AI summaryCambridgeshire and Peterborough Combined Authority's Growth Committee noted the Place Division's Q3 2025/26 position, including a £435k revenue underspend and £740k capital underspend.
Written from the decision and the officer reportPDF Pro
OutcomeNotedQ3 2025/26 Place Division update
Money£435k and £740k underspendsRevenue £435k and capital £740k expected
What happens nextSlippage into 2026/27£413k deferred, extension to March 2027
Who it affectsPlace Division budgetResilience, Net Zero and climate lines
What was decided
The committee noted the Place Division's financial position for 2025/26 to the end of the third quarter, December 2025. Report P1
Why
Financial reporting is carried out for each quarter; this is the Q3 update covering the period ending December 2025. Report 1.1, 2.1
What happens next
Around £413k of resilience revenue funding will move into 2026/27, including work on the Resilience Plan, Local Area Energy Plan and Local Nature Recovery Strategy delivery plan. Report 3.3
A project change request to extend the Nature Investment Fund to 31 March 2027 and move funding into 2026/27 is being considered. Report 4.2
The money
£435k expected revenue underspend at year end in Resilience lines Report 3.3
£413k resilience revenue expected to slip into next financial year Report 3.3
£40,000 Local Area Energy Plan funding moving into 2026/27 Report 3.3
£90,000 Local Nature Recovery Strategy funding for delivery plan commissioning Report 3.3
£740k expected capital underspend at year end in Climate lines Report 4.2, P20
£50k Climate capital deferred Report 4.2, P20
£92,000 Climate Programme Bidding Fund underspend expected Report 4.2
£84,000 Huntingdonshire Biodiversity for all capital underspend Report 4.2
Options considered
Chosen: Note the Q3 financial position of the Place Division. Quarterly reporting requirement Report P1, 2.1
Implications
Financial: Revenue underspend of £435k and capital underspend of £740k expected at year end; no other financial implications beyond the report. Report 3.3, 4.2, P25
Legal: The Combined Authority is required to prepare a balanced budget in accordance with statutory requirements.
Other: Public health, environmental and climate change, and other significant implications marked as N/A.
Who and where
Place Division, including Resilience, Net Zero Hub and Climate programmes Report P5, 3.2, 4.1
Cambridgeshire and Peterborough Combined Authority budget Report 3.5, 4.4
Partners and project beneficiaries of biodiversity, climate and energy schemes (funding reprofiling affects delivery timing) Report 3.3, 4.2
Timeline
30 September 2025: Climate capital expenditure reporting cut-off Report 4.1
31 October 2025: Huntingdonshire Biodiversity for all project completed Report 4.2
2026/27: Resilience Plan, Local Area Energy Plan and Nature Investment Fund funding proposed to be used or moved into this year Report 3.3, 4.2
period ending December 2025: Q3 financial position reported Report 1.1, 2.1
31 December 2025: Place income, Resilience revenue and Net Zero revenue reporting cut-off Report 3.1, 3.2
31 March 2027: Proposed new end date for the Nature Investment Fund under a change request Report 4.2
Plain English for the jargon
Place Division: The part of the Combined Authority covering growth, resilience, climate and net zero activity reported to this committee.
CPCA: Cambridgeshire and Peterborough Combined Authority.
FO Variance: Forecast Outturn Variance, the change from the original full year budget to the latest forecast outturn.
YTD: Year to Date, spending or income from the start of the financial year to the reporting date.
GSENZ Hub: Greater South East Net Zero Hub, a government-funded regional net zero support programme.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
A. To note the financial position of the Place Division for the financial year 25/26 to the end of the third quarter, December 2025 A. To note the financial position of the Place Division for the financial year 25/26 to the end of the third quarter, December 2025
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A Note the financial position of the Place Division for the financial year 25/26 to the end of the third quarter, December 2025
Strategic Objectives:
The proposals within this report fit under the following strategic objective(s):
☒ Growth ☐ Jobs ☒ Resilience
☐ Connectivity ☐ Homes ☒ Performance Key activities of the Place Division largely fall under the Corporate Plan objectives of Homes and Resilience, with strong synergies with Growth and Connectivity objectives. This budget reporting is part of the Performance objective
1. Purpose
1.1To provide an update of the financial position for 2025/26 and to provide analysis against the 2025/26 budgets, up to the period ending December 2025
Background
2.1Financial reporting is carried out for each quarter. This report provides an update of the performance against budget up to the period ending December 2025.
3. Revenue Income and Expenditure
3.1A breakdown of the Growth Committee Place income for the period to 31 December 2025 is set out in Table 1 below. Table 1 25/26 25/26 25/26 25/26 25/26 25/26 25/26 Actual Budget Variance Budget FO Variance Deferral -- Growth Committee Place Income YTD YTD YTD FY FY FY £k £k £k £k £k £k £k
Biodiversity Net Gain -27 -27 0 -27 -27 0 0 Local Nature Recovery Strategy -136 -136 0 -136 -136 0 0 Cambridgeshire Constabulary Solar 0 0 0 -700 -700 0 0 Canopy
Total -163 -163 0 -863 -863 0 0
The are no variances to report.
3.2A breakdown of the Revenue Expenditure for the period to 31 December 2025 is set out in Table 2 below. Table 2
25/26 25/26 25/26 25/26 25/26 25/26 25/26 Growth Committee Resilience Actual Budget Variance Budget FO Variance Deferral Revenue Expenditure YTD YTD YTD FY FY FY £k £k £k £k £k £k £k Constituent Authority Biodiversity 294 294 0 300 279 -21 0 Contribution Biodiversity Net Gain Grant 0 0 0 27 27 0 0 Resilience Plan Development and 6 50 44 380 7 -373 373 Delivery Climate Programme Bidding Round Rev 42 50 8 100 100 0 0 Developing Resilience evidence and 0 0 0 47 47 0 0 data Doubling Nature Metrics 0 0 0 91 91 0 0 Extending the “Retrofitting your Home” 17 5 -12 72 72 0 0 Fenland Soil 60 60 0 60 60 0 0 Future Fens 0 0 0 63 63 0 63 Huntingdonshire Biodiversity for all 3 5 2 5 4 -1 0 Local Area Energy Plan 0 0 0 250 210 -40 40 Local Nature Recovery Strategy 1 0 -1 136 136 0 0 Natural Cambridgeshire 120 120 0 120 120 0 0 Non Statutory Spatial Plan 15 0 -15 444 444 0 0 Sustainable Infrastructure 0 0 0 400 400 0 0 Resilience Total 558 584 26 2,495 2,060 -435 413
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting held on 23 June 2026 were approved as an accurate record. The Action Log was noted by the ...
Regional Energy Governance Proposals(Unanimous) A. To recommend to the Combined Authority Board to agree the proposal for the CPCA Area Energy Governance...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.