Resilience Plan

Noted Committee 1 paper

AI summaryCambridgeshire and Peterborough Growth Committee noted proposals for a two-phase Resilience Plan. Phase 1, due June 2026, will focus on short-term water-related risks; Phase 2 will cover longer-term risks to 2050.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedTwo-phase plan: Phase 1 short term, Phase 2 to 2050
MoneyMTFP allocates revenue and capital to Resilience objective, no figure given
What happens nextFinal draft Phase 1 by 11 June 2026CA Board approval scheduled 15 July 2026
Who it affectsRegion's residents, infrastructure and authoritiesWater, energy, biodiversity, emergency planning partners

What was decided

The Committee noted the proposal, scope and timescales for producing a Resilience Plan covering the Combined Authority area. Report P1

The Plan will be developed in two phases, with Phase 1 focused on immediate, mainly water-related risks over the next five years. Report 2.4

Phase 2 will address the wider range of regional risks and run to 2050, aligned to the Local Growth Plan. Report 2.10

Why

Resilience is one of six Corporate Plan objectives, linked to delivering the Local Growth Plan and the Mayor's Manifesto commitment to improve resilience and protect the countryside. Report P5, 3.1, 3.2

Climate change, growth in demand and ageing infrastructure are affecting water supply, wastewater treatment and flood risk, requiring coordinated regional action. Report 2.4

The Combined Authority sees a leadership and convening role where lack of resilience could affect Corporate Plan delivery or cause system-wide cascade effects. Report 2.6, 2.7

What happens next

A Place Directors steering group will guide the work, using existing data and stakeholder input. Report 2.8, 2.9

Project team and resources to be agreed by March 2026, with priorities identified between April and May 2026. Report 2.9

Final draft Phase 1 Plan to be presented to Growth Committee on 23 June 2026, with Combined Authority Board approval on 15 July 2026. Report 2.9

Options considered

  • Chosen: Develop the Resilience Plan in two phases. Allows focus on urgent water-related risks first, then longer-term risks to 2050 Report 2.4, 2.10

Implications

  • Financial: The Medium Term Financial Plan has allocated revenue and capital to the Resilience objective, to be deployed once the Plan identifies priorities; additional capacity will need to be procured. Report P24
  • Legal: The Civil Contingencies Act 2024 provides the framework, placing duties on organisations to assess risks and prepare emergency plans; consultancy support will be procured. Report P24
  • Climate: Phase 1 will draw on water, flood and climate evidence; energy is being addressed through the Local Area Energy Plan and biodiversity through the Local Nature Recovery Strategy. Report 2.4, P24
  • Other: Public health: resilience to external events and impacts will protect and enhance public health. Report P24

Who and where

  • Residents and communities across Cambridgeshire and Peterborough Report 2.1, 2.2, 3.1
  • Constituent local authorities of the Combined Authority Report 2.5, 2.6
  • Critical infrastructure providers, including water and energy Report 2.4, 2.6
  • Cambridgeshire and Peterborough Local Resilience Forum Report 2.5, 3.3
  • Other regional partners and stakeholders feeding into evidence and delivery Report 2.1, 2.5, 2.8

Timeline

  • March 2026: Project team and resources agreed Report 2.9
  • April 2026: Map existing information and data to support the Plan Report 2.9
  • April to May 2026: Identify priorities for inclusion in Resilience Plan Report 2.9
  • June 2026: Potential Growth Committee briefing Report 2.9
  • 11 June 2026: Final Draft Resilience Plan Phase 1 Report 2.9
  • 23 June 2026: Growth Committee agreement on Phase 1 Report 2.9
  • 15 July 2026: Combined Authority Board approval of Phase 1 Report 2.9
  • By 2050: Phase 2 longer-term Resilience Plan to align with Local Growth Plan timescales Report 2.10

Plain English for the jargon

  • Combined Authority Board: The governing body of Cambridgeshire and Peterborough Combined Authority that approves major decisions.
  • Local Resilience Forum: A multi-agency partnership that prepares for and responds to local emergencies and extreme weather.
  • MTFP: Medium Term Financial Plan, the council's multi-year budget framework.
  • Local Growth Plan: The Combined Authority's plan setting out regional growth ambitions and priorities.
  • Local Area Energy Plan: A plan setting out local energy supply and decarbonisation priorities for the area.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

A. To note the proposal, scope and timescales for the production of the . A. To note the proposal, scope and timescales for the production of the .
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Growth Committee

Recommendations

A To recommend that the Committee, subject to its feedback/comments, note the proposal, scope and timescales for the production of the Resilience Plan.

Strategic Objectives:

The proposals within this report fit under the following strategic objective(s):

☒ Growth ☐ Jobs ☒ Resilience

☐ Connectivity ☒ Homes ☐ Performance Resilience is one of the six Corporate Plan Objectives. Development of a Resilience Plan is strongly linked to our economic growth ambitions and will identify how the region manages risks

1. Purpose

1.1The purpose of this paper is to update on the proposals to develop a Resilience Plan and its timescales.

2. Proposal

2.1As defined in the Corporate Plan (see para 3.3 below) a Resilience Plan will help identify and mitigate the strategic risks to ensure the region is prepared and enable growth to help deliver our ambitions as set out in the Local Growth Plan. There are a range of organisations across the region addressing these risks and this plan will look to identify roles and responsibilities, where we can work together, add value and the resources and investment required in the short, medium and longer term.

2.2A Cambridgeshire and Peterborough Resilience Plan should aim to improve the resilience of the area to the challenges that are already occurring as well as addressing the future risks, ensuring this considers the ambitions set out in the Local Growth Plan to unlock the potential of this region and make future development resilient. 2.3 It is proposed to develop the Resilience Plan in two phases: • Phase 1 will develop a plan by June 2026 that will include current challenges and anticipated risks that need intervention in the short term (next 5 years). This will ensure the area has a delivery plan that will identify the priorities, resources and investment needed to drive forward the actions of the region in the short term. This will utilise existing data and evidence including input from stakeholders and partners. • Phase 2 will develop a longer-term plan to 2050, to align with the Local Growth Plan timescales. This will set out the short-, medium- and long-term priorities for this region. Timing will be dependent on the scope of this work and if additional evidence would need to be commissioned.

2.4Phase 1 will concentrate on the most pressing resilience risks that require immediate or short-term responses. Based on the evidence to date, this would require a focus on water-related issues. The impact of the changing climate, growth in demand and ageing infrastructure is affecting the resilience of public water supply, waste water treatment, non-domestic water supply, and flood risk. The Phase 1 plan will particularly draw upon the evidence-base already developed that has informed the Regional Water Plan and emerging Local Plans. It will scope the need for any bespoke studies to address water- related resilience issues across the Combined Authority area, and/or water catchments that have a different boundary (such as the Great Ouse where major developments are also proposed from Milton Keynes through Bedfordshire into Cambridgeshire). Availability and security of energy is being addressed through the Local Area Energy Plan workstream (and the revisions to regional energy planning processes). Similarly, biodiversity risks and nature impacts are being addressed through the Local Nature Recovery Strategy.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Resilience PlanReport 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 19 attended
SC
Councillor Sarah Conboy Mayor's RepresentativeChair, present
LD
Councillor Lara Davenport-Ray Huntingdonshire District CouncilVice-Chair, present
RM
Councillor Rosy Moore Cambridge City CouncilCommittee Member, present
RH
Councillor Ros Hathorn Cambridgeshire County CouncilCommittee Member, present
MG
Councillor Martin Goodearl East Cambridgeshire District CouncilCommittee Member, present
ST
Councillor Steve Tierney Fenland District CouncilCommittee Member, present
MF
Councillor Mohammed Farooq Peterborough City CouncilCommittee Member, present
NW
Councillor Natalie Warren-Green South Cambridgeshire District CouncilCommittee Member, present
EG
Emma Garfield Business BoardCo-Optee, present
TJ
Tim Jones Business BoardCo-Optee, expected
MC
Councillor Martin Cahn Overview and Scrutiny Committee RapporteurGuest, expected
MD
Councillor Mike Davey Overview and Scrutiny Committee GuestGuest, expected

All 19 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Resilience PlanThis decision
  2. Resilience Plan Phase 2 UpdateDecided
  3. Water Resilience PlanNoted
  4. Developing The Resilience PlanNoted

More from Cambridgeshire and Peterborough Combined Authority Growth Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of the previous meetingThe minutes of the meeting held on 23 June 2026 were approved as an accurate record. The Action Log was noted by the ... Approved Open
15 Sep 2026 Director's Highlight ReportTo note the content of the report. Noted Open
15 Sep 2026 Regional Energy Governance Proposals(Unanimous) A. To recommend to the Combined Authority Board to agree the proposal for the CPCA Area Energy Governance... Agreed Open
15 Sep 2026 Sage Novation on properties at Wisbech Road, March(Unanimous) A. To recommend to the CA Board to agree to a novation requested by Sage Homes Limited to transfer all th... Agreed Open
15 Sep 2026 Regional Visitor Economy Branding and NarrativeA. To review and endorse the regional destination brand and narrative, developed in partnership with industry and loc... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies