AI summaryCambridgeshire and Peterborough Combined Authority Board noted Q3 2025/26 performance: 13 KPIs updated, none rated Red, and progress on the Devolution Deal Gateway Review submitted to government.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedKPIs, programmes and Gateway Review progress
Money£20 million per annumDevolution Deal Investment Fund, over 30 years
What happens nextMid-2026Expected conclusion of Gateway Review by Ministers
Who it affectsCombined Authority regionResidents, businesses, MHCLG
What was decided
The Board noted performance information for 27 Key Performance Indicators in the Interim Outcomes Framework, with 13 updated in Q3 2025/26 and none rated Red. Report P1, 2.1, 3.1, P18
The Board noted performance on Strategic Programmes and Projects, with 1 Red (Cygnet Bridge), 7 Amber and 3 Green, and noted changes to the list of projects. Report P1, 5.1, 5.3
The Board noted progress on evaluating the impact of the Devolution Deal Investment Fund through the second Gateway Review, with the Final Report submitted to MHCLG in December 2025. Report P1, 7.1
Why
The report is presented to strengthen scrutiny and accountability under the English Devolution Accountability Framework, with KPIs linked to the Corporate Plan 2025-2029. Report P5
Of the 13 KPIs updated with new data, 9 met or exceeded targets (7 Blue, 2 Green), 2 were Amber and 1 had no target set, while 0 were Red.
The Cygnet Bridge project is Red due to a longer design assurance process and unforeseen Anglian Water chambers, though revised planning permission is not required and enabling works have commenced. Report 5.3
What happens next
Targets for new KPIs will be developed over the next two quarters, with work to ensure they are meaningful, realistic and aligned with existing plans and strategies.
The second Gateway Review is expected to conclude by mid-2026, with the outcome, Final Report and lessons learned to be shared with the Board following Ministerial confirmation. Report 7.1
The next Corporate Performance Report (Q4 2025/26) will include progress against the new Annual Business Plan using milestones, starting from that report onwards.
The money
£20 million per annum Devolution Deal Investment Fund (Gainshare) over 30 years, subject to 5-yearly Gateway Reviews Report 7.1
Options considered
Chosen: Note Q3 performance information on KPIs, programmes and the Gateway Review. Standard scrutiny and accountability process under EDAF Report P1, P5
Rejected: Assess performance against numerical targets set immediately. Targets for new KPIs are still being developed; direction of travel used instead to avoid arbitrary targets
Implications
Financial: No immediate financial implications from the report itself; future Investment Fund funding depends on a successful Gateway Review outcome. Report 7.1
Legal: No direct legal implications; report is read alongside the Combined Authority's duty under Section 3 of the Local Government Act 1999 to secure continuous improvement.
Equalities: No immediate equality, diversity and inclusion implications from delivering the report.
Climate: No direct environmental or climate change impacts from the report; KPI 23 (nature-rich land) has implications for Thematic Committees and the Board.
Risk: Cygnet Bridge is rated Red due to design assurance delays and unforeseen utility chambers, though enabling works have commenced on the Sand Martin House side. Report 5.3
Who and where
Cambridgeshire and Peterborough Combined Authority Board and Overview and Scrutiny Committee Report P1
Ministry of Housing, Communities and Local Government (MHCLG) and HM Treasury Report 7.1
Residents and businesses across the Cambridgeshire and Peterborough region Report 2.1, P5
Anglian Water, as utility partner on the Cygnet Bridge project Report 5.3
Cambridgeshire Fire and Rescue Service staff in new CPCA-funded posts providing cladding remediation data Report 6.1
Timeline
End of Q3 2025/26 (December 2025): Latest performance data for KPIs and Strategic Programmes and Projects Report 1.1, 2.1, 5.1
December 2025: Final Report on Devolution Deal Gateway Review submitted to MHCLG by consultants SQW Report 7.1
Late February 2026: Challenge Session held with senior Government officials on the Final Report Report 7.1
Mid-2026: Expected conclusion of the second Gateway Review with recommendations to Ministers Report 7.1
Q4 2025/26 report onwards: Annual Business Plan milestone reporting to be introduced
Q4 2025/26: Next performance update expected for most updated KPIs Report P13, P14, P15, P16
Q1 2026/27: KPI 12 (Connect to Work) first update and KPI 21 next update expected Report P14
Plain English for the jargon
IOF: Interim Outcomes Framework, the set of Key Performance Indicators linked to the Corporate Plan 2025-2029, adopted December 2025.
KPI: Key Performance Indicator, a measurable value showing progress against a corporate objective.
RAG: Red, Amber, Green rating system used to flag performance against targets.
Gainshare: The Combined Authority's Devolution Deal Investment Fund, £20 million per year for 30 years.
Gateway Review: Independent five-yearly review of the impact of Devolution Deal investments on local economic growth, carried out for MHCLG.
EDAF: English Devolution Accountability Framework, setting out expectations for scrutiny and accountability.
PMF: Performance Management Framework 2025-2029, adopted December 2025.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
It was resolved to: A Note performance information relating to the Combined Authority’s Key Performance Indicators in the Interim Outcomes Framework (IOF). B Note performance information relating to the Combined Authority’s Strategic Programmes and Projects. C Note progress to evaluate the impact of the Devolution Deal Investment Fund in a Gateway Review.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A Scrutinise performance information relating to the Combined Authority’s Key Performance Indicators in the Interim Outcomes Framework (IOF). B Scrutinise performance information relating to the Combined Authority’s Strategic Programmes and Projects. C Note progress to evaluate the impact of the Devolution Deal Investment Fund in a Gateway Review.
Strategic Objectives:
The proposals within this report fit under the following strategic objective(s):
☒ Growth ☒ Jobs ☒ Resilience
☒ Connectivity ☒ Homes ☒ Performance The performance information presented in this report includes results for Corporate Key Performance Indicators (KPIs) at the end of Q3 2025/26 and is intended to strengthen scrutiny and accountability in line with expectations outlined in the English Devolution Accountability Framework (EDAF). These KPIs are linked to the Corporate Plan 2025-2029’s objectives, as set out in the IOF adopted in December 2025. The authority’s approach to Corporate Performance Reporting is set out in the Performance Management Framework 2025-2029 (PMF), which was also adopted in December 2025.
1. Purpose
1.1Sections 2, 3, 4 and Appendix A present performance information for the Key Performance Indicators (KPIs) in the IOF, drawing on the latest available data at the end of Q3 2025/26. Section 2 introduces a dashboard which groups each KPI under the relevant Corporate Plan objective. The Dashboard is included at Appendix A and sets out the latest results, commentary and actions for all IOF KPIs, alongside graphs showing historic results and trends. Section 3 provides details of KPIs which have been updated with new data or are new KPIs being reported with the latest available data. Section 4 is an exception report focused on KPIs with a Red status where the latest performance is off target by more than 10%. 1.2 An Annual Business Plan has been developed for Q4 2025/26-Q4 2026/27 to provide further detail on the most significant activities contributing to the delivery of each Corporate Plan Strategic Objective and agreed deliverables. In line with the Performance Management Framework, progress on delivering the Annual Business Plan will be reported as part of future quarterly Corporate Performance Reports from the Q4 2025/26 report, using milestones set for each activity to allow actual delivery to be compared against plans. In the interim, progress on key activities is reported in Section 5 and Appendix B, which present performance information on Strategic Programmes and Projects as at the end of December 2025. This provides a Red, Amber, Green rating summary, an exception report and dashboard, for Members’ scrutiny and comment. The dashboard included at Appendix B shows how the Programmes and Projects have progressed, including changes to RAG ratings linked to risks and delivery. 1.3 Feedback from the review of the Q2 report at January’s Overview and Scrutiny Committee recognised that data for new KPIs was being reported for the first time and that reporting should be improved in future cycles. As time series are created, the graphs and commentary will be able to provide greater insight into how performance levels have changed. Members also requested further breakdowns and more granular analysis. An update on development work completed and future plans can be found in section 6. 1.4 Section 7 presents an update on the evaluation of the impact of the Combined Authority’s current Devolution Deal, for Members to note.
Follow Combined Authority Board at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.