Update on Development Work for a Spatial Development Strategy (SDS)
NotedCommittee1 paper
AI summaryCambridgeshire and Peterborough Combined Authority Growth Committee noted progress on the Spatial Development Strategy and the MHCLG consultation response, with £585k in current funding deemed insufficient for full delivery.
Written from the decision and the officer reportPDF Pro
OutcomeNotedNoted SDS work and NPPF consultation response
Money£585k in current MTFPCurrent funding for spatial planning, deemed insufficient
What happens nextWorkshops in March, June reviewPlace Directors 9 March, Committee 16 March, June Statement of Intent
Who it affectsCambridgeshire and PeterboroughSpatial planning for the combined authority area
What was decided
The Committee noted progress in Spatial Development Strategy work being undertaken by the Combined Authority in responding to the Planning & Infrastructure Act. Report P1
The Committee noted submission of the response to the MHCLG consultation on the Draft National Planning Policy Framework, in line with recommendations of the January Committee. Report P1
Why
The Planning & Infrastructure Act received Royal Assent in December 2025 and, once commenced, will place a duty on the Combined Authority to prepare a Spatial Development Strategy to support sustainable growth. Report 3.1, P21
The Combined Authority's Corporate Strategy 2025-29 sets an objective to adopt a Spatial Development Strategy to shape growth, future planning policies and support the Local Growth Plan. Report P5
The current Medium Term Financial Plan includes £585k for spatial planning, which is insufficient to progress the SDS through all required stages to adoption, and discussions with MHCLG on further funding are ongoing. Report P11, P21
What happens next
Workshops are arranged for Place Directors on 9 March and for Growth Committee members on 16 March, facilitated by Catriona Riddell, to inform a Statement of Intent. Report P14
The June Committee cycle will consider the Statement of Intent and progress on the revised evidence base. Report P14
The September Committee cycle will, subject to Regulations being confirmed, agree the SDS timetable and its submission to Government; formal SDS preparation stages are assumed to commence from Autumn 2026. Report P14, 2.1
The money
£585k Current MTFP funding for spatial planning, described as insufficient to progress the SDS through all required stages to adoption. Report P11
Options considered
Chosen: Note progress on SDS work and the NPPF consultation response (as recommended by officers).. Standard update to keep the Committee informed of work responding to the Planning & Infrastructure Act 2025. Report P1
Implications
Financial: Current £585k MTFP funding is insufficient for full SDS delivery; an s.31 Grant from MHCLG may be made in March 2026 as an early part of an overall payment, with further tranches subject to MHCLG monitoring. Report P11, P21
Legal: The SDS provisions in the Planning & Infrastructure Act 2025 are now law and are mandatory for strategic planning authorities; formal commencement (expected around June 2026) awaits secondary legislation, and commissioning technical advice will require legal and procurement activity. Report 3.1, P21
Equalities: The SDS has the potential to address longstanding spatial and structural health inequalities, with health and equity considerations to be embedded in development, consultation and delivery, aligned with Public Sector Equality Duty obligations. Report P22
Climate: The Act requires that the SDS is designed so that land use and development contribute to mitigation of, and adaptation to, climate change, integrating climate and environmental goals with housing, economy and infrastructure planning. Report P23
Risk: Without additional MHCLG funding the Combined Authority cannot take the SDS through all required stages to adoption, and the ALIGN modelling tool may not be available until the end of the year. Report P11, P18
Who and where
Residents and communities across the Cambridgeshire and Peterborough Combined Authority area Report P5, P22
Constituent councils and local planning authorities within the Combined Authority Report P5, 3.7
Strategic planning authorities more widely (subject to the new statutory duty) Report 3.1, P21
MHCLG, NISTA and the proposed Greater Cambridge Development Corporation as partner bodies Report P11, 3.7, P18
Timeline
December 2025: Planning & Infrastructure Act received Royal Assent. Report 3.1
4 February 2026: MHCLG published the consultation on establishing a Greater Cambridge Development Corporation.
9 March 2026: Place Directors workshop on SDS requirements and opportunities. Report P14
10 March 2026: NPPF consultation closes.
11 March 2026: Growth Committee meeting considers this update.
16 March 2026: Workshop for Growth Committee members on SDS requirements and opportunities. Report P14
1 April 2026: Greater Cambridge Development Corporation consultation closes.
Probably June 2026: Formal commencement of the SDS powers in the Planning & Infrastructure Act, subject to secondary legislation. Report 3.1, P21
Autumn 2026: Working assumption for commencement of formal SDS preparation stages. Report 2.1
June Committee cycle: Consideration of the Statement of Intent and revised evidence base progress. Report P14
September Committee cycle: Agreement of SDS timetable and submission to Government, subject to Regulations. Report P14
Up to March 2029: Period over which MHCLG has indicated it is working to confirm an SDS funding package. Report P11
Plain English for the jargon
SDS: Spatial Development Strategy, a statutory long-term spatial plan that the Combined Authority will be required to prepare under the Planning & Infrastructure Act 2025.
NPPF: National Planning Policy Framework, the government planning policy framework now subject to a revised draft consultation.
MHCLG: Ministry of Housing, Communities and Local Government, the UK government department leading on planning reforms.
CPCA: Cambridgeshire and Peterborough Combined Authority.
MTFP: Medium Term Financial Plan, the council's multi-year budget document.
NISTA: National Infrastructure and Service Transformation Authority, body developing the ALIGN spatial modelling tool.
ALIGN: Spatial modelling tool combining spatial, economic, demographic, infrastructure and environmental datasets to test growth and infrastructure scenarios.
PSED: Public Sector Equality Duty, the legal duty to consider equality in policy and decision-making.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
A. To note progress in Spatial Development Strategy work being undertaken by the Combined Authority in responding to the Planning & Infrastructure Act. B. To note submission of the response to the MHCLG consultation on the Draft National Planning Policy Framework in line with the recommendations of the January Committee A. To note progress in Spatial Development Strategy work being undertaken by the Combined Authority in responding to the Planning & Infrastructure Act. B. To note submission of the response to the MHCLG consultation on the Draft National Planning Policy Framework in line with the recommendations of the January Committee
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A To note progress in Spatial Development Strategy work being undertaken by the Combined Authority in responding to the Planning & Infrastructure Act. B To note submission of the response to the MHCLG consultation on the Draft National Planning Policy Framework in line with the recommendations of the January Committee
Strategic Objective(s):
The proposals within this report fit under the following strategic objective(s):
☒ Growth ☒ Jobs ☒ Resilience
☒ Connectivity ☒ Homes ☐ Performance Development of an SDS aligns strongly with the Combined Authority’s strategic objectives. The CPCA’s Corporate Strategy 2025-29 sets an objective to adopt a Spatial Development Strategy to shape growth, future planning policies and support delivery of Local Growth Plan priorities. It will be a key tool through which the CPCA can positively drive delivery of the Local Growth Plan, playing an important integration role to ensure that spatial investment and infrastructure investment decisions to fully reflect wider economic, environment, health, climate and infrastructure priorities, building investor certainty and reducing risks.
1. Purpose
1.1The purpose of this report is to update members on progress with Spatial Development Strategy work being undertaken by the Combined Authority in responding to the Planning & Infrastructure Act 2025. 2. Proposal
2.1This report updates the Growth Committee on development work underway in preparation for formal commencement of a statutory long-term spatial strategy for Cambridgeshire & Peterborough. In discussion with Government, our working assumption is that the CPCA's timetable for the formal stages of SDS preparation will commence from Autumn 2026, once the enabling secondary legislation is in place.
2.2This report also updates on the Combined Authority's response to the MHCLG consultation on the revised draft National Planning Policy Framework (NPPF), the latest government funding position, and the Cambridge Development Corporation consultation.
Background
3.1The January 2026 Growth Committee paper noted that the Planning and Infrastructure Act (“the Act”) received Royal Assent in December 2025, with commencement powers to follow, probably in June 2026. The Act, when the powers are commenced, will place a duty on CPCA to prepare a Spatial Development Strategy (SDS) to support the delivery of sustainable growth. Preparatory work is being undertaken by the Combined Authority to respond to the Act, including responding to proposed reforms to the National Planning Policy Framework, which sets out how SDS will form part of the development plan system. The Government have also issued, for consultation, proposals for establishing a development corporation in Greater Cambridge.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting held on 23 June 2026 were approved as an accurate record. The Action Log was noted by the ...
Regional Energy Governance Proposals(Unanimous) A. To recommend to the Combined Authority Board to agree the proposal for the CPCA Area Energy Governance...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.