Jobs ☒ Resilience

☒ Connectivity ☒ Homes ☒ Performance

The proposals within this report impact on all of the Combined Authority’s strategic objectives as understanding the budget available for 2025/26 and the current forecasts against it allows the continuation of the delivery of the Authority’s programmes in an efficient manner, and within its means.

1. Purpose

1.1This report provides the Board with an update on the income and expenditure received to the end of December 2025 and forecasts of financial performance to the end of the financial year 2025/26. 1.2 Alongside forecasts Officers have also identified where projects and programmes have budget within 2025/26 which will not be spent by the end of March and have requested these funds be carried forward into 2026/27 to allow the continued delivery of these projects.

2. Budget Update

2.1This report presents the year to-date actual expenditure and associated budgets along with the full year budgets and outturn forecasts for the 2025/26 financial year. 2.2 The figures presented in the body of the report and Appendix 1 show the spend against those budgets which have been approved to spend by the Board, or relevant Committee, and are thus being actively delivered against, Appendix 2 sets out the project budgets which have been allocated subject to business case approval and shown as “Subject to Approval”. 2.3 Budgets have been updated to align with MTFP approved in January and other decisions taken since then which has had the impact of removing or reducing some forecast variances previously reported. Further detail is contained in the report. 2.4 The materiality threshold above which changes in outturn expenditure forecasts for the year are required to provide a specific explanation within Appendix 3 are £200k for all revenue budgets and £500k for capital projects. 2.5 The budget update report also includes a summary of the position against the thematic funds and reports the investment decisions approved by the Chief Executive and Funding Committee as part of the delegated authority provided through the Strategic Assurance Framework (SAF). This is set out in Section 6 of the report. 2.6 As a general rule of thumb, where a budget is showing a year to-date (YTD) variance, but is not forecasting a variance at year end, this should indicate that the timing of actual expenditure within the year has not matched to what was expected when the budget was profiled at the start of the year but that this will even out and there will not be an overall over- or under-spend at the end of the year.

3. Revenue Expenditure Position

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Detailed BudgetsAppendix 1 289 KB Download
PDF
STA BudgetsAppendix 2 78 KB Download
PDF
Material Variance ExplanationsAppendix 3 84 KB Download
PDF
Q3 2025/26 Budget Monitoring Report: KD2025/023Report 322 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 21 attended
PB
Paul Bristow Cambridgeshire and Peterborough Combined AuthorityChair, present
AB
Councillor Anna Bailey East Cambridgeshire District CouncilCommittee Member, present
CB
Councillor Chris Boden Fenland District CouncilCommittee Member, present
SC
Councillor Sarah Conboy Huntingdonshire District CouncilCommittee Member, present
LN
Councillor Lucy Nethsingha Cambridgeshire County CouncilCommittee Member, present
SQ
Councillor Shabina Qayyum Peterborough City CouncilCommittee Member, present
AS
Councillor Anna Smith Cambridge City CouncilCommittee Member, apologies, sent representative
BS
Councillor Bridget Smith South Cambridgeshire District CouncilCommittee Member, present
DP
Darryl Preston Police and Crime CommissionerCo-Optee, present
RP
Robin Porter Central East Integrated Care BoardCo-Optee, present
CM
Councillor Christopher Morris Cambridgeshire and Peterborough Fire AuthorityCo-Optee, apologies
JH
Councillor Julia Huffer East Cambridgeshire District CouncilSubstitute

All 21 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Q3 2025/26 Budget Monitoring Report - KD2025/023This decision
  2. Draft Outturn Budget Monitoring Report 2025/26 [KD2026/034]Noted
  3. Q2 2025/26 Budget Monitoring Report - KD2025/019Noted
  4. Q1 2025/26 Budget Monitoring Report - KD2025/018Noted
  5. Outturn Budget Monitoring Report - KD2025/017Noted
  6. Budget Monitoring Update Report 2024/25 - end of Quarter 3 and 2025/26 Financial StrategiesNoted

More from Cambridgeshire and Peterborough Combined Authority Combined Authority Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti... Approved Open
23 Sep 2026 Public QuestionsOne public question was received. The question is published . Decided Open
23 Sep 2026 Forward PlanIt was resolved to : A Approve the Forward Plan for September 2026 Approved Open
23 Sep 2026 CPCA Meetings CalendarIt was resolved to : A Approve the proposed amendments to the calendar of meetings for the 2026/27 Municipal Year B A... Approved Open
23 Sep 2026 Updates to the ConstitutionIt was resolved to : A Approve the changes to the Constitution as proposed in Sections 4 and 5 of the report and asso... Approved Open